Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
This half-yearly report covers the progress of Capital, Alterations, Additions, Repairs and Improvements
(AA&I) as well as major renovation, spatial reorganization and fitting out projects delivered by the
Campus Development Office (CDO) from July to December 2019.
Capital Projects Under Construction and Funding Applications (Appendix A and B)
Under the UGC-funded Hostel Development Plan to construct six new hostels to mitigate the
shortfall in hostel bed places in the past years, foundation works of the new hostel for New Asia College
was in progress during the report period. Consultants were also engaged to commence the detailed design
of two new hostels for United College and Shaw College respectively. The other three hostels for Chung
Chi College, Wu Yee Sun College and Postgraduate Students were scheduled in future phases of
development.
2. In parallel with the UGC-funded projects, foundation work was also in progress for the
donation-funded Chung Chi Student Development Complex and consultant was engaged to embark the
detailed design of a donation-funded annex for the Art Museum of the University, namely the
Lo Kwee-Seong Pavilion.
3. In spite of the social unrest and disturbances during the report period, e.g. road blockages, impact on
mass transit services and situations on the campus ground etc., only marginal impact was registered in the
abovementioned works as the site operations were mainly foundation works with limited machinery and
labour content only.
4. During the report period, significant progress was also registered in UGC funding applications with
the submission of four new capital project proposals in September 2019; following the Government’s
announcement in the 2019-20 Budget to set aside a dedicated provision of HK$16 billion to cater for the
expansion and improvements of the local institutes and universities.
5. These submissions included the Technical Feasibility Studies (TFS) and Project Definition
Statements (PDS) for: (a) Proposed Engineering Building at Central Campus; (b) Innovation and
Sustainability Building at Station Road; (c) Centralised General Research Laboratory Complex (Block 3)
in Area 39; and (d) Teaching Building Adjacent to Art Museum. Funding approval to commence the
detailed design would be pending the selection of the projects to Category B- status by the Capital Works
Resources Allocation Exercise (CWRAE) in September 2020 the earliest after departmental approval of
the submissions.
6. Regarding the Centralized General Research Laboratory Complex (Block 2) in Area 39 which was
upgraded to Category B+ in 2019 CWRAE; detailed design and preparation for calling the superstructure
and foundation tender were in full swing. The project was scheduled for tabling in upcoming LegCo
committee meetings in 2019/2020 legislative session, to seek funding approval for the construction
works. Land formation was also embarked by Civil Engineering and Development Department targeted
for site handover to CUHK in mid-2020 to commence the construction.
香 港 中 文 大 學
校 園 發 展 處
THE CHINESE UNIVERSITY OF HONG KONG
Campus Development Office
P. 2 of 18
7. Regarding the Food & Health Bureau (FHB)-funded capital project of Proposed Teaching-Research
Complex in Area 39 for Faculty of Medicine, Category B- status was already granted by CWRAE to
apply for the detailed design funding. However, the process was impacted by the disturbances to the
LegCo Complex during the social unrest; the LegCo meetings have to be rescheduled to 2020 after
completion of the reinstatement works.
8. Progressive liaisons were also conducted with FHB regarding site and funding allocations to provide
CUHK with the needed facilities and new buildings in association with the Redevelopment of the Prince
of Wales Hospital (PWH) which was underway. FHB has also clarified that these provisions on CUHK
and PWH campuses to support the needy expansion of medical education, research and nurse training
would not be accountable under the UGC space inventory.
AA&I, Renovation and Minor Works Projects (Appendix C, D and E)
Funded by the Food & Health Bureau (FHB), urgent renovations works for the Choh-Ming Li Basic
Medical Sciences Building was delivered swiftly by the Campus Development Office during the report
period to facilitate the intake of increased number of medical and nursing students in the academic year
2019-20. In parallel, the UGC-funded AA&I projects e.g. Sports Centre Annex, alteration and addition
works to existing laboratory buildings were in steady progress together with various universal access and
slope enhancement works etc.
2. Regarding the assets enhancement works for the aged facilities, privately-funded renovations were
being carried out to various I-Houses, University lodges of Chiangs Building and Chan Kwan Tung
Inter-University Hall. Detailed Design was also in full swing to facilitate the conversion of the
Inter-University Hall near MTR Station into an InnoHub for knowledge transfer and incubation.
3. With the funding support to establish six research centres for the Health@InnoHK and
AIR@InnoHK in Hong Kong Science & Technology Park (HKSTP) under the HK$10 billion Innovation
Funding Scheme initiated by the HKSAR Government, users’ engagement and fitting out works design
were also coordinated progressively with the project consultants; works will be tendered and carried out
in phases to tally with the operational schedules of the six InnoCentres and space availability in HKSTP.
Preliminary Master Plan Concept for Redevelopment of Existing Public Transport Interchange
near MTR University Station
In response to an earlier conversation between the Government and the University Management, a
Preliminary Master Plan Concept was also compiled to explore the potential redevelopment of the
existing Public Transport Interchange near the MTR University Station and the adjacent areas to cater for
CUHK and CUHK Medical Center’s future expansions and long range developments in the vicinity.
Project Portfolio
The updated portfolio of active projects under planning, funding applications, detailed design and
construction are summarized as follows; the monthly and cumulative totals for consultancies services and
works in progress are listed overleaf for reference:
i) UGC-funded capital projects under detailed design and construction amounted to HK$2,600mil;
ii) Donation-funded capital projects amounted to HK$850mil;
iii) The budget estimates for new capital projects under planning and applications for UGC / FHB funding
amounted to HK$11,600mil.
P. 3 of 18
Green Building & Architectural Design Awards 2019
The Chinese University of Hong Kong 香港中文大學
Green Building Leadership Category (Government, Institutions & NGOs) - PIONEER AWARD
綠建領導類別 - 先鋒大獎 (政府機構,公用機構及非政府組織)
CUHK is the first and only University in Hong Kong receiving this prestige award; putting CUHK in the GBA Green Building Leadership
hall of fame together with other top notch companies / organizations e.g. Henderson Land Development Company Limited, New World
Development Limited, Swire Properties Limited, The Hong Kong Housing Authority etc.
