THE MANAGEMENT OF TRAFFIC IN
CONSTRUCTION WORK ZONES -The Malaysian Experience-
Ir MOHAMED SHAFII MUSTAFA
INTERNATIONAL SEMINAR AND
WORKSHOPSAFER ROADS BY INFRASTRUCTURE
DESIGN AND OPERATION
INCREASED in accident types:
◼Fixed Object
◼Rear End
◼Head On
DECREASED accident types:
◼ Right Angle
◼ Turning
◼ Ran Off the Road
ALL THESE LEADS TO...
ARAHAN TEKNIK (JALAN)
2C/85
1985In 1985,
the Malaysian Public
Works Dept (PWD)
produced their first
Technical Instruction
on Traffic
Management at Work
Zones
12
ATJ 2C/85 (1985)
- Focussing on Designs of TMP
- Use of Standardised TCDs
- Use of Templates for
Placement of TCDs
- In 2003, added Standard BQ
JKR/SPJ/2017-
S19
19.1
GENERAL
19.2THE EFFECTIVE
IMPLEMENTATION
OF TMWZ
19.3
TEMPORARY
SIGNAGE
19.4
TEMPORARY
ROAD
MARKING
19.5
TRAFFIC
MGMT
EQUIPMENTMATERIALS
SPECIFICATIONS
METHOD OF INSTALLATION
APPLICATION
REQUIREMENT
SPJ
WHAT’S NEW ?
CONTENTATJ 2C/86 PINDAAN
2016
ATJ 2C/86 PINDAAN
2017
General Principles of Traffic Management at Work Zones
Strategies for Effective Implementation
Responsibility
Planning of TMWZ
Designing Principles TMWZ
Typical Layout
Taking Off Quantities
Placement and Removal
Maintenance of Traffic Control Zones
Report Outline (TMP, TMSR)
Temporary Traffic Control Devices
RESPONSIBILITYPLANNING
SITE EXECUTION
MAINTENANCE
REPORTING
The New Manual
Focuses on
- Roles of the Players
- Monitoring and Reporting
- Inspection and Maintenance
TRANSFORMATION
DURING CONSTRUCTION STAGE
➢ TMP Monitored by Management Framework
➢ Contractor sets up TMT & ERT Teams
➢ Contractor designs Localised TCPs
➢ Contractor prepares TMSR
➢ Site Placements/Removals
➢ Maintenance of Work Zones
➢ TMO Daily Inspections
➢ RSA Audit TMP/TMSR
➢ Design Localised TCPs
➢ Sets up TMT & ERT Teams
➢ Maintain Effectiveness of Localised
TCPs
➢ Prepares TMSR
➢ Daily Inspections
Traffic Management Officer (TMO)
➢ Ensure Effective Implementation of
TCPs
➢ Efficient Placement and Removals of
TCDs
➢ Ensure Safety and Smooth Traffic
Flows
➢ Maintain Effectiveness of TCDs
Traffic Management Team (TMT)
➢ Provide 24hr patrol of Work Zones
➢ Provide Traffic Control during
emergency situations
➢ Implement Emergency Response Plan
Emergency Response Team (ERT)
- TMP Masterplan (within 1 month of site possession)
- Traffic Safety Management
Report (every 3 months)
- TMP Audit Report (after every TMSR)
REPORTS
➢ Comprehensive inspection and maintenance program
➢ Inspection procedures
➢ Frequency of Inspection
➢ Documentation
➢ Record Keeping
✓ To carry out routine inspection on all traffic control devices.
✓ Frequency of inspection depends on several factors.
✓ Documentation can be done through Inspection Form.
✓ Record Keeping can be done through Inventory Forms together with Site Diary complete with photos and brief description (date, time, location, etc)
STANDARD DEFINITIONS
TMWZ – Traffic Management at Work Zone
TMP – Traffic Management Plan
TCP – Traffic Control Plan
TCD – Traffic Control Devices
TMO – Traffic Management Officer
WORK ZONE LENGTH
Excavation
• Length < 200m• Nos < 4
Work zone not including
surcharge area
• Length < 5km (rural) • Length < 2km (urban)
CONCLUDING REMARKS
To achieve Safer Environment in Construction Work Zones, we have ...
➢ Shifted FOCUS from Designs to Operations➢ Simplified and Standardise Designs➢ Set up systems for CHECK & BALANCE➢ Set up Monitoring Framework➢ Set up Inspection & Monitoring➢ Introduce frequent Reporting