SICURO Parapet
INSTALLER MANUAL
VERSION 2 March 2018
-
Product introduction
Sicuro parapets are made from galvanised steel posts, rails & rail joints. These are bolted together with galvanised & stainless steel fasteners onto anchors to create a permanent vehicle restraint system.
The Sicuro parapet has post centres @ 2000mm Maximum post centres at the end of Sicuro parapets are 2000mm Maximum rail overhangs at the end of Sicuro parapets are 450mm
There is no statutory requirement to install safety fences or barriers but if they are provided risk assessments must show that they create no additional hazard.
The system has been tested in accordance with parts 1 & 2 of BS EN 1317.
When used on motorways and trunk roads it must also conform to the current requirements of Highways England.
Locations and usage will be determined by an appropriately qualified designer.
This manual does not include design criteria, and is therefore to be used only to demonstrate competence in handling and installation.
However a basic understanding of the performance value of the system is included to assist in prevention of misuse. Vehicle restraint system is categorized according to containment value (N1, N2, H1, H2 etc) and working width (W1, W2, W3, etc).
These values are obtained as a result of dynamic (actual impact) tests using a variety of different vehicles to produce the containment and working width values.
Typical values in relation to SICURO Parapets are shown below.
PARAPET CONTAINMENT WORKING WIDTH
IMPACT SEVERITY LEVEL
UNFACTORED ULTIMATE MOMENT kNm
CO EXISTING SHEAR kN
ULTIMATE SHEAR kN
Sicuro H2 W2 CLASS B 33.1 79.9
-
Requirements to install, inspect & repair Sicuro Parapets
In essence any company wishing to install Parapets on motorways and trunk roads must work to the specifications laid out in the sector scheme document. This will ensure compliance with Highways England requirement that all companies must have third party certification for a Quality Management Scheme that is administered in accordance with a National Highways Sector Scheme as mentioned earlier.
To ensure that the installation, inspection & repair is both appropriate and adequate all installers must also be qualified to the standards laid out in sector scheme document 5b.
This course has been registered with Lantra Awards and is recognised as being compliant with Sector Scheme 5b. Those who successfully complete the course will be issued with a Lantra Awards registration card. This will be in addition to any registration card that has already issued in respect any other type of fencing.
All sector scheme documents are published by UKAS (United Kingdom Accreditation Service) and can be viewed on their web site in full.
-
Page 4- March 2018
Personal Protective Equipment Required
• Gloves • Hard hat • Steel toe cap boots • HI-VIS Vest (with sleeves) or Jacket to Class III • HI-VIS trousers
Additional PPE if cutting, drilling, etc
• Goggles • Dust Mask • Ear defenders
Installation Tools
One set per team
• Ratchet wrench and sockets • Open jaw I ring spanners • Hammer / mallet • Files • Torque wrench • Tape measure / ruler & pencil
Generic Information & drawings
• Installers Manual • S/GA-01 rev00 issued 21/3/12 = Sicuro Parapets General Details • BLG 5190011 = Sicuro Parapets Main Drawing • BLG 5190041 = Sicuro Parapets Joint Detail •
Contract Specific Information
• Method statement – How the parapet will be installed safely • Risk assessment – What risks are present & how their effects are removed or
reduced – needs to be reviewed & amended if site conditions or method change
• Delivery instruction sheet – Site address & general details • Delivery Note – Record of components sent to site • Layout drawing – Specific drawing for parapet location • Parts list – list of all components required for the parapet • Erection check sheet – completed on site as a record of installation
-
Page 5- March 2018
Sicuro Parapet Components
IMPACT RAIL HOLES FOR RAIL JOINTS
IMPACT RAIL SLOT FOR ‘T’ BOLT
-
Page 6- March 2018
TOPRAIL VIEW ON END
1M HIGH POST
-
Page 7- March 2018
M24 SETSCREW, ST/ST WASHER,NYLON TOPHAT, M27 X56mm O/D GALV WASHER
T BOLT
-
Page 8- March 2018
T BOLT LOCATOR PLATE
IMPACT RAIL JOINT
-
Page 9- March 2018
TOP RAIL JOINT
RAILS PACKED FOR TRANSPORT
POSTS PACKED FOR TRANSPORT
-
Page 10- March 2018
Safety zones during installation reminder
During installation Highways Agency Chapter 8 safety zones must be established and maintained.