Jockey Club Postgraduate Halls 2&3, CUHK 賽馬會研究生宿舍二座及三座
GREEN BUILDING AWARD 2019: FINALIST
(New Buildings Category: Completed Projects – Residential Building)
THE HONG KONG INSTITUTE OF ARCHITECTS ANNUAL AWARDS 2018/19: FINALIST
(Residential Building)
Chung Chi Student Development Complex 崇基學生活動中心
GREEN BUILDING AWARD 2019: FINALIST
(New Buildings Category: Projects Under Construction and /or Design - Institutional Building)
WORLD ARCHITECTURE FESTIVAL 2019: SHORTLISTED
(Future Project: Education)
CUHK Medical Centre 香港中文大學醫院
GREEN BUILDING AWARD 2019: FINALIST
(New Buildings Category: Projects Under Construction and / or Design – Commercial Building)
P. 4 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
Description 2019
Cumulative Total for the Fiscal Year(s)
July August September 2019-20 2018-19/2017-18
Expenditures on Capital and AA&I Works, inclusive of hostel development and private funds
$15.811m $24.056m $24.297m $88.317m $210.932m/$138.018m
Expenditures on Minor Works (supported by Minor Works vote and others)
$15.692m $14.207m $15.757 $80.971m $69.046m/$83.319m
Description 2019
Cumulative Total for the Fiscal Year(s)
October November December 2019-20 2018-19/2017-18
Expenditures on Capital and AA&I Works, inclusive of hostel development and private funds
$22.246m $10.286m $34.719m $155.568m $247.102m/$228.762m
Expenditures on Minor Works (supported by Minor Works vote and others)
$20.979m $16.539m $17.253m $135.742m $111.639m/$110.927m
Note: Fiscal year - 1st April 2019 to 31st March 2020
Report Period - 1st July 2019 to 31st December 2019
P. 5 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
Section Content Page
I. MAJOR CAPITAL PROGRAMME ON UGC FUNDING 7 - 9 1. Jockey Club Postgraduate Halls 2 & 3
(previously named 2x338-place Student Hostels (Block A3 & A4) on Northern Campus)
2. New Student Hostels under Hostel Development Fund (HDF)
(a) 300-place Student Hostel at New Asia Campus
(b) 250-place Student Hostel at United Campus
(c) 300-place Student Hostel at Shaw Campus
(d) 300-place Student Hostel at Chung Chi Campus
(e) 250-place Student Hostel at Wu Yee Sun Campus
(f) 394-place Student Hostel in Area 39
3. Centralised General Research Lab Complex (Block 2) in Area 39
4. Final Accounts of 3+3+4 Capital and New College Projects
II. AA&I WORKS ON UGC BLOCK ALLOCATION 10 - 12 A. 2019-2020 Block Allocation
1. Space Addition and Reorganization at G/F of Lady Shaw Building for Office / Teaching Laboratory
2. Infrastructure and Safety Enhancement Works -
(a) Stabilisation Works for Slope Behind University Residence No. 16 & 17
(b) Construction of New Dangerous Goods Stores for Compressed Gases on Campus
3. Repairing Works for Two Slopes with Potential Danger B. 2018-2019 Block Allocation
1. Upgrading of Information Technology Infrastructure for Next Generation Campus Network
2. Provisions of New Laboratory Space –
(a) Spatial Reorganisation of 5/F Mong Man Wai Building and Lady Shaw Building
(b) Extension on 2/F of Ho Sin-Hang Engineering Building
3. Spatial Re-organization and Improvement Works for Dissecting Laboratories on LG/F of Choh-Ming Li
Basic Medical Sciences Building
C. 2017-2018 Block Allocation
1. Extension on roof of Mong Man Wai Building and 1/F of William M.W. Mong Engineering Building for
new laboratory space
2. Extension of University Sports Centre
III. OTHER CAPITAL PROJECTS AND AA&I WORKS 13 - 14 1. Teaching-Research Complex in Area 39 2. Redevelopment of Prince of Wales Hospital and Associated University Facilities in Prince of Wales Hospital by
Hospital Authority
3. Chung Chi Student Development Complex 4. Lo Kwee Seong Pavilion of the Art Museum 5. Renovation of Facilities in Choh-Ming Li Basic Medical Science Building (Remaining Works) 6. Six InnoCentres at the Hong Kong Science and Technology Park
7. Other Minor Projects Being or Having Been Put Forth to the UGC for AA&I Funding Consideration
IV. MINOR WORKS 15 - 18
Appendix – Selected Projects Images
i – xv
P. 6 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
Key Legend:
P: Project: M: Amount of Contract/Sub-contract:
AP Authorized Person $A Air-conditioning Installation
PA Project Architect/Architectural Consultant $AV Audio-visual System
PB Building Services Consultant $C Construction Works
PD Project Designer $E Electrical Installation
PG Geotechnical Consultant $F Fire Services Installation
PLA Landscape Architect $F&E Major Equipment Installation
PM Project Manager $FO Fitting-out Works
PQ Quantity Surveyor/Building Surveyor $L Lifts Installation
PS Structural Consultant $LF Laboratory Furniture Installation
TBA To be Appointed $M Building Construction / Main Contract Works
$R Foundation / Sub-structure
$S Site Investigation/Slopes/External Works
$T Telephone System
C: Contract/Sub-contract:
CA Air-conditioning Installation
CAV Audio-visual System
CD&B Design & Build D: Date:
CE Electrical Installation D/AIP Date accorded AIP
CF Fire Services Installation D/C Date for Commencement
CF&E Furniture & Equipment Installation DC/E Date for Completion with Anticipated EOT
CFO Fitting-out Works D/FA Date accorded Full Approval
CL Lifts Installation D/PC Date of Practical Completion
CLF Laboratory Furniture Installation D/TC Date for Targeted Completion
CM Building Main Contractor
CR Substructural
CS Site Investigation/Slopes/External Works
CT Telephone System
GI Ground Investigation
TS Topographic Survey
P. 7 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
I. Major Capital Programme on UGC Funding:
Project Title
Percentage
of Works
Completed
Description
Dec
I. 1. Jockey Club Postgraduate Halls 2 & 3
(previously named 2x338-place Student Hostels
(Block A3 & A4) on Northern Campus)
PM – Holman Chong
AP/PA – Andrew Lee King Fun & Associates Architects Ltd.
