SUMMARY OF CONSTRUCTION PROJECTS

WHITE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

- PE OnlyHwy. 67 – Hwy. 25 P.E. 5

Addt'l Rte.-Sec.: Cleburne 5-15; Lonoke 5-12; White 5-14

- 13 Programmed - - 001748*

- PE OnlyVilonia Bypass – Beebe P.E. 64

Addt'l Rte.-Sec.: Faulkner 64-9

- 10 Programmed - - 012154*

Major WideningVilonia Bypass – East (F) 5.1964

Addt'l Rte.-Sec.: Faulkner 64-9

$14,970,21410 Completed Jan. 2016 Mar. 2019 7.37 $21,386,020012155

Safety ImprovementsCabot – Bald Knob (Sel. Secs.) (Cable Median Barrier) (S) 29.8267

Addt'l Rte.-Sec.: Lonoke 67-11; White 67-13

$4,290,46412 Completed Apr. 2013 Aug. 2013 39.19 $5,645,347012179

Safety ImprovementsHwy. 167 – Hwy. 226 (Sel. Secs.) (Cable Median Barrier) (S) 9.0667

Addt'l Rte.-Sec.: Craighead 67-15; Jackson 67-14/15

$1,850,30113 Completed Sep. 2014 Jun. 2016 36.67 $7,489,024012195

ResurfacingHwy. 367 – Crittenden Co. Line (S) 9.0964

Addt'l Rte.-Sec.: Cross 64-15/16; Woodruff 64-12/13/14

$2,784,80711 Sub. Completed Jul. 2017 Dec. 2018 62.51 $19,149,095012287

Safety ImprovementsHwy. 64 – Hwy. 5 (Safety Impvts.) (Sel. Secs.) (S) 2.0236

Addt'l Rte.-Sec.: Faulkner 36-1

< $1 M2 Scheduled Aug. 2020 25.30 $5 - $10 M012290

- Structure & ApproachesCypress Bayou Strs. & Apprs. (S) 67

Addt'l Rte.-Sec.: Lonoke 67-11

$1 - $5 M12 Scheduled Feb. 2022 - $1 - $5 M012328

- Bridge RehabilitationDistricts 4, 5, 8 & 9 Bridge Preservation (2020) (S) 5

Addt'l Rte.-Sec.: Various

$186,30213 Under Construction May. 2020 - $6,147,965012351*

- Roadside AppurtenancesPark & Ride Lot Improvements (Dist. 5) (S) < $1 MProgrammed - < $1 M050025*

Passing LanesPangburn – Searcy (Passing Lanes) (S) 2.3116 $6,065,93113 Completed Mar. 2010 Aug. 2011 2.31 $6,065,931050188

New LocationHwy. 13 Extension (Searcy) (S) 4.99New $16,395,783Completed Sep. 2012 May. 2016 4.99 $16,395,783050189

- Safety ImprovementsHwy. 16/Holmes Rd. Signal (Searcy) (S) 16

Addt'l Rte.-Sec.: White CS

$88,96313 Completed Jan. 2010 Dec. 2010 - $88,963050197

- Safety ImprovementsHwy. 67B/Hwy. 31/Hwy. 367 Signal (Beebe) (S) 31

Addt'l Rte.-Sec.: White 67-12B, 367-15

$124,7264 Completed Jan. 2010 Aug. 2010 - $124,726050208

ResurfacingHwy. 67B – West (Searcy) (Overlay) (S) 2.4036 $753,0113 Completed Apr. 2010 Aug. 2010 2.40 $753,011050224

Structure & ApproachesBrier Creek Str. & Apprs. (S) 0.14305 $1,132,7723 Completed Dec. 2011 Sep. 2012 0.14 $1,132,772050229

Major WideningHwy. 367 – Hwy. 67 (Beebe) (S) 0.20367 $1,267,86715S Completed Jun. 2013 Apr. 2014 0.20 $1,267,867050232

ResurfacingHwy. 310 – Hwy. 305 (Overlay) (S) 6.3836 $792,8283 Completed Jun. 2010 Aug. 2010 6.38 $792,828050234

- EmergencyDist. 5 Emergency Repairs (FFY10) (S) 64

Addt'l Rte.-Sec.: Independence 69-4

$7,76211 Completed Jun. 2010 Jun. 2010 - $15,523050238*

Program Management

White

June 3, 2020

* Job not shown on county map.

