site reconnaissance visits for april 5, 13 and 28, 2011 at the scorpio … · 2020. 11. 28. ·...

Post on 13-Aug-2021

1 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

14 Wall Street, Suite 1702 New York, New York 10005 Tel. 212-785-9123 Fax. 212-227-1692

May 23, 2011  Mr. Adalberto Bosque Remedial Project Manager U.S. Environmental Protection Agency Caribbean Environmental Protection Division Centro Europa Building, Suite 417 1492 Poncé de Leon Avenue San Juan, Puerto Rico 00907‐4127  PROJECT:  RAC 2 Contract No.: EP‐W‐09‐002 

Work Assignment No.: 016‐RICO‐02HA  DOC. CONTROL:     3320‐016‐00869  SUBJECT:  Site Reconnaissance Notes: April 5, 13, and 28, 2011   Scorpio Recycling, Inc.   Remedial Investigation/Feasibility Study    Toa Baja, Puerto Rico  Dear Mr. Bosque:  This  letter provides a  summary of  the  conditions observed by Mr.  Jose Reyes, CDM Field Technician, during  site  reconnaissance performed  at  the  Scorpio Recycling,  Inc.  (SRI)  site on April 5, 13,  and 28, 2011. Photos of the SRI facilities taken during the subject visits are included as Attachments A, B and C. 

April 5, 2011 ‐ Site Observations  Operations:  Five people were picking  through  scrap; Mrs. Gloria Rodriguez, Mr. Manuel  Figueroa 

and three laborers.   Southern Area: No active work observed; no change apparent since prior visit, with one large vine‐

covered soil pile and one tire pile.  Northern Area: Four soil piles,  four  large scrap piles, ponding of water along an  interior  road and 

near the bases of the piles.  Central Area: Piles are mostly composed of  tires with scrap material  in various proportions, some 

puddles were observed along the interior dirt roads.  Northern Access Road: Up  to  two  feet of soil/sediment has accumulated within approximately 20 

feet of the access road as a result of a metal obstruction.  CDM awaiting access to background locations to continue OU2 soil sampling. 

 April 13, 2011 ‐ Site Observations  Operations: Five people were working,  including Mrs. Gloria Rodriguez, Mr. Manuel Figueroa and 

three  laborers. Mrs. Rodriguez  communicated  that her group  recently  submitted  to  the property owner’s  attorneys  a proposal  for  the processing of  tires. The proposal  includes  the  creation of  a platform along the Aluminum Pit, the use of water accumulated  in the pit, and reuse of the water throughout the process. Sediments will be collected separately and will be disposed at the facility.   

R2-0001228

Mr. Adalberto Bosque May 25, 2011 Page 2

Clean tires would be stored in the warehouse. Her group plans to start clearing the warehouse while waiting for approval. 

Equipment: Digger.  Other:  Mrs.  Rodriguez  communicated  that  her  group  is  willing  to  share  photographs  and 

information documenting their activities performed at the SRI site upon request.  April 28, 2011 ‐ Site Observations  Operations:  Five  people  picking  through  scrap,  segregating material: Mrs.  Gloria  Rodriguez, Mr. 

Manuel Figueroa and three laborers.   Equipment at the Site: Digger, Bobcat and Track Excavator  Southern Area: No active work observed; no change apparent since prior visit with one  large vine‐

covered soil pile and one tire pile.  Key Observation: Apparently some new material has been brought to the facility  Northern Area: Four soil piles,  four  large scrap piles, ponding of water along an  interior  road and 

near the bases of the piles.  Central Area: Piles are mostly composed of  tires with scrap material  in various proportions, some 

puddles  were  observed  along  the  interior  dirt  roads.  New  clearing  in  the  area  suggest  that displacement and/or removal of material had occurred at these areas. 

Northern Access Road: Up to 2 feet of soil/sediment has accumulated within approximately 20 feet of the access road as a result of a metal obstruction. 

Monitoring Wells: Both wells in good condition.  Other: The Warehouse has been cleared.  Key Issues in Moving the RI Forward  SRI remains partially operational. It is apparent that new material has been discarded at the facility.  

Current  conditions within  the Northern Area would not  support  implementation of  the proposed subsurface investigation.  

Site  Clearing:  The Northern Area  is  not  clear  and  some  previously  cleared  portions  now  contain scrap and are the location of ongoing work at the property.  Areas determined to be 'cleared' by SRI should  be  free  and  clear  of  waste,  scrap,  and  other metallic  debris  protruding  through,  visible within, or otherwise  identifiable near  the surface, such  that surveys and subsurface  investigations can be efficiently and safely performed. Surveys are to include (1) situation of a grid to establish soil sampling locations and (2) a subsurface geophysical survey to investigate the presence of materials including large objects which may contain waste or inhibit subsurface exploration and establish the location  of  buried  utilities.  Performing  the  surveys  before  the  site  is  appropriately  cleared  will generate  less  informative data, result  in additional mobilization costs of surveyors and equipment, potentially damage downhole equipment, and potentially impact subsurface conditions. 