PS/PG – Meinhardt (C&S) Ltd.
PLA – ACLA Ltd.
PB – Parsons Brinckerhoff (Asia) Ltd.
PQ – Rider Levett Bucknall Ltd.
CM – Chinney Construction Co. Ltd.
D/FA – July 2015
D/C – November 2016 (CM)
D/TC – 4th Quarter 2018
(a) Outline Proposal / Schematic Design 100% Occupation Permit for the hostel blocks was issued by
Buildings Department in November 2018.
Hostel blocks had been completed and handed over to user in
December 2018. Fitting-out works for Amenity Hall and
statutory inspections for Sports Court were completed in June
2019.
Defects rectification were in progress. Ad hoc site meetings
were conducted to review the status of defect rectification.
Materials and documents for BEAM Plus Final Assessment
submission had been made in December 2019.
Preparation of final accounts were in progress for the Main
Contract and direct contracts for FF&E.
Opening Ceremony with donor was held in October 2019.
(b) Detailed Design 100%
(c) Tendering 100%
(d)
(e)
Foundation Works
Site Works
100%
100%
P. 8 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
I. Major Capital Programme on UGC Funding (cont’d):
Project Title
Percentage
of Works
Completed
Description
Dec
I. 2. New Student Hostels under Hostel Development Fund
(HDF)
(a) 300-place Student Hostel at New Asia Campus
(Project Estimate : HK$269.2Mil)
PM – Stephen Leung
PA – Spence Robinson Ltd.
PQ – K.C. Tang Consultants Ltd.
CM – Build King Construction Ltd.
D/C – 17 Jun 2019 (CM)
D/PC – 2nd Quarter 2022
D/TC – 3rd Quarter 2022
(i) Hoarding Work
(ii) Site Formation Work
(iii) Foundation Work
100%
16%
0%
Main Contract was awarded in June 2019. Hoarding work
was completed in Oct 2019. Section 1 Works including Site
Formation and Foundation Works are in progress. Section 2
on Superstructure Works will be commenced tentatively in
August 2020.
(b) 250-place Student Hostel at United Campus
(Project Estimate : HK$224.3Mil)
PM – Thomas Yuen / Hocky Lam AP – LWK & Partners (HK) Ltd. PA – Ida & Billy Architects Ltd. PS/PG – Arthur Yung and Associates Co. Ltd. PB – Far East Consulting Engineers Ltd. PLA – LWK & Partners (HK) Ltd. PQ – Beria Consultant Ltd.
D/FA – December 2018
D/C – 1st Quarter 2021
D/TC – 3rd Quarter 2023
(i) Consultancy appointment
(ii) Outline Proposal / Schematic Design
(iii) Statutory Submission
100%
70%
10%
The Lead Architectural Consultancy Service was awarded in
May 2019 for commencement of design, and the Quantity
Surveying Consultancy Service was awarded in July 2019.
Design workshops with the College were held in September
and October 2019 to explore design possibilities and options.
Building Committee Meetings were held in September and
November 2019 to review and discuss the project design,
budget, programme and proposal for adjustments / addition
parameters.
College consultation was scheduled to be held in 1st Quarter
2020. General building plan was under preparation and
scheduled to be submitted to Buildings Department for
approval in 1st Quarter 2020.
(c) 300-place Student Hostel at Shaw Campus
(Project Estimate : HK$269.2Mil)
PM – Patrick Chan / German Cheung
PA – WCWP International Ltd.
PQ – Rider Levett Bucknall Ltd.
D/FA – December 2018
D/C – 2nd Quarter 2021
D/TC – 2nd Quarter 2024
(i) Consultancy appointment
(ii) Outline Proposal / Schematic Design
100%
50%
The Lead Architectural Consultancy Service was awarded in
October 2019 for commencement of schematic design.
(d) 300-place Student Hostel at Chung Chi
Campus (Project Estimate : HK$269.2Mil)
(e) 250-place Student Hostel at Wu Yee Sun
Campus (Project Estimate : HK$224.3Mil)
Undergoing planning and preliminary design
(f) 394-place Student Hostel in Area 39
(Project Estimate : HK$353.5Mil)
P. 9 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
I. Major Capital Programme on UGC Funding (cont’d):
Project Title
Percentage
of Works
Completed
Description
Dec
I. 3. Centralized General Research Laboratories Complex
(Block 2) in Area 39
(Project Estimate : HK$1,400Mil)
PM – S.C. Li / Thomas Yuen AP/PA – Andrew Lee King Fun & Associates Architects Ltd. PS/PG – Meinhardt (C&S) Ltd. PLA – Urbis Ltd. PB – WSP Hong Kong Ltd. PQ – Rider Levett Bucknall Ltd.
D/FA – September 2017
D/C – July 2020
D/TC – December 2023
The project was upgraded to Cat. B+ in 2019 CWRAE.
Detailed design report and full set of tender document were
submitted to UGC / ArchSD for their vetting in September
and November 2019 respectively.
Detailed design was in full swing and regular design
workshops were held with the users to establish the detailed
laboratory requirements.
Tender for superstructure and foundation works was
scheduled to be issued in March 2020. PWSC and FC
meetings of the Legislative Council were scheduled in 2nd
Quarter 2020 for construction funding approval.
I. 4. Final Accounts of 3+3+4 Capital and New College
Projects
(a) Centralized General Research Laboratories
Complex (Block 1) in Area 39
Assessment of bills of variations and preparation of final
account of works contracts for project close out with the UGC
were in progress. The project final accounts are anticipated
to be completed progressively.