SUMMARY OF CONSTRUCTION PROJECTS

WHITE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

-RehabilitationHwy. 67 Ramps (Exits 28, 31, 35 & 42) (Rehab.) (S) 67 $914,55612 Completed Aug. 2010 Mar. 2011 - $914,556050242

RehabilitationLonoke Co. Line – North (Rehab.) (S) 6.5667 $1,856,01112 Completed Aug. 2010 Sep. 2011 6.56 $1,856,011050243

- Safety ImprovementsHwy. 67B/Poplar St. & Hwy. 67 SB Ramp Signals (Searcy) (S) 67

Addt'l Rte.-Sec.: White 67-12C

$374,53812 Completed May. 2012 Apr. 2013 - $374,538050244

- Safety ImprovementsHwy. 16/Elm St. Signal (Searcy) (S) 16

Addt'l Rte.-Sec.: White CS

$235,70113 Completed Jul. 2013 Apr. 2014 - $235,701050245

New LocationHwy. 36 – Hwy. 16 (S) 3.71New $11,385,566Completed Aug. 2016 Mar. 2018 3.71 $11,385,566050249

New LocationHwy. 16 – Hwy. 67 (S) 4.24New $16,284,376Completed Dec. 2015 Mar. 2018 4.24 $16,284,376050251

ResurfacingUnion Pacific R.R. Overpass – East (Overlay) (S) 3.5464 $555,46511 Completed Jun. 2011 Jul. 2011 3.54 $555,465050252

-EnhancementJudsonia Truss Bridge Restoration (ATEP-11) (S) $938,353Completed May. 2012 Dec. 2014 - $938,353050259*

ReconstructionHwy. 157 – Hwy. 167 (Ph. II) (S) 4.9867 $19,548,04713 Completed Feb. 2013 Aug. 2015 4.98 $19,548,047050260

Major WideningBeebe – West (F) 3.2764 $8,993,59010 Completed Jun. 2016 Sep. 2017 3.27 $8,993,590050263

Safety ImprovementsPangburn – Fourmile Hill (Safety Impvts.) (Sel. Secs.) (S) 2.9516 $4,523,46113 Under Construction May. 2020 2.95 $4,523,461050279

Safety Improvements

Structure & Approaches

Joy – Searcy (S) 8.6736 $8,910,1183 Under Construction Sep. 2019 8.67 $8,910,118050280

- MiscellaneousDistrict 5 Bridge Painting (Phase I) (2013) (S) 67

Addt'l Rte.-Sec.: Various

$821,46512 Completed Jun. 2013 Mar. 2014 - $3,576,399050290*

-RR CrossingMorris Rd. RR Signal (Garner) (S) $217,623Completed Oct. 2014 Aug. 2015 - $217,623050311*

-RR CrossingSafley Rd. RR Signals (NE of Judsonia) (S) CR $433,300Under Construction Feb. 2016 - $433,300050340*

Structure & ApproachesCypress Bayou – Hwy. 267 Strs. & Apprs. (S) 1.1031 $5 - $10 M4 Scheduled Nov. 2020 1.10 $5 - $10 M050342

ResurfacingLonoke Co. Line – Hwy. 67B (Sel. Secs.) (S) 11.0667

Addt'l Rte.-Sec.: White 367-15

$4,578,73912C Completed Apr. 2019 Oct. 2019 11.06 $4,578,739050350

ResurfacingHwy. 64 – North (Sel. Secs.) (S) 5.595 $1,142,46714 Completed Jan. 2017 Mar. 2018 5.59 $1,142,467050351