It is not possible to install the parapet unless such a safety zone is provided. It is suggested that a work area of not less than 1.5 metre will be required between the parapet and the safety zone.
On motorways the safety zone must be 1.2m regardless of any temporary speed limit
On other roads if there is a limit of 40mph or less then this may be reduced to 0.5m
Only leave the work area when it is absolutely essential.
Installers must not store materials in the Safety Zone.
Safety Zones for Offloading and Loading
As previously stated the swinging load must be controlled with correctly fixed rope tethers. The load must not be allowed to swing over or into live traffic lanes.
Suitable safety zones will need to be considered as part of the planning process taking into account the lengths of the units being delivered.
Strong winds which will affect the controllability of the suspended load must be risk assessed
The load should be lowered so that it is immediately above the ground as soon as it is clear of the lorry and then jibbed out to the final position.
-
Page 11- March 2018
LIFTING EQUIPMENT
Required basic checks by the operator before using the lifting equipment
• Current Lift Plan and associated RAMS available • What is the safe working load of the equipment? • Are there are any defects with the equipment? • There are no overhead cables • The vehicle is stabilised • The vehicle is on reasonably level ground.
Pre-lifting checks by the operator
• Competent and experienced • Check the safe working load of any slings or chains • Establish the weight of the load and accessories • Check that the area to receive the load is clear • Ensure that the load will not swing out of control, use tag lines • Provide protection between sharp edges of the load and slings • Ensure that the load is balanced.
Lifting restrictions
The operator must not allow
• The load to swing the load over any other workers, exclusion zones • Others to walk under a suspended load • The load to swing out of control • The jib or load to swing into a live traffic lane • Not exceed the safe working load
Operators post lifting procedure
• The operator must check to ensure no damage has been caused to the slings • Slings have in date certification and SWL identified • Secure the crane in such a way that it cannot move during the transit • Length of Slings • Slings should not be longer than the minimum required to give the correct angle
between the legs. If an excessive length of chain or sling is used, crane movements will take longer for the hook to be in a position where it can be reached.
-
Page 12- March 2018
Lifting the Parapet components
COMPONANT SIZE WEIGHT SICURO TOPRAIL 8.090mm LONG 120KG
SICURO IMPACT RAIL 8.090mm LONG 60KG
SICURO POST 1M HIGH 51KG
SICURO TOPRAIL JOINT 1No JOINT PLATE 770mm X 70mm X 30mm 2No CATCH PLATES 240mm X 70mm X 20mm
10.5KG 2 X 3KG = 6KG
SICURO IMPACT RAIL JOINT 90mm O/D X 4mmW/T @ 522mm LONG
4KG
SICURO ‘T’ BOLT IMPACT POST TO RAIL FASTENER ASSEMBLY
M16 X 60mm ‘T’ BOLT CLAMP PLATE M16 NYLON WASHER M16 FLAT WASHER GALV M16 HEX NUT GALV
325g
SICURO ‘BENT’ BOLT IMPACT JOINT FASTENER ASSEMBLY
M16 X 110mm ‘LOCK’ DOME HEAD BOLT M16 FLAT WASHER MI6 NUT
250g
SICURO TOP RAIL JOINT BOLT ASSEMBLY
M20 X 50mm HEX SET ST GALV M20 FLAT WASHER GALV
200g
ANCHOR BOLT ASSEMBLY M24 X 90mm HEX SET ST/ST M24 FLAT WASHER ST/ST M24 NYLON TOPHAT M27 X 56mm O/D X 4mm THK FLAT WASHER GALV
500g
SICURO POST TO TOPRAIL BOLT ASSEMBLY
M20 X 110mm HEXAGON HEAD BOLT M20 FLAT WASHER M20 NUT
250g
Lifts that contain multiple components can be calculated from the table above. Allowance should be made for weight of pallets / packaging included in the Lift Plan.