(b) 1,500-place Student Hostels
Site A: Morningside College & S.H. Ho College
Site B: Lee Woo Sing College
(c) Extension to Existing University Library 100%
(d) Student Amenity Centre
(e) An Integrated Teaching Building
(f) Two-Integrated Teaching Buildings
- Yasumoto International Academic Park (YIA)
- Wu Ho Man Yuen Building (WMY)
P. 10 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
II. AA&I Works on UGC Block Allocation:
A. 2019-2020 Block Allocation
Project Title
Percentage
of Works
Completed
Description
Dec
II.A.1. Space Addition and Reorganisation at G/F of Lady
Shaw Building for Office/Teaching Laboratory
(Approved Project Estimate: HK$29.946Mil)
PM – Patrick Chan / German Cheung
D/FA – March 2019
D/C – 4th Quarter 2020
D/TC – 1st Quarter 2022
(a)
Structural Feasibility and Invitation of
Expression of Interest for Consultancies
Services
80%
Users’ allocation to be discussed to formulate the users’
requirements.
II.A.2. Infrastructure and Safety Enhancement Works
(Approved Project Estimate: HK$29.078Mil)
(a)
Stabilisation Works for Slope Behind University
Residence No. 16 & 17 (7NE – C/C65)
PM – Arthur Ma
PG – AECOM Asia Co. Ltd.
D/FA – August 2018
D/C – November 2019
D/TC – 3rd Quarter 2020
(i) Investigation / Site Survey
(ii) Detailed Design
(iii) Tendering
(iv) Stabilization Works
100%
100%
100%
15%
Design submission was approved by Buildings Department.
Contract for the slope stabilization works was awarded and
site works was commenced in November 2019.
(b)
Construction of New Dangerous Goods Stores
for Compressed Gases on Campus
PM – Hocky Lam
AP/PA –Singular Studio Ltd.
D/FA – March 2019
D/C – 3rd Quarter 2020
D/TC – 1st Quarter 2021
(i) Consultancy Services Appointment
(ii) Outline Proposal / Schematic Design
(iii) Statutory Submission
100%
100%
50%
The Lead Architectural Consultancy Services and the
Quantity Surveying Consultancy Service were awarded in
August 2019 for commencement of design. Regular meetings
with the users were held to establish the users’ requirement,
reviewing the conceptual design and design development.
General building plans and structural plans were submitted to
Buildings Department for approval in December 2019.
II.A.3. Repairing Works for Two Slopes with Potential
Danger
(Approved Project Estimate: HK$6.0Mil)
PM – Arthur Ma / Paul Seto
PG – Au Posford Consultants Ltd.
D/FA – 2nd Quarter 2020
D/C – 3rd Quarter 2020
D/TC – 1st Quarter 2021
(a)
(b)
(c)
(d)
(e)
Consultancy Services Appointment
Investigation / Site Survey
Design and Statutory Approval
Tendering
Stabilization Works
100%
20%
0%
0%
0%
Geotechnical consultant was appointed in December 2019 and
desk study / stability investigation began. Slope stabilization
design targeted to be submitted to Buildings Department for
approval in February 2020.
P. 11 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
II. AA&I Works on UGC Block Allocation:
B. 2018-19 Block Allocation
Project Title
Percentage
of Works
Completed
Description
Dec
II.B.1. Upgrading of Information Technology Infrastructure
for Next Generation Campus Network
(Approved Project Estimate: HK$29.938Mil)
D/FA – March 2018
D/C – March 2019
D/TC – December 2020
(a)
(b)
(c)
(d)
Outline Proposal / Schematic Design
Detailed design
Tendering
Construction
100%
100%
100%
70%
Detailed design for the information technology infrastructure
was completed. Procurement of equipment was underway.
Site works commenced in January 2019 and to be completed
progressively.
II.B.2.
Provisions of New Laboratory Space
(Approved Project Estimate: HK$27.462Mil)
(a)
Spatial Reorganisation of 5/F Mong Man Wai
Building and Lady Shaw Building
PM – Mabel Lam
D/FA – May 2019
D/C – March 2020
D/TC – December 2020
(i) Outline Proposal / Schematic Design
(ii) Detailed Design
(iii) Tendering
(iv) Site Work
100%
100%
100%
50%
Construction works for the new office / workshop at Lady
Shaw Building were completed. The detailed design for the
laboratories on 5/F of Mong Man Wail Building was mostly
completed. General building plan submission was made.
Site work would commence in April 2020.
(b) Extension on 2/F of Ho Sin-Hang Engineering
Building
PM – Hocky Lam
AP/PA – Seniorman Design Ltd.
D/FA – March 2018
D/C – 1st Quarter 2020
D/TC – 3rd Quarter 2020
(i) Consultancy Appointment
(ii) Outline Proposal / Schematic Design
(iii) Statutory Submission
(iv) Detailed Design
(v) Tendering
100%
100%
100%
100%
80%
General building plans and structural plans submissions were
approved by Buildings Department. Regular design
workshops were held with the users to review and develop the
detailed designs and tender drawings. Tender for main contract
was issued in November 2019 and returned in December 2019.
Tender assessment was underway.
II.B.3. Spatial Re-organization and Improvement Works for
Dissecting Laboratories on LG/F of Choh-Ming Li
Basic Medical Sciences Building
(Approved Project Estimate: HK$29.986Mil)
PM – S.C. Li
D/FA – December 2018
D/C – March 2019
D/TC – August 2019
(a)
(b)
(c)
(d)
Outline Proposal / Schematic Design
Detailed design
Tendering
Construction
100%
100%
100%
100%
Detailed design was completed. Main Contract was awarded
in February 2019. The works were completed in August
2019 and handovered to users to meet the new academic term
of September 2019.