Eliminate  potential  recontamination:  Via  enforcement,  such  that  no  portion  of  the  site  that  is cleared and/or investigated is re‐inhabited by scrap/waste/operations. 

Establish site controls: It is critical to project safety and execution that (1) PRP establish operational practices and physical controls at SRI to eliminate potential migration of contaminants offsite or to areas investigated to date, and (2) PRP eliminate further damage to existing site wells and any other project‐related installations due to SRI operations. 

   

R2-0001229

Mr. Adalberto Bosque May 25, 2011 Page 3 Information Sharing: CDM respectfully requests that SRI share the following: (a) site Utility Plans to 

support clearance activities  for the subsurface  investigation,  (b) any updates to PRP's schedule  for clearing  remaining  areas  and  (b)  an  explanation of how  PRP will  control  the  site  perimeter with respect to potential contaminant migration. 

 Schedule  CDM and EPA will continue periodic site visits to assess the progress of clearing activities.  If you have any questions concerning the notes for the site visit, please contact me at your earliest convenience at (787) 722‐5410.  Very truly yours,  CDM FEDERAL PROGRAMS CORPORATION  

 Brendan MacDonald, P.E., LEED AP® RAC 2 Site Manager  Enclosure 

cc: M. Valentino, CDM RAC 2 Document Control 

R2-0001230

A

Attachment A Photographs April 5, 2011

R2-0001231

Former Loading and Aluminum Sorting Area

Looking W

R2-0001232

Clearing of the Aluminum Pit 

R2-0001233

Operations at Central Area

Looking E

R2-0001234

Maintenance Shop Area

Looking E

R2-0001235

Behind the Mechanic Shop

Looking E

R2-0001236

Drop‐Off and Torch Cutting Area

Looking E

R2-0001237

M i t Sh d C t l AMaintenance Shop and Central Area   

Looking W

R2-0001238

Work Shop Storage

R2-0001239

Clearing in Warehouse

R2-0001240

C t l A M dCentral Area Mounds

Looking E

R2-0001241

A l th W i h St tiArea along the Weigh Station

Looking E

R2-0001242

Monitoring Well Areas/Conditions

MW‐4A on left, MW‐1 on right

R2-0001243

Sorting and storage area

R2-0001244

Several places with oil spills remain

R2-0001245

Northern Accessway

Looking N

y

R2-0001246

A

Attachment B Photographs April 13, 2011

R2-0001247

Loading Area and Former Aluminum Sorting Area

Looking E

R2-0001248

Apparently some new material has been dropped off at the site near the Scale Area

R2-0001249

Operations Behind Maintenance Area

R2-0001250

Maintenance Area

R2-0001251

Central Operations Area

Looking E

R2-0001252

Drop Off and torch Metal Cutting Area

R2-0001253

D b i t id th N th E tDebris outside the Northern Entrance 

Looking S

R2-0001254

E i t ki t th SitEquipment working at the Site   

R2-0001255

Cleared Warehouse

R2-0001256

Central Area / Northern Scrap Mounds

Looking E

R2-0001257

A l th W i h St tiArea along the Weigh Station

Looking W

R2-0001258

Monitoring Wells: Area / Conditions

MW‐1 on left (under tires); MW‐4A to the right

R2-0001259

Material segregation apparently occurring

R2-0001260

Former Central Area Crusher/Shear buried at the Central Area 

Looking E

/

R2-0001261

Northern Accessway / Entrance Looking S

R2-0001262

A

Attachment C Photographs April 28, 2011

R2-0001263

Loading / Former Aluminum Sorting Area

Looking N

R2-0001264

Clearing of Aluminum Pit 

R2-0001265

Operations at Central Area

Looking N

R2-0001266

Mechanic Shop Area

Looking E

R2-0001267

Behind the Maintenance Shop Area

Looking E

R2-0001268

Drop Off and Metal Cutting AreaDrop Off and Metal Cutting Area

Looking E

R2-0001269

Scale Area   

R2-0001270

Cleared WarehouseCleared Warehouse

R2-0001271

Central Area Scrap Mounds

Looking E

R2-0001272

A l th W i h St tiArea along the Weigh Station

Looking E

R2-0001273

Monitoring Wells: Local Area / Conditions

MW‐4A to left, MW‐1 on right (under tires)

R2-0001274

Sorting and Storage

R2-0001275

Several places with oil spills remain

R2-0001276

Former Crusher/Shear Buried at the Central Area 

Looking E

R2-0001277

Northern Accessway / Entrance Looking N

R2-0001278

top related