the construction of the highway over dnipro river in zaporizhia

Post on 09-Jan-2017

101 Views

Category:

Government & Nonprofit

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

The construction of the highway over the Dnipro River in

ZaporizhiaChief administrator of state budget funds: The State Agency of Ukrainian

Automobile Roads “Ukravtodor”

Responsible executor: The Agency of roads in Zaporizhia region

The State Agency of Ukrainian Automobile Roads “Ukravtodor”

Short project descriptionShort project description

Goal: the building of a highway over the Dnipro River in Zaporizhzhia, a total length of 9.1 km.

Project contains 6 traffic junctions and 26 engineering structures:•1 cable-stayed bridge over the Dnipro River with the length of 660 m;•1-frame girder bridge with a total length of 340 meters;•17 reinforced concrete and steel and concrete platforms;•7 overpasses.

.The highway is planned to be constructed in two stages. The first stage of construction involves construction of 4 (four) starting complexes. The first starting complex is already implemented (the installation is completed and the construction of outdoor lighting of road junction №1) and is put into operation. The second starting complex is already implemented, the period of putting into operation is 3 months. The third starting complex is already implemented, the period of putting into operation is 6 months.

 It is planned within the project to build the 4th starting complex of the first stage of construction.

The 5th starting complex of the first construction stage and the second stage of construction of the highway over the Dnipro River ( the completion of construction in general) are not included in the project.

The term of the project: 2017 - 2020 years.The total estimated construction cost of phase I and II after conversion is 7,585 191.18 thousand UAH.

The total cost of the project ( the construction of the 4th starting complex of the I stage of construction): 4 991 318.994 thousand. UAH. (Funds provided from the state budget), including:Work with the adjustment of project documentation etc.: 62 908.000 thousand. UAH .;work of construction: 4928 410.994 thousand. UAH.

The scheme of a highway in Zaporizhzhya over the Dnipro The scheme of a highway in Zaporizhzhya over the Dnipro RiverRiver

Construction readiness of object under construction (I phase of

construction): 65%

Scheme of a highway in. Zaporizhzhia over the Dnipro RiverScheme of a highway in. Zaporizhzhia over the Dnipro River

5

Construction Construction № 1№ 1Implementation of work of the I construction stageImplementation of work of the I construction stage

6

Construction Construction № 2№ 2

7

Road interchange Road interchange № 1№ 1

8

Transport junction Transport junction № 2№ 2

9

Transport junction Transport junction № 3№ 3

10

Construction Construction № 4№ 4

ConstructionConstruction№4.№4.

11

Construction Construction №5№5

12

Construction Construction №6№6

13

Construction Construction №7№7

Construction Construction №9№9

15

Construction Construction №10.№10.PylonPylon

Construction Construction №10.№10.Construction of slant legsConstruction of slant legs

Bridge cables

18

Construction Construction №11,12№11,12

19

Construction Construction №13№13

20

Construction Construction №14№14

21

22

The current situation and problemsThe current situation and problems

The problem of transport communication between the territories of the city of Zaporizhzhia is associated with a particular geographical location, due to its division by the Dnipro River into two parts: the Left Bank and Right Bank and location of the island Khortytsya (almost in the middle between the two parts of the city).Nowadays the traffic between the left and right banks of the Dnipro River in Zaporizhya is provided by two road-rail Preobrazhenskyi bridges, constructed in 1953, with one lane in each direction, as well as on the roadway of the dam of the Dnipro HYES.The current technical condition of Preobrazhensky bridges is in terrible situation. To this day they have never been capitally repaired, affecting the reduction of bearing capacity of bridges and in future it may cause industrial disaster.

The results expected from the projectThe results expected from the project

The project is designed to solve the transport problems of the city of Zaporizhzhia, namely the lack of reliable transport communication between left-bank and right-bank parts of the city and the right bank and left bank of south-eastern parts of Ukraine and solve engineering and communication problems of National Reserve "Khortytsya" considering its status, values and concepts of the island Khortytsya as a reserve.

Proposed for implementation in 2017 construction and repair works on 5 constructions will open traffic direction to the Reserve "Khortytsya" and solve the above-mentioned problem with transport communication.

 

Plan the projectPlan the projectPlanned arrangements

Total funded 01/01/2016

Planfor 2017

(ths. UAH)

Planfor 2018

(ths. UAH)

Planfor 2019

(ths. UAH)

Adjustment of construction documents

Execution of construction work

The diversion of land and compensation for losses to land users

Other activities within the development phase (supervision, maintenance of customer service, scientific support of design work and construction, etc.)

Total funded:

Total (in years):

TOTAL (demand from the State budget):

TOTAL (the cost of the whole project):

The plan of the project in 2017The plan of the project in 2017 

ActivitiesProvided indicators under the state investments project

Planned deadlines Cost (thousand. UAH).

Land allocation, land surveying work  January-December 2017 70,00Design and survey workadjustment of the "Project“ phasedevelopment of working documentation

January-December 2017 13 879,60січень-жовтень 2017 12 879,60

January-December 2017 1 800,00Examination of the adjusted Project phase

листопад-грудень 2017 999,60

Construction worksconstruction of engineering structures:

January-December 2017 89 030,00

Construction number 1 (highway and railroad overpass - exit from Radyanskyi ave, total length of 135 m) January-December 2017 4000,00

Construction number 2 (railroad overpass, total length of 45.2 m) January-December 2017 500,00The construction number 3 (overpass to the construction №4, total length of 289.3 m) January-December 2017 33 010,00

Construction number 4 (girder bridge over the river Old Dnipro, total length of 340.6 m) January-December 2017 28 220,00

The construction number 5 (346.6 m length overpass to the island Khortytsya on contiguity to Construction №4) January-December 2017 23 300,00

SupervisionJanuary-December 2017 120,00

Maintenance of customer service January-December 2017 1 266,36Scientific support of project work and construction January-December 2017 200,00

Total   105 565,56

THANK YOU FOR THE THANK YOU FOR THE ATTENTION!ATTENTION!

Kyiv, 2016

The State Agency of Ukraine roads