LOCATION CONSTRUCTION PROJECT ARCHITECT A/E START GC/CM OPEN SUMMARY STATUSHIGH SCHOOL ADDITIONS AND MODIFICATIONS

North Forsyth H.S. Stadium visitors concession and restroom BRPH Done Charles Black Done Certificate of Occupancy issued 8/14/14Additions & Cafeteria FSF Done Barton Malow Done FM Certificate of Completion issued 5/31/16 , Furniture installedGymnasium FSF Done Barton Malow Done FM Certificate of Occupancy issued 6/24/16Renovations FSF Done Barton Malow Aug-17 In progress

Forsyth Central H.S. Additions CPL Done Parrish Done FM Certificate of Occupancy issued 5/17/16 , Furniture installedRenovations CPL Done Parrish Aug-17 In progress

South Forsyth H.S. Gymnasium MSSA Done Balfour Beatty Done FM Certificate of Occupancy issued 6/2/16Additions & Cafeteria MSSA Done Balfour Beatty Done FM Certificate of Completion issued 6/8/16 , Furniture installedRenovations MSSA Done Balfour Beatty Aug-17 In progress

Lambert H.S. Additions- 19 classrooms , band BRPH Done Charles Black Done FM Certificate of Completion issued 5/27/16, Furniture installedRenovations (Engineering & Health Labs) BRPH Done Charles Black Aug-16 completion scheduled for 7/29/16 Artificial Turf Field (IGA $ , not bond) Breedlove Done Shaw Done

West Forsyth H.S. Additions - Performing Arts (Band,Choral) BRPH Started Cooper & Co Apr-17 Addition grading, site utilities, foundations in progress Renov's (Art,Computer,Engineering Labs) BRPH Started Cooper & Co Aug-17

High School #7 Denmark HS New Construction BRPH Started Barton Malow Jun-18 sitework in progress , foundations to begin 8/8/16Denmark H.S. BRPH Started Barton Malow Jun-18

MIDDLE SCHOOL ADDITIONS AND MODIFICATIONSLiberty M.S. Modify front entrance for security James Buckley Done Done Done Complete

Modifications band ,cafeteria James Buckley Sep-15 Kevin Price Aug-17 Band, Cafeteria renovations to be complete 8/1/16 Expand Band Classroom James Buckley Sep-15 Kevin Price Aug-17 Band Addition to be complete 11/1/16

Little Mill M.S. Modify front entrance for security James Buckley Done Done Done Complete

Modify front drive entranceMcFarland

Dyer Sep-16 Mar-17 Aug-17

North Forsyth M.S. Modify front entrance for security James Buckley Done Done Done CompleteMedia center , band , team room James Buckley Sep-15 Kevin Price Aug-17 Band , Media Renovations to be complete 8/1/16, Adds 11/1/16HVAC replacement / modification CGE Done Capital City Aug-15 HVAC completed

Otwell M.S. Modify front entrance for security James Buckley Done Done Done CompleteExpand engineering lab , band James Buckley Sep-15 Kevin Price Aug-17 Band Renovation to be complete 8/1/16 , Adds 11/1/16

Piney Grove M.S. Modify front entrance for security James Buckley Done Done Done Complete

Front Drive sidewalkMcFarland

Dyer Sep-16 Mar-17 Aug-17 in progress Modify technology lab James Buckley Sep-15 Kevin Price Aug-17 Tech Lab Renovation to be complete 8/1/16

South Forsyth M.S. Modify front entrance for security James Buckley Done Done Done Complete23 Classroom Addition James Buckley Done RaLin Done FM Certificate of Completion issued 5/24/16, Furniture installed

Expand Media Ctr ,Cafeteria, Modify PA James Buckley Done RaLin Aug-16 loop road , pkg lot paved 6/27/16HVAC replacement / modification James Buckley Done RaLin Aug-16

Riverwatch M.S. Modify front entrance for security James Buckley Done Done Done Complete24 Classroom Addition James Buckley Done RaLin Done FM Certificate of Completion issued 5/19/16, Furniture installedExpand band room James Buckley Done RaLin Aug-16 Band Renovation to be complete 8/1/16

Vickery Creek M.S. Modify front entrance for security James Buckley Done Done Done CompleteExpand Media Ctr , Engineering Lab James Buckley Sep-15 Kevin Price Aug-17 Addition foundations in progress HVAC replacement / modification CGE Done Capital City Aug-15 HVAC completed

DeSana MS MS #10 New Construction James Buckley Done Evergreen Done FM Certificate of Occupancy issued 6/15/16 , furniture installed

Middle School #11 MS #11 land purchase search, due dilligence options in progress

ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONSBrandywine ES Brandywine ES New Construction LPBC Done Charles Black Done Certificate of Occupancy issued 6/9/16 , furniture installed

Midway ES Sanitary sewer service CEC Started MidSouth Done Completed 7/12/16Daves Creek HVAC replacement / modification CGE Done Waters Aug-15 HVAC completed Settles Bridge HVAC replacement / modification CGE Done Capital City Aug-15 HVAC completed

General security,media ctr, partitions, parking TBD

South Forsyth Middle School