P. 12 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
II. AA&I Works on UGC Block Allocation:
C. 2017-18 Block Allocation
Project Title
Percentage
of Works
Completed
Description
Dec
II.C.1. Provision of New Laboratory Space
(Approved Project Estimate : HK$29.811Mil) (a) Extension on roof of Mong Man Wai Building
for New laboratory space
PM – Thomas Yuen / Hocky Lam AP/PA – Cheung Kong-Yeung Architects Ltd. CM – Goldfield N&W Construction Co. Ltd D/FA – March 2017 D/C – November 2019 D/TC – 3rd Quarter 2020
(i) Consultancy Appointment
(ii) Outline Proposal / Schematic Design
(iii) Statutory Submission
(iv) Detailed Design
(v) Tendering
(vi) Construction
100% 100% 100% 100% 100% 5%
Tender assessment was completed and Main Contract was
awarded in October 2019. Consent application to Buildings
Department for commencement of work was submitted in
November 2019 and scheduled to commence works in
January 2020.
(b) Extension on 1/F of William M.W. Mong
Engineering Building for new laboratory space
PM – Thomas Yuen/ Hocky Lam
AP/PA – Cheung Kong-Yeung Architects Ltd.
CM – Goldfield N&W Construction Co. Ltd
D/FA – March 2017
D/C – November 2019
D/TC – 2nd Quarter 2020
(i) Consultancy Appointment
(ii) Outline Proposal / Schematic Design
(iii) Statutory Submission
(iv) Detailed Design
(v) Tendering
(vi) Construction
100%
100%
100%
100%
100%
5%
Tender assessment was completed and Main Contract was
awarded in October 2019. Consent application to Buildings
Department was submitted in November 2019 and scheduled
to commence work in January 2020.
II.C.2. Extension of University Sports Centre
(Approved Project Estimate: HK$29.951Mil)
PM – Thomas Yuen AP/PA – Meta 4 Design Forum Ltd. CM – Chiu Lee Construction Co. Ltd. D/FA – March 2017 D/C – April 2019 D/TC – 1st Quarter 2021
(a)
(b)
(c)
(d)
(e)
Consultancy Appointment
Outline Proposal / Schematic Design
Statutory Submission
Detailed Design
Tendering
100% 100% 100% 100% 100%
Construction works was commenced in August 2019. Site
formation, foundation and drainage diversion works were in
progress.
(f) Construction
20%
P. 13 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works:
(on private funds or seeking UGC’s support)
Project Title
Percentage
of Works
Completed
Description
Dec
III. 1. Teaching–Research Complex in Area 39 Building Committee was formed and its 1st meeting was held
in December 2019. A first draft of the tender document for
the consultancy was also prepared and issued to ASD for
comment in November 2019. Invitation for Expression of
Interest in the Lead Architectural and Associated Consultancy
was issued in December 2019.
III. 2. Redevelopment of Prince of Wales Hospital (PWH)
and the associated University Facilities in Prince of
Wales Hospital by Hospital Authority (HA)
Schedule of Accommodation for University space in PWH
was worked out by Faculty of Medicine and submitted to HA
for their incorporation. Scheme layout plans on the
reprovisioned space at existing HA premises from the project
consultants of HA was commented by the University for HA’s
consideration. In addition, scheme design proposals for the
Faculty’s proposed new developments in / or adjoining to the
PWH Campus was under study for FHB’s and HA’s
consideration.
III. 3.
Chung Chi Student Development Complex at Chung
Chi College
(Project Estimate : HK$250Mil)
PM – Patrick Chan / German Cheung
PA – Leigh & Orange Ltd.
PQ – KC Tang Consultants Ltd.
D/FA – 1st Quarter 2019
D/C – March 2019
D/TC – 3rd Quarter 2021
(a) Feasibility Study 100% Site works commenced in March 2019 and in steady progress.
The target completion date is scheduled in 3rd Quarter 2021.
(b) Consultancy Appointment 100%
(c) Detailed Design 100%
(d) Site Work (Section 1) 63%
III. 4.
Art Museum - Lo Kwee-Seong Pavilion
(Project Estimate : HK$150Mil)
PM – Stephen Leung
PA – Rocco Design Architects Associates Ltd.
PQ – Turner and Townsend Ltd.
D/FA – 1st Quarter 2020
D/C – September 2019
D/TC – 3rd Quarter 2023
(a) Feasibility Study 100% Lead Consultancy was awarded in September 2019 and in
Schematic Design stage. (b) Consultancy Appointment 100%
(c) Detailed Design 20%
(d) Site Work 0%
III. 5.
Renovation of Facilities in Choh-Ming Li Basic
Medical Sciences Building (Remaining Works)
(Project Estimate : HK$57.2Mil)
PM – Mabel Lam
PA – Seniorman Design Ltd.
PQ – TLS & Associates Ltd.
D/FA – March 2019
D/C – May 2020
D/TC – December 2021
(a) Feasibility Study 100% Detailed design was completed. The draft tender documents
and PWSC Paper have been submitted to FHB / ArchSD for
their comment. It was tentatively scheduled for construction
funding approval at PWSC and FC meetings of the Legislative
Council in 2nd Quarter 2020.
(b) Consultancy Appointment 100%
(c) Detailed Design 70%
(d) Tender Documentation 0%
P. 14 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works: (cont’d)
(on private funds or seeking UGC’s support)
Project Title
Percentage
of Works
Completed
Description
Dec
III. 6.
Six InnoCentres at the Hong Kong Science and
Technology Park
(Project Estimate : HK$150Mil)
PM – Mabel Lam
PA – Tony Ip Green Architects Ltd.
PQ – Turner & Townsend Ltd.
D/FA – September 2019
D/C – May 2020
D/TC – December 2020
(a) Feasibility Study 100% With the funding support to establish six research centres for
Health@InnoHK and AIR@InnoHK in Hong Kong Science
and Technology Park (HKSTP) under the HK$10 billion
Innovation Funding Scheme initiated by the HKSAR
Government, users’ engagement and fitting out works design
were also coordinated progressively with the project
consultants; works will be tendered and carried out in phases
to tally with the operational schedules of the six InnoCentres
and space availability in HKSTP.