ResurfacingVelvet Ridge – North of Hwy. 87 (S) 5.66167

Addt'l Rte.-Sec.: Jackson 167-15; White 167-16

$2,211,27714 Completed Apr. 2018 Oct. 2018 7.16 $2,797,305050355

ResurfacingHwys. 64 & 67B (Sel. Secs.) (Beebe) (S) 4.1864

Addt'l Rte.-Sec.: White 67-12B

$1,705,69310 Completed Apr. 2018 Oct. 2018 4.18 $1,705,693050358

ResurfacingHwy. 67B – Hwy. 367 (Searcy) (S) 2.3836 $1,287,4263 Completed Apr. 2017 Feb. 2018 2.38 $1,287,426050359

ResurfacingMidsouth Dr. – Ranes Rd. (S) 0.89385 $369,0681 Completed Apr. 2017 Oct. 2017 0.89 $369,068050360

ResurfacingHwy. 36 – Bald Knob (S) 7.30367 $2,610,47117 Completed Apr. 2018 Aug. 2018 7.30 $2,610,471050362

ResurfacingHwy. 67B – Hwy. 36 (S) 3.99367 $1,959,91916 Completed Feb. 2019 Jul. 2019 3.99 $1,959,919050364

Program Management

White

June 3, 2020

* Job not shown on county map.

SUMMARY OF CONSTRUCTION PROJECTS

WHITE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

ResurfacingHwy. 31 – Hwy. 36 (S) 7.025 $1,561,98614 Completed Apr. 2018 Jul. 2018 7.02 $1,561,986050365

ResurfacingHwy. 67 – Jackson Co. Line (S) 3.5087 $899,2581 Completed May. 2018 Oct. 2018 3.50 $899,258050368

RehabilitationLonoke Co. Line – Judsonia (S) 24.8667

Addt'l Rte.-Sec.: White 67-13

$20,889,15912 Under Construction Jul. 2019 24.86 $20,889,159050374

Bridge Rehabilitation

Rehabilitation

Bald Knob – Newport (S) 11.6667

Addt'l Rte.-Sec.: Jackson 67-14/15

$7,966,17813 Under Construction Dec. 2018 27.36 $18,692,510050375

ResurfacingPrairie Co. Line – North (S) 3.5011 $181,78911 Completed Jan. 2019 Jul. 2019 3.50 $181,789050380

- RR CrossingVine St. RR Signals & Surf. (Judsonia) (S) < $1 MProgrammed - < $1 M050384*

- RR CrossingKensett RR Corridor Crossing Upgrades (Kensett) (S) 36

Addt'l Rte.-Sec.: White CS

$1 - $5 M5 Programmed - $1 - $5 M050388*

-RR CrossingHammons St. RR Signals (Judsonia) (S) $309,600Under Construction Jan. 2018 - $309,600050389*

-EnhancementPangburn Sidewalk Impvts. (TAP-17) (S) $104,315Completed Mar. 2019 Dec. 2019 - $104,315050391*

SealingDistrict 5 Sealing Program (2018) (S) 14.5331

Addt'l Rte.-Sec.: Various

$178,1784 Under Construction 72.32 $886,844050392*

ResurfacingS. of White Co. Line – Batesville (S) 2.16167

Addt'l Rte.-Sec.: Independence 167-17

$535,49116 Under Construction Feb. 2020 19.05 $4,722,726050404

ResurfacingHwy. 5 – Hwy. 67B (Sel. Secs.) (S) 12.5436 $5 - $10 M3 Scheduled 2022 12.54 $5 - $10 M050405

ResurfacingHwy. 67 – Hwy. 385 (Kensett & Searcy) (S) 7.5536

Addt'l Rte.-Sec.: White 67-12C

$3,592,9824 Under Construction May. 2020 7.55 $3,592,982050407

Structure & ApproachesBarber's Lake Str. & Apprs. (S) 0.5436 $1 - $5 M5 Scheduled Jan. 2021 0.54 $1 - $5 M050417

