THE SOUTHERN GATEWAY MANAGED LANES PROJECT

Oak Cliff Chamber of Commerce

September 9, 2015

2

Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental Assessment (EA)

Study limits:

– I-35E from I-20 to 8th St. (8.6 miles)

– US 67 from FM 1382 to I-35E (9.4 miles)

Original Scope:

– Total Reconstruction

– Additional General Purpose (GP) lanes capacity

– Reversible High-Occupancy Vehicle lanes (HOV) in center median

History & Background

The Southern Gateway Managed Lanes Project

3

Finding of No Significant Impact (FONSI) obtained June 30, 2006

In 2013 The Southern Gateway project was granted the authority to be developed as a Public-Private Partnership (P3) project by the 83rd Legislature

In 2014, through collaboration with Federal Highway Administration and North Central Texas Council of Governments, and due to regulatory and anticipated funding constraints, the decision was made to deliver the Southern Gateway as three independent projects

History & Background (cont.)

The Southern Gateway Managed Lanes Project

The Southern Gateway

Corridor

The Southern Gateway’s Four Independent Projects

The Southern Gateway Managed Lanes Project 4

Full Reconstruction of I-35E from US 67 to Colorado Blvd.

HOV transition to Managed Lanes on I-35E from Colorado Blvd. to Reunion Blvd

Managed Lane Implementation on US 67 from I-20 to I-35E and on I-35E South from I-20 to US 67

The Southern Gateway Managed Lanes Project

The Southern Gateway’s Four Independent Projects

5

Full Reconstruction of I-35E from US 67 to Colorado Blvd.

HOV transition to Managed Lanes on I-35E from Colorado Blvd. to Reunion Blvd

Managed Lane Implementation on US 67 from FM I-20 to I-35E and on I-35E South from I-20 to US 67

The Southern Gateway Managed Lanes Project

The Southern Gateway’s Four Independent Projects

6

US 67 General Purpose Widening Project

Widening of US 67 from FM 1382 to I-20

Full Reconstruction of I-35E from US 67 to Colorado Blvd.

HOV transition to Managed Lanes on I-35E from Colorado Blvd. to Reunion Blvd

Managed Lane Implementation on US 67 from FM I-20 to I-35E and on I-35E South from I-20 to US 67

Full Reconstruction of US 67 from FM 1382 to I-35E

The Southern Gateway Managed Lanes Project

US 67 Reconstruction Project

The Southern Gateway’s Four Independent Projects

7

US 67 General Purpose Widening Project

Widening of US 67 from FM 1382 to I-20

Full Reconstruction of I-35E from US 67 to Colorado Blvd.

HOV transition to Managed Lanes on I-35E from Colorado Blvd. to Reunion Blvd

Managed Lane Implementation on US 67 from FM 1382 to I-35E and on I-35E South from I-20 to US 67

Full Reconstruction of I-35E from I-20 to US 67

The Southern Gateway Managed Lanes Project

I-35E South Reconstruction Project

The Southern Gateway’s Four Independent Projects

8

US 67 General Purpose Widening Project

Widening of US 67 from FM 1382 to I-20

Full Reconstruction of US 67 from FM 1382 to I-35E

US 67 Reconstruction Project

9

The objective of this meeting is to present in-progress project information and receive public comment on The Southern Gateway Managed Lanes Project.

We welcome and value your input.

Meeting Objective

The Southern Gateway Managed Lanes Project

10

Purpose and Need of The Southern Gateway Managed Lanes Project

– Increase Capacity

– Reduce Traffic Congestion

– Improve Mobility

– Improve Design Deficiencies

– Improve System Linkage

Purpose and Need

The Southern Gateway Managed Lanes Project

I-35E was designed and built in late 1950s and early 1960s

Design elements that need to be updated to current design standards to

improve safety and freeway operations include:

- Undesirable Shoulder Widths

11

Undesirable Shoulder Widths

Design Deficiencies

The Southern Gateway Managed Lanes Project

12

I-35E was designed and built late 1950s and early 1960s

Design elements that need to be updated to current design standards to

improve safety and freeway operations include:

- Undesirable Shoulder Widths

- Horizontal Curvature

Design Deficiencies

The Southern Gateway Managed Lanes Project

13

Clarendon Drive

I-35E was designed and built late 1950s and early 1960s

Design elements that need to be updated to current design standards to

improve safety and freeway operations include:

- Undesirable Shoulder Widths

- Horizontal Curvature

- Short Ramp and Acceleration/Deceleration Lane Lengths

Design Deficiencies

Inadequate Acceleration Length

Short Ramp Lengths

The Southern Gateway Managed Lanes Project

Typical Sections – The Southern Gateway Managed Lanes Project

I-35E from US 67 to Colorado Blvd.

14 The Southern Gateway Managed Lanes Project

Frontage Roads begin at Beckley/12th St. and are continuous to Colorado Blvd.

Typical Sections – The Southern Gateway Managed Lanes Project

I-35E from I-20 to US 67

15 The Southern Gateway Managed Lanes Project

Typical Sections – The Southern Gateway Widening Project

US 67 from I-20 to I-35E

16 The Southern Gateway Widening Project

Concurrent HOV lanes will be utilized for Reversible Managed Lanes Facility with NB and SB open for AM and PM Peak respectively

Typical Sections – The Southern Gateway Managed Lanes Project

US 67 from FM 1382 to I-20

17 The Southern Gateway Managed Lanes Project

18

Project Refinements based on Stakeholder and Public Input

Since the Summer 2015 Public Meetings – Shifted managed lane access points north to allow access to/from Camp Wisdom Rd.

along I-35E and US 67

– Wider x-street accommodations for pedestrian and bicycle accessibility

– Reconfigured I-35E and Beckley intersection to reduce ROW impacts

– Shifted the managed lane access point along I-35E at Marsalis Ave. to south of Cedar

Creek to reduce ROW impacts

– Additional general purpose lane along I-35E from Marsalis to US 67 and along US 67

from I-35E to FM 1382

– Assessing the feasibility of a deck park or larger bridge connections linking

neighborhoods, City of Dallas facilities (Dallas Zoo), and businesses

– TxDOT CityMAP team to evaluate as part of scenario option development

Current Status – Project Refinements

The Southern Gateway Managed Lanes Project

Current Status

19

The Southern Gateway Managed Lanes Project

– Funding sources identified

– TxDOT coordinating pre-procurement activities for anticipated design-build

project delivery

– Anticipated environmental clearance (FONSI): December 2016

US 67 General Purpose Widening Project from I-20 to FM 1382

– Anticipated environmental clearance (FONSI): December 2016

The Southern Gateway Managed Lanes Project

Note: All dates are subject to change

The Southern Gateway Managed Lanes Project

20

Project Timeline

The Southern Gateway Managed Lanes Project

We are here

Additional Information

21

Project Websites

– www.thesoutherngateway.org

– www.keepitmovingdallas.com

Questions?

The Southern Gateway Managed Lanes Project

top related