General building plans submission to Buildings Department
were made. Detailed design for the six InnoCentres were
mostly completed and will be tendered out in packages
progressively. Site works for two centres under first package
will commence in May 2020. Overall completion of all
centres will be by end December 2020.
(b) Consultancy Appointment 100%
(c) Detailed Design 60%
III. 7. Other Minor Projects Being or Having Been Put
Forth to the UGC for AA&I Funding Consideration
Projects submitted to UGC for consideration in June
2019 under 2020/2021 Block Allocation
(1)
Spatial re-organization and Improvement Works
a) Music Department at Hui Yeung Shing Building
b) Faculty of Education at Ho Tim Building
(Estimated Cost: HK$29.8 Mil)
(2) Upgrading and Addition of Sports Facilities at Outdoor
Areas for Active Campus Project
(Estimated Cost: HK$28.8 Mil)
(3) Accessibility Improvement Works for Barrier Free Access
a) Replacement of Lift at Chan Chun Ha Hall
b) New Lifts at Adam Schall Residence
c) Improvement Works to Lift Lobby and Upgrading
Existing Lift at Elisabeth Luce Moore Library
d) Installation of Automatic Doors to Toilets and
Automatic Swing Gates in Libraries
e) Addition of Lift from International House I/II to
LG2/4 of Lee Woo Sing College
(Estimate Cost: HK$29.7 Mil)
(4) Stabilization of Slopes – Phase 15
(Estimated Cost: HK$29.2 Mil)
(5) Safety Enhancement Works – Construction Pedestrian
Footbridge between Basic Medical Sciences Building
and Mong Man Wai Building to Enhance the Pedestrian
Safety
(Estimated Cost: HK$27.28 Mil)
The outcome will be known in March 2020.
P. 15 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019 IV. Minor Works:
(July 2019 - Dec 2019)
A. The following minor works have been completed during the period of report: (Project Cost: HK$121 Mil)
(1) Fitting Out Works at LG12C at University Administration Building
(2) Fitting Out Works of Makerspace (phase 2) at LG/F University Library
(3) Fitting Out Works of Microfilm Room at G/F University Library
(4) Renovation Works of Laboratory at Room 258 at University Science Centre for Department of Chemistry
(5) Alteration and addition works for green roof at 3/F podium Choh-Ming Li Basic Medical Sciences
Building
(6) Alteration and addition works for converting language laboratories into multi-purpose classrooms at Lee
Shau Kee Building for Registry
(7) Application for Extension of Temporary Occupation Permit & Temporary Building Permit of temporary
structure at Nissen Hut and Chien Mu Library
(8) Fitting Out Works at 2/F of Elisabeth Luce Moore Library
(9) Upgrading Works at Central Data Centre at Wu Ho Man Yuen Building for High Performance
Computing System
(10) Alteration and addition work for new passenger lift at G/F to LG4/F of Lee Woo Sing College
(11) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:
(a) Lui Che Woo Clinical Sciences Building
Room 124010, 10/F for Li Ka Shing Institute of Health Sciences
(b) Li Ka Shing Specialist Clinics, North Wing
Surgical Skill Lab, 3/F for CUHK Jockey Club Minimally Invasive Surgical Skills Centre
(Phase 1)
(12) Renovation Works for Faculty of Medicine at Tai Po Hospital:
(a) Multicentre
Room GB6, G/F Multicentre for Department of Psychiatry
(13) GIS based Slope Information System and Engineer Inspection for Maintenance – Reports of Engineer
Inspection and Maintenance Manual for 75 features were completed. Inspection Reports for 23 new
features were submitted to GEO and pending for registration. The GIS based Slope Information System
is in progress.
P. 16 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
IV. Minor Works: (July 2019 - Dec 2019)
B. The following minor works are at different stages of construction or implementation: (Project Cost: HK$51 Mil)
(1) Alteration and addition works for Chan Kwan Tung Inter-University Hall (January 2020) & Chiang’s
Building (July 2020)
(2) Spatial Re-organisation of 10/F and 11/F of William M. W. Mong Engineering Building for Department of
Biomedical Engineering – (June 2020)
(3) Alteration and Major Renovations to convert Inter-University Hall into an InnoHub – (Phase 1: April 2020 /
Phase 2: July 2020)
(4) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:
(a) Lui Che Woo Clinical Sciences Building
Room 34141, 1/F for Department of Chemical Pathology – (June 2020)
Room 74002, 5/F for Department of Orthopaedics & Traumatology (May 2020)
(b) Li Ka Shing Specialist Clinics, North Wing
Surgical Skill Lab, 3/F for CUHK Jockey Club Minimally Invasive Surgical Skills Centre
(Phase 2) – (July 2020)
(c) Special Block E & F
Office 2 & 3, 1/F Block F for Department of Obstetrics and Gynaecology – (July 2020)
(d) CUHK Li Ka Shing Medical Sciences Building
10/F (ROOMS 1016A to 1016D) for Li Ka Shing Institute of Health Sciences (April 2020)
11/F (ROOM 1107) for Li Ka Shing Institute of Health Sciences – (May 2020)
Orthopaedic Learning Centre, 1/F for Department of Orthopaedics and Traumatology –
(May 2020)
(e) The Sir Yue-Kong Pao Centre for Cancer and The Lady Pao Children’s Cancer Centre
CC4, LG/F for Department of Imaging & International Radiology (March 2020)
Entrance Lobby, LG/F for Faculty and Planning Office (March 2020)
Remarks: ( ) denotes scheduled completion date
P. 17 of 18
Physical Development – Half-yearly Progress Report
For the Period Ended 31 December 2019
IV. Minor Works: (July 2019 - Dec 2019)
(C) The following minor works are at different stages of feasibility studies, design or tender:
(1) Proposed extension of existing Fitness Room at C.W. Chu College – Schematic design was completed and pending confirmation of funding.
(2) Proposed PET/MRI laboratory at Shanghai Fraternity Association Research Services Centre – Schematic
design in progress.