- Roadside AppurtenancesBeebe Center St. Sidewalk Ext. (TAP-18) (S) < $1 MProgrammed - < $1 M050424*

- Roadside AppurtenancesMcRae Sidewalks (TAP-18) (S) < $1 MProgrammed - < $1 M050425*

- Safety ImprovementsDoyle Rd. RR Signals (N. of McRae) (S) CS < $1 MProgrammed - < $1 M050433*

ResurfacingLonoke Co. Line – Hwy. 64 (S) 2.845 $1 - $5 M13 Scheduled 2021 2.84 $1 - $5 MA50002

Structure & ApproachesBayou Des Arc Str. & Apprs. (S) 0.19CR $1,236,738Completed Jul. 2011 May. 2012 0.19 $1,236,738BR7313*

ResurfacingBeebe & Higginson Overlay (Sel. Secs.) (S) 1.75CS $256,824Completed Mar. 2015 Jun. 2015 1.75 $256,824C73001*

ResurfacingBald Knob Overlay (Sel. Secs.) (S) 1.70CS $208,463Completed Jul. 2015 Oct. 2015 1.70 $208,463C73002*

ResurfacingSearcy Benton Ave. Overlay (S) 1.73CS $274,225Completed Jul. 2015 Oct. 2015 1.73 $274,225C73003*

ResurfacingBradford Overlay (Sel. Secs.) (S) 1.49CS $161,471Completed Mar. 2016 Jun. 2016 1.49 $161,471C73004*

ResurfacingGarner,rosebud&russell Overlay (Sel Secs)(s) 5.69CS $639,235Completed Feb. 2017 Jun. 2017 5.69 $639,235C73005*

Program Management

White

June 3, 2020

* Job not shown on county map.

SUMMARY OF CONSTRUCTION PROJECTS

WHITE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

ResurfacingGeorgetown Overlay & Surf (Sel. Secs.) (S) 1.52CS $227,059Completed Apr. 2017 Aug. 2017 1.52 $227,059C73006*

ResurfacingGriffithville & Pangburn Ovrly & Surf(selsecs 2.95CS $321,690Completed May. 2018 Sep. 2018 2.95 $321,690C73007*

-ResurfacingBeebe, Higginson & McRae Overlay (Selsecs)(s) CS $694,688Completed May. 2019 Sep. 2019 - $694,688C73008*

-ResurfacingJudsonia & Kensett Overlay (S) CS $433,954Under Construction Feb. 2020 - $433,954C73009*

-ResurfacingLetona Overlay (S) CS $258,273Sub. Completed Feb. 2020 Apr. 2020 - $258,273C73011*

ResurfacingWard and McRae Overlay (Sel. Secs.) (S) 1.82 $234,382Completed Apr. 2015 Jul. 2015 4.37 $468,764C76019*

Major WideningTurner Rd. – Co. Rd. 5 (Widening) (S) 2.9964 $8,024,79210 Completed Jan. 2016 Aug. 2017 2.99 $8,024,792CA0501

-Structure & ApproachesGlaise Creek Str. & Apprs. (S) CR $1,110,819Completed Sep. 2014 Mar. 2016 - $1,110,819FA7314*

ResurfacingFaulkner Co. Line – East (Sel. Secs.) (S) 12.3436

Addt'l Rte.-Sec.: White 36-3

$1,952,1632 Completed Aug. 2010 Sep. 2010 12.34 $1,952,163FS5001

ResurfacingHwy. 67 – Hwy. 5 (S) 16.9531 $2,256,8074 Completed Aug. 2010 Jan. 2011 16.95 $2,256,807FS5002

ResurfacingHwy. 16 – Hwy. 157 (S) 9.17124 $1,723,63512 Completed Sep. 2010 Jan. 2011 9.17 $1,723,635FS5003