-
Page 13- March 2018
-
Page 14- March 2018
WORKING AT HEIGHT Definition of Height The HSE do not recommend a minimum height where edge protection should be provided. The risk assessment should identify the risk of a fall & advise measures to prevent a fall happening. A fall from a height of 150mm could cause a twisted ankle & therefore action must be taken to prevent a fall.
The type & duration of the works will determine the measures used to prevent falls.
Working at height on parapets Most parapet works take place at locations where the parapet will provide a permanent edge protection that prevents vehicles & pedestrians falling from height. The location is almost certain to have falls from height as a risk to the parapet installers therefore the risk assessment must address the risk of operatives & materials falling.
The most effective method of edge protection is a scaffold on the outside of the parapet that allows free access to the parapet anchors.
Parapet installers must not adjust or tamper with any scaffold or edge protection provided.
If installers become aware of defects in the edge protection, works must stop & the client informed.
Works must only proceed with a safe edge protection in place.
The main contractor will sometimes use the cradle anchors provided for the parapet as anchors for an edge protection scaffold. It will be necessary to remove the edge protection to install the parapet.
Parapet installers must not remove the edge protection to gain access to the parapet.
Once the edge protection is removed, alternative methods need to be found to prevent men & materials falling from the parapet
Where no edge protection is available or it has been removed prior to parapet installation, it may be possible for the parapet installers to install the parapet wearing a safety harness secured to a suitable anchorage point.
The safety harness must be free from defects & adjusted to fit the wearer.
The lanyard must be free from defects & the spring loaded clips must have a screw lock.
The anchorage for the lanyard must be capable of holding the load of operatives if they fall.
The lanyard should not be secured to a vehicle; there is a risk that the vehicle may move whilst installers are tethered.
There must be a method of preventing materials & tools from falling.
Hand tools can be tied to installer’s wrist or harness.
Materials cannot be tethered to the installer.
Access for pedestrians, vehicles & other trades under the area of works must be prohibited
A method of recovery for a fallen installer must be advised & recorded prior to works starting.
-
Page 15- March 2018
Mobile Elevated Work Platform (MEWP)
Two types of MEWP are available for parapet works A Cherry Picker can be used to access the works from under the parapet A specialist inspection platform that goes over & returns back to the parapet.
The MWEP is delivered to site by the hire company
Operatives must be trained to operate the MEWP
A harness must be worn & tethered whilst working in a MEWP
-
Page 16- March 2018
Prior to erection of the parapet the anchors will be tested & results recorded on Site test report sheet GQF-54 Iss 2 June 09
The ratio of anchors to be tested at site is determined as below
1 No anchor test on each length parapet where the number of cradle anchors is 30 or less 2 No anchor test on each length parapet where the number of cradle anchors is greater than 30 & less than 60 3 No anchor test on each length parapet where the number of cradle anchors is greater than 60 & less than 90
An additional test will be undertaken for additional anchors in the ratio of 1:30
If an anchor fails the test then the parapet must not be installed, the parapet proprietor is to be Informed
Test anchors
1. Confirm with client, which anchor location will be tested.
2. Set up rig above anchor, level rig with adjustable screwed legs.
3. Place testing adaptor over anchor and connect with M20X90 stainless steel bolt.
4. Pump jack to take up slack in rig.
5. Place DTI gauge plunger onto head of bolt, set gauge to zero.
6. Load anchor @ 10kn for 30 seconds and record reading on DTI.
7. Repeat this procedure @ 20kn and in 10kn increments up to 70kn, record readings.
8. At 80kn lock off the hydraulic jack and hold the pressure for 5 minutes, record the reading.
9. During this last test monitor the reading on the force gauge, should it drop below 80kn, pump up as required.
10. If the anchor moves more than 1mm it has failed.
11. Slowly release pump pressure and record the return pressure on the DTI.
12. Remove test rig.
13. Ensure a test record sheet is completed for each anchor and a copy is returned with site
records to the contracts manager.