(3) Hong Kong Institute of Biotechnology
(a) Proposed GMP Laboratories on G/F – Schematic design in progress.
(b) Renovation Works of Clean Room Laboratories on 2/F – Detailed design was completed and
preparation of tender document was underway.
(4) Proposed Electronic Microscope Laboratory at LG/F University Science Centre – Schematic design in
progress.
(5) Fitting Out Works of LG/F (Rooms LG1 & LG2) East Wing of Art Museum – Schematic design in progress.
(6) Fitting Out Works of Laboratory 3 & 5 on 8/F Mong Man Wai Building – Detailed design in progress.
(7) Renovation Works of PV panel, metal shelter and climbing wall at University Sports Centre annex –
Detailed design in progress.
(8) Proposed Renovation Works at 1/F Tin Ka Ping Building
(a) Phase 1: Expansion of HK Literature - Appointment of Consultant
(b) Phase 2: New Space for Contemporary Chinese Literature – Funding Application
(9) Proposed Renovation Works at Choh-Ming Li Basic Medical Sciences Building - Detailed design was
completed and pending confirmation of funding.
(10) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:
(a) Lui Che Woo Clinical Sciences Building
Room 104023A, 8/F for Clinical Research Management Office – Tender was issued, pending
HA’s approval.
Seminar Room & CSLC Office, 2/F for Faculty and Planning Office – Tender was issued,
pending HA’s approval.
Rooms 64002, 64042, 64043 & 64048, 4/F for Department of Surgery – Tender was issued,
pending HA’s approval.
Rooms 74043 to 74046, 5/F for Department of Orthopaedics & Traumatology – Tender was
issued, pending HA’s approval.
Rooms 114038 & 114041, 9/F for Department of Medicine and Therapeutics – Tender was
issued, pending HA’s approval.
Rooms 24151A, 24156A & 24160A, G/F for Department of Surgery. – Tender was issued,
pending HA’s approval.
Rooms 84026 to 84031, 6/F for Department of Otorhinolaryngology, Head and Neck Surgery –
(Pending by HA/User)
(b) The Sir Yue-Kong Pao Centre for Cancer and The Lady Pao Children’s Cancer Centre
Room 424A, 4/F for Department of Surgery – Tender was issued, pending for HA’s approval.
3/F (Room 306A) & 4/F (424B & 428) for Department of Surgery – Tender was issued, pending
for HA’s approval.
Programme – Capital Projects
Programme – AA&I Projects
- i -
CDO - Dec 2019
CDO - Dec 2019
Note: Programmes will be adjusted from time to time to suit actual progress and/ or rescheduling arrangements
Appendix A- Capital Projects
Jockey Club Postgraduate Halls 2 & 3 on Northern Campus
Two multi-storey hostel blocks with a total of 676 student hostel places, including accommodation for wardens,tutors and attendants; common and supporting facilities
CFA : 15,980 sqm
Project cost : HK$675.2 mil
Status : Occupation Permit for Hostel Blocks was issued by BuildingsDepartment in November 2018. Fitting-out for Amenity Hall andstatutory inspections for Sports Court completed in June 2019.
Completion : 4th Quarter 2018 for main hostel blocks
Physical Development –
Half-yearly Progress Report
Period ended 31 December 2019
Proposed Centralized General Research Laboratory Complex Block 2 in Area 39 (Expanded and relocated version )
Proposed Lab Block 2Revised TFS
approved
Block 1 Block 3
& 4
Teaching-
Research
ComplexP G
HallsC W Chu
College
A multi-storey research laboratory building in Area 39, including research laboratories, seminar rooms, offices, DG stores, car parking facilities
CFA : 23,674 sqm
Preliminary Estimate : HK$1,400 mil @4th Quarter 2019
Status : The project was upgraded to Cat. B+ in 2019 CWRAE. Building Committee Meetings were held to explore the design concepts and formulate the user’s requirements.
Detailed design was in progress. The detailed design report and tender document were
submitted to UGC/ ArchSD for vetting.
Completion : 2023 - 2024
Block 2
- ii -
New Student Hostels under Hostel Development Fund (HDF) - 300-place Student Hostel, New Asia Campus
Appendix A- Capital Projects
New Student Hostels under Hostel Development Fund (HDF) - 250-place Student Hostel, United Campus
Multi-storey 300-place student hostel on New Asia Campus with multi-purpose hall and related facilities
CFA : 5,920 sqm
Project Cost : HK$269 mil
Status : Phase 1 of Main Contract Works including hoarding, site formation and foundation work were commenced in June 2019. Site formation work was mostly completed andfoundation work is in progress.
Completion : 3rd Quarter 2022
Multi-storey 250-place hostel with accommodation for wardens, tutors and supporting facilities
CFA : 5,100 sqm
Preliminary Estimate : HK$232 mil @ 3rd Quarter 2019
Status : Consultant was appointed to commence Detailed Design in May 2019. Building Committee Meetings and design workshops were held to explore the design concepts and formulate the user’s requirements.
Completion : 3rd Quarter 2023- iii -
New Student Hostels under Hostel Development Fund (HDF) - 300-place Student Hostel, Shaw Campus
Appendix A- Capital Projects
Multi-storey 300-place hostel with accommodation for wardens, tutors and supporting facilities
CFA : 5,800 sqm
Preliminary Estimate : HK$293mil @ 3rd Quarter 2018
Status : Building Committee was formed; consultant was appointed to commence DetailedDesign in Oct 2019.