ResurfacingHwy. 16 – Hwy. 36 (S) 13.40310 $1,747,0431 Completed Apr. 2011 Sep. 2011 13.40 $1,747,043FS5004

ResurfacingHwy. 67 – Hwy. 157 (S) 3.09385 $450,4801 Completed Apr. 2011 Jun. 2011 3.09 $450,480FS5005

ResurfacingHwy. 258 – North (S) 8.78157 $1,254,4061 Completed Apr. 2011 Jul. 2011 8.78 $1,254,406FS5006

ResurfacingCo. Rd. 142 – Hwy. 124 (S) 0.53110

Addt'l Rte.-Sec.: Cleburne 110-6

$56,3507 Completed Apr. 2011 Jul. 2011 10.49 $1,230,885FS5007

ResurfacingHwy. 67 – East (S) 0.61258 $120,9710 Completed Apr. 2011 Jul. 2011 0.61 $120,971FS5008

ResurfacingHwy. 25 – Pangburn (S) 1.8716

Addt'l Rte.-Sec.: Cleburne 16-12

$306,07713 Completed Jun. 2011 Oct. 2011 14.09 $2,686,142FS5009

ResurfacingHwy. 16 – Hwy. 124 (S) 5.47305 $959,8993 Completed Jun. 2011 Oct. 2011 5.47 $959,899FS5011

ResurfacingIndependence Co. Line – South (S) 7.00157 $1,109,0361 Completed Jul. 2011 Nov. 2011 7.00 $1,109,036FS5013

ResurfacingHwy. 31 – Hwy. 36 (S) 7.50305 $1,177,0791 Completed May. 2012 Sep. 2012 7.50 $1,177,079FS5020

ResurfacingHwy. 167 – Jackson Co. Line (S) 10.76367 $2,805,09118 Completed May. 2012 Aug. 2012 10.76 $2,805,091FS5021

ResurfacingLonoke Co. Line – Hwy. 67 (S) 4.8631

Addt'l Rte.-Sec.: White 67-12B

$841,2594 Completed Jun. 2012 Sep. 2012 4.86 $841,259FS5024

ResurfacingLonoke Co. Line – Little Cane Creek (Shldrs.) (S) 6.5667 $1,073,08712 Completed Jun. 2012 Nov. 2012 6.56 $1,073,087FS5025

ResurfacingHwy. 124 – North (S) 3.95305 $511,8814 Completed Jun. 2012 Oct. 2012 3.95 $511,881FS5026

ResurfacingHwy. 67 – Hwy. 323 (S) 6.0036

Addt'l Rte.-Sec.: White 36-5

$1,062,6564 Completed Jun. 2012 Nov. 2012 6.00 $1,062,656FS5027

ResurfacingSearcy – West (Sel. Secs.) (S) 8.3116 $1,289,70113 Completed Apr. 2013 Aug. 2013 8.31 $1,289,701FS5028

Program Management

White

June 3, 2020

* Job not shown on county map.

SUMMARY OF CONSTRUCTION PROJECTS

WHITE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

ResurfacingHwy. 31 – Hwy. 367 (S) 15.47267 $2,524,4511 Completed Jul. 2013 Dec. 2013 15.47 $2,524,451FS5032

ResurfacingHwy. 36 – Hwy. 64 (S) 8.52367

Addt'l Rte.-Sec.: White 367-17Y

$1 - $5 M17 Programmed 8.52 $1 - $5 MFS5036

ResurfacingHwy. 11 – Hwy. 36 (S) 7.36323 < $1 M3 Programmed 7.36 < $1 MFS5039

ResurfacingFiretower Rd. – North (S) 2.76167

Addt'l Rte.-Sec.: Jackson 167-15; White 167-16

$1 - $5 M14 Programmed 4.26 $1 - $5 MFS5041

ResurfacingHwy. 25 – Hwy. 36 (S) 1.25124

Addt'l Rte.-Sec.: Cleburne 124-8; Faulkner 124-9

$326,56810 Completed Sep. 2010 Jun. 2011 7.94 $2,041,051FSX001

- Roadside AppurtenancesLake Barnett Access Parking Lot Impvts. (S) $20,255Completed Jan. 2017 Apr. 2017 - $20,255GF5112*

