1
SMART METERING
ROAD MAP FOR DESCO
NOVEMBER 2019
Contents
2
1 Introduction 04 1.1 Briefly describe smart metering 05 1.2 Briefly describe Power line communication (PLC) 05
1.3 Briefly describe Data concentrator unit (DCU) 06
2 Working Procedure 07-08
2.1 Survey 09 2.2 Prepare plan file 10
2.3 Meter installation 11-16
3 Subcontractor Information
3.1 Subcon data 3.2 Necessary information
3.3 Experience 20
4 Visual 20
4.1 Installation secnario 20
3
Abbreviations
PLC - Power line communication
DCU - Data concentrator unit
DESCO - Dhaka Electric Supply Company Limited
AMI - Advanced Metering Infrastructure
Introduction
4
This smart metering road map has been prepared to enhance the operational efficiency of
the Utility like DESCO, improving the quality of the power supply through near-real-time granular
readings provided by smart meters, enhancing the satisfaction of consumers and increasing
consumer participation. However, the benefits of smart metering is not limited only to the NEA
and go beyond various stakeholders as listed below.
Utility Consumers
Reduced Technical & Commercial losses Accurate view of electricity consumption
Improved collection efficiency More reliable supply of electricity to all
consumers
Lower cost of purchased power Higher-quality electricity supply Enhanced
grid visibility Reducing the need for voltage stabilizers Self-healing
power grid; User-friendly and transparent interface with
utilities
5
1.1Smart Meter
A smart meter is an electronic device that records consumption of electric
energy and communicates the information to the electricity supplier for monitoring and billing.
Smart meters typically record energy hourly or more frequently, and report at least daily. Smart
meters enable two-way communication between the meter and the central system.
Communications from the meter to the network may be wireless, or via fixed wired connections
such as power line communication (PLC).
1.2Power Line Communication
Power-line communication (PLC) carries data on a conductor that is also used simultaneously for
AC electric power transmission or electric power distribution to consumers. It is also known
as power-line carrier.There are many communication technologies for smart metering applications,
power line communications (PLC) have proven to be a cost-effective solution in a large number of
scenarios. Moreover, it provides distribution system operator a proprietary communication
network and innately integrates the sensing and communication functionalities. Consequently, it
has become the predominant smart metering technology.
Connection with Data
Acquisition center or master
station through radio,
Ethernet, GPRS
Smart meter
with PLC
module
6
1.3 Data Concentrator Unit
Data concentrator is one important part of Advanced Metering Infrastructure (AMI) system and
Smart prepaid system. Data concentrator is a centralized meter reading terminal, It can collect and
save various types of data of electricity meter by presetting or timing and exchange data with system
master station via wireless module (GPRS) or Ethernet. Data concentrator can reserve a large data
and can ensure that data can be stored for several years. Data concentrator sits on the loop of
secondary of the distribution transformer. Collects Meter reading from all the meters using power line
communication system. The DCU and all the meters are connected to it can be considered as a sub
system. The sub system is set up with a DCI monitoring the low voltage power zone of a distribution
transformer.
GPRS or Ethernet
Smart meter
with PLC module
7
The manpower organogram for prepaid meter installation
1. One project manager.
2. Two assistant project manager will work under project manager.
3. Four supervisors, two supervisors will work under each assistant project manager.
4. Twenty groups means total 4o technicians and 2o hhu operator, five groups will work
under each supervisor.
8
Working Procedure
Group Member in each Group
(1)
Total Group (2)
Installation Qty. Per Group
Per Day (3)
Daily Installation
Qty. 4=(2*3)
Monthly Installation
Qty. 5=(4*25)
2 or 3 20. 25 Nos. 500 Nos. 12,500 Nos.
FINISHED: Hand over the
old meter & cable with goods to
Hesing store
START:Sel ect the Area
and do survey.
Train the Customer
Preliminary
Take the new meter,cable,co
nnection material from Hexing store
Install the Prepaid
meter with cable if required
Fill up the customer
Installation form
Go to site for
Installation Prepaid Meter
9
Meter installation guideline
The installation team shall have a installation sheet instructing them what to do. The following
information shall be printed on the installation form
Customer Name Supplied by the Utility and verified by
Survey
Customer address Supplied by the Utility and verified by
Survey
Customer Number Supplied by the Utility
Old Meter Number & Reading Supplied by the Utility
Tariff Code The specific tariff to be allocated to the
customer must be identified by the tariff code
There are different categories of installations that will be required
Removal of induction & conventional digital meter and direct installation of prepayment
meter with additional wiring or service line work required
Removal of induction & conventional digital meter, re-routing of wiring with replacement
of service connection and installation of pre-payment meter potential joints shall not be
allowed in service drop cable.
Removal of service line and meter, replacement of service connection and installation of
meter.
New customer installation including service connection and installation of pre-payment
meter.
The following guide lines must be followed by the supplier during installation
of the meters
The meters shall be sealed with Ferrule Type/Twist Type seals compatible with the meters
that uniquely identify the utility person who sealed the meters.
Meters shall be tested and commissioned by the installation supervisor using the data from
the works order form to program the tariff details.
10
At the time of meter installation the customer’s induction & conventional digital meter
reading shall be captured on the order by the installation supervisor and the data returned
to the UCC. The date of commissioning is also entered onto the installation form.
The service connections shall not be replaced unless the survey indicates service line with
joints or inadequately rated service lines or bad in selected line.
All meters shall be installed indoors at a location convenient to the customer as well as
service personnel away from sources of heat and moisture.
The installation shall be symmetrical, vertical and parallel to respective walls and floors.
From the points where the service enters customers building, it shall be enclosed
in a
25mm2 PVC pipe until it enters the metering house.
At the time of installation onsite training and instruction shall be given to the customer.
Carefulness
We have to do survey very carefully. We have to confirmed first these meter belongs
which transformer. Otherwise DCU can’t collect data from the meter.
Before installing the meter we have to insert the module into the meter, otherwise DCU
can’t read the meter data.
After completing survey we have to make plan in Microsoft excel using prepaid meter
number.
Plan file Templete
11
Meter Installation
Required Tools
Sl Name of the tools
01 Pliers with PVC insulation
02 Electric Tester
03 Screw Driver Star type with PVC insulation
04 Screw Driver Flat type with PVC insulation
05 Cable Cutter
06 Nose Pliers
07 Hammer
08 Drill Machine
09 Electric Tape
Installation of Meter
Disconnect the load before connection
Connect the service cable and customer side cable according to the connection diagram
on the meter terminal cover. Output connection firstly, Input connection secondly.
When connect the cables, the metal part of cable needs to be fully contacted with two
terminal screws, and ensure that the metal part is not exposed
The terminal screws must be fixed.
Installation Diagram
MODULE
We have to insert the module into the meter before installation
12
Incoming
service
line
Customer
side
Three phase meter installation diagram
Incoming
service
line
Customer
side
Single phase meter installation diagram
13
Load
side
Single Phase
Three Phase
Connection diagram respectively single and three phase
14
DCU installation Diagram
Connection between DCU and CT
15
Successfully install DCU
16
Single
phase
smart
meter
Three
phase
smart
meter
Connection diagram between DCU and Smart Meter
20
Necessary Information
Experience
We have successfully installed around 10k nos smart meter with around 80 no DCU in
West Zone Power Distribution company Limited (WZPDCL) under Ideal Electrical
Enterprise Ltd.
Now We are working in REB 5 lacks project under Hexing Electrical co.,Ltd.
Visual
Here we have shared some visual scenario about our work.
Thank You