Completion : 2nd Quarter 2024
- iv -
Appendix A– Capital Projects
Government Funding by Food & Health Bureau
Re-provision and expansion of CUHK facilities in Prince of Wales Hospital Redevelopment by Hospital Authority / Food & Health Bureau
Faculty of Medicine Teaching & Research Complex in Area 39
- v -
Area 39 Master Development Plan
Appendix B – Capital Projects
Private Funding
Redevelopment of Art Museum Annex
Redevelopment of existing Art Museum Annex to extension of gallery space with Exhibition Area, Café, Artist Studio, workshop and supporting facilities
CFA : 4,780 sqm
Project Cost : HK$150 mil
Status : The Lead Consultancy Contract was awarded to Rocco Design Architects Associates Ltd in Sep 2019 for commencement of Schematic Design
Completion : 3rd Quarter 2023
Proposed Lab Block 2Revised TFS
approved
- vi -
Proposed Lab Block 2Revised TFS
approved
Chung Chi Student Development Complex
Chung Chi Student Development Complex includes upper block as “Multi-functional Building” with staff quarters and a mini-theatre and the lower block as “Student Development Centre” with activity rooms and CC student union offices. A footbridge will link the two blocks with direct access from roof of Pommerenke Student Centre.
CFA : 4,420 sqm
Project Estimate : HK$250 mil @ 3rd Quarter 2018
Status : Site works commenced in Mar 2019. Site foundation & formation works in progress.
Completion : 3rd Quarter 2021
Extension of University Sports Centre
Appendix C- Selected AA&I Projects
A new extension block of single floor fitness centre next to the existing University Sports Centre with roof garden on top.
CFA : 445 sqm
Project Cost : HK$35 mil
Status : Construction works commenced in August 2019. Site formation, foundation and drainage diversion works in progress.
Completion : 1st Quarter 2021
- vii -
Provision of New Laboratory Space on Roof Extension of Mong Man Wai Building
Roof top extension to provide new wet / teaching laboratories for research activities
CFA : 640 sqm
Project Cost : HK$20 mil
Status : under construction Completion : 3rd Quarter 2020
Provision of New Laboratory Space at 1/F of William M W Mong Engineering Building
Extension on existing 1/F flat roof to provide new teaching laboratories for research activities
CFA : 190 sqm
Project Cost : HK$10 mil
Status : under construction.Completion : 2nd Quarter 2020
Appendix C- Selected AA&I Projects
- viii -
Appendix C- Selected AA&I Projects
Construction of New Dangerous Goods Stores for Compressed Gases on Campus
Construction of New Dangerous Goods Stores for Compressed Gases on Campus
CFA : 155 sqm
Project Cost : HK$ 8.89 mil
Status : Detailed design in progressCompletion : 1st Quarter 2021
Proposed New Dangerous
Goods Store
Section
Construction of an extension at the open courtyard at G/F of Lady Shaw Building for office use
CFA : 795 sqm
Project Estimate : HK$30 mil @ 4th Quarter 2018
Status : Expression of interest for Consultancy under invitation
Completion : 1st Quarter 2022
Space Addition and Reorganisation at G/F of Lady Shaw Building for Office/Teaching Laboratory
- ix -
Appendix C- Selected AA&I Projects - Infrastructure Enhancements
Traffic Improvement Work near Central Avenue
Construction of new staircase with flatter gradient to provide pedestrian friendly linkage between Clinic Road and Central Avenue connecting the shuttle lifts at Pentecostal Mission Hall Complex and Mong Man Wai Building, forming a walking route linking the lower and upper level of the campus.
Project cost : HK$9.44mil
Completion : Dec 2019
Slope Improvement Work
Slope stabilization works for Feature no. 7NE-C/C65 at the south of University Residence No.17
Project Cost : HK$11 mil
Completion : 3rd Quarter 2020
- x -
Appendix D–Asset Enhancement Projects
Renovation Works for Chan Kwan Tung Inter-University Hall and Chiang’s Building
Chan Kwan Tung Building Inter-University HallCFA : 1,113 sqmProject Cost : HK$ 24 milCompleted : under constructionCompletion : 1st Quarter 2020
Chiang’s BuildingCFA : 2,345 sqmProject Cost : HK$ 55 milStatus : under constructionCompletion : 3rd Quarter 2020
Renovation Works of Chan Kwan Tung Inter-University Hall and Chiang’s Building
Chiang’s Building sample flat interior
- xi -
Appendix E- Selected Minor Works Projects
Additional Lift at Lee Woo Sing College
Installation of new glazed passage lift from G/F to LG3/F at canteen area.
Status : Lift shaft and lift car installation completed and under statutory inspections.
Project Cost : HK$7.44 mil
Commencement : December 2018
Completion : 1st Quarter 2020
Renovation Works to International House 1 & 2
Renovation of House 1 & 2 in phases including student bedrooms, pantries and common areas.
Project Cost : HK$ 30 milCompletion : July 2019
- xii -
Enhancement of Study Spaces to existing library at 2/F
CFA : 1,100 sqm
Project Cost : HK$5.5mil
Completion : August 2019
Fitting Out Works at 2/F Elisabeth Luce Moore Library, Chung Chi College
Appendix E– Selected Minor Works Projects
Conversion of existing reading and bookshelving areas into MakerSpace.
CFA : 1,000sqm
Project Cost : HK$6mil
Completion : August 2019
Fitting Out Works of MakerSpace at University Library
- xiii -
Appendix E- Selected Minor Works Projects
Renovation of Inno Hub at Inter-University Hall
Renovation of Inter-University Hall from LG/F to 5/F for InnoHub (renamed as Innoport) to house Pi Centre, EPIN Office for ORKTS including the facilities for café, offices, exhibition area, co-working space, workshop and warden flat etc.
Status : Construction in progress
Project Cost : HK$15 mil
Commencement : October 2019
Completion : Phase 1 – April 2020
: Phase 2 – July 2020 - xiv -
The Sir Yue-Kong Pao Centre for Cancer, Prince of Wales Hospital
Renovation Works for The Sir Yue-Kong Pao Centre for Cancer, Prince of Wales Hospital
CFA : 146 sqm
Project Cost : HK$ 2M
Status : Work in progress
Completion : 1st Quarter 2020
Appendix E- Selected Minor Works Projects
Major Renovation of 10/F and 11/F William M W Mong Engineering Building
Spatial Reorganization of 10/F and 11/F William M W Mong Engineering Building for Faculty of Engineering
CFA : 2,000 sqm
Project Cost : HK$23 mil
Completion : Substantial completion in December 2019