Base & SurfacingHwy. 13-Co. Rd.626 (Base & Surfacing) (S) 1.10CR $156,168Completed Jun. 2010 Sep. 2010 1.10 $156,168SA7377*

Base & SurfacingCo. Rd. 26-Base & Surfacing (Sel. Sec.) (S) 1.20CR $115,475Completed Apr. 2010 Jun. 2010 1.20 $115,475SA7378*

Base & SurfacingRussell City Limits-Northwest(base&surf)(s) 1.00CR $147,215Completed Jun. 2011 Aug. 2011 1.00 $147,215SA7379*

ResurfacingHwy. 267-South (Base & Surfacing) (S) 1.10CR $153,472Completed Apr. 2011 Jul. 2011 1.10 $153,472SA7380*

ResurfacingCo. Rd. 70 Sel. Sec. (Base & Surfacing) (S) 0.60CR $86,545Completed Feb. 2012 May. 2012 0.60 $86,545SA7381*

Base & SurfacingCo. Rd. 629 Sel. Sec. (Base & Surfacing) (S) 1.00CR $151,132Completed Mar. 2012 Jun. 2012 1.00 $151,132SA7382*

ResurfacingHwy. 5-East (Base & Surfacing) (S) 1.30CR $170,537Completed May. 2012 Jul. 2012 1.30 $170,537SA7383*

Base & SurfacingHwy 31-West (Base & Surfacing) (S) 1.50CR $159,805Completed Jun. 2013 Aug. 2013 1.50 $159,805SA7384*

Base & SurfacingCo Rd 26 Base & Surfacing No 2(SEL Secs)(s) 0.70CR $101,515Completed Jul. 2013 Sep. 2013 0.70 $101,515SA7385*

Base & SurfacingHwy. 385-Hwy. 36 Base & Surf (Sel. Secs.) (S) 1.00CR $146,283Completed Jun. 2014 Sep. 2014 1.00 $146,283SA7386*

Base & SurfacingHwy 385-Hwy 36 Base&srfcng No.2(sel Secs)(s) 1.00CR $140,464Completed Jul. 2014 Sep. 2014 1.00 $140,464SA7387*

ResurfacingHwy. 385-Hwy. 323 Base (S) 1.52CR $121,096Completed Jun. 2015 Aug. 2015 1.52 $121,096SA7388*

ResurfacingHwy. 385-Hwy. 323 (Surfacing) (S) 1.52CR $105,288Completed Jul. 2015 Oct. 2015 1.52 $105,288SA7389*

ResurfacingHwy. 267-Co. Rd. 629 (Base & Surfacing) (S) 1.10CR $161,957Completed May. 2016 Aug. 2016 1.10 $161,957SA7390*

ResurfacingHwy. 157-Co. Rd. 527 (Base & Surfacing) (S) 0.92CR $131,887Completed Jun. 2016 Oct. 2016 0.92 $131,887SA7391*

-ResurfacingHwy. 87 - West (Overlay) (S) CR $446,092Completed Jul. 2017 Dec. 2017 - $446,092SA7392*

ResurfacingWhite Co. Overlay (Sel. Secs.) (S) 5.37CR $528,104Completed Jul. 2018 Dec. 2018 5.37 $528,104SA7393*

-ResurfacingWhite County Overlay No.2 (S) CR $604,181Completed Jun. 2019 Oct. 2019 - $604,181SA7394*

-ResurfacingWhite County Overlay No. 3 (S) CS $614,395Under Construction May. 2020 - $614,395SA7395*

$242,780,016430.00Totals For All Projects In White County

Program Management

White

June 3, 2020

* Job not shown on county map.