-
Page 17- March 2018
Installation of Parapet
OPERATION METHOD TOOLS REQUIRED
FIXINGS / MATERIALS REQUIRED
DOCUMENTS REQUIRED
CHECK ANCHOR POSITIONS
MEASURE DISTANCE BETWEEN ANCHOR POSITIONS TO CONFIRM AS BUILT DIMENSIONS
TAPE MEASURE
NONE
LAYOUT DRAWING
PLACE POST ON ANCHOR
PLACE 20mm THICK PACKER IN CENTRE OF ANCHOR CLUSTER.
PLACE 1No St/St FLAT WASHER, 1No Galv FLAT WASHER & 1 No NYLON TOPHAT ONTO M24 FIXING
PLACE POST ONTO PACKER & SCREW M24 FIXINGS INTO ANCHOR THROUGH BASEPLATE
PLUMB POST TO UPRIGHT POSITION
TIGHTEN SETSCREWS TORQUE 50-60Nm
REPEAT AT ALL ANCHOR POSITIONS
WRENCH / SOCKET OR SPANNER TO SUIT M24 HEX SET
SPIRIT LEVEL
PARAPET POST
FOR EACH PARAPET POST
4No M24 X90 HEX-SETS
4 No M24 St/St FLAT WASHERS
4 No M27 Galv FLAT WASHERS
4No M24 NYLON TOPHAT WASHERS
INERT PACKERS
LAYOUT DRAWING
PARTS LIST
LAYOUT RAILS DISTRIBUTE & LAY IMPACT & TOPRAILS IN FRONT OF PARAPET POSTS RELATIVE TO THEIR FINAL POSITION
TAPE MEASURE
PARAPET RAILS LAYOUT DRAWING
PARTS LIST
FIT IMPACT RAILS TO POSTS
PLACE LOWER IMPACT RAIL INTO POSITION IN FRONT OF PARAPET POSTS
INSERT M16 ‘T’ BOLT INTO RAIL & ROTATE 90 DEGREES
PLACE LOCATOR PLATE ONTO ‘T’ BOLT/ RAIL
PLACE NYLON WASHER ONTO ‘T’ BOLT TO LOCK BOLT & LOCATOR PLATE IN POSITION
WRENCH / SOCKET OR SPANNER TO SUIT M16 HEX SET
PARAPET POSTS
PARAPET IMPACTRAILS
FOR EACH POST TO RAIL LOCATION
1No M16 X 60 ‘T’ HEAD BOLT GALV
1No LOCATOR PLATE GALV
1No NYLON WASHER
1No M16 FLAT WASHER GALV
1No M16 NUT GALV
LAYOUT DRAWING
PARTS LIST
-
Page 18- March 2018
REPEAT FOR ALL POST POSITIONS ON RAIL
LIFT RAIL ON TO POST WITH ‘T’ HEAD BOLT THROUGH HOLE IN FACE OF POST
PLACE WASHER & NUT ON ‘T’ BOLT FROM REAR OF POST FACE
TIGHTEN M16 NUT TORQUE 40-50Nm
REPEAT FOR ALL POST TO IMPACT RAIL CONNECTIONS
FIT TOP RAILS TO POSTS
PLACE TOP RAIL INTO POSITION IN FRONT OF PARAPET POSTS
LIFT TOPRAIL ONTO TOP OF POSTS ENSURE THAT LOCATING LUG ON TOPRAIL IS ON THE SIDE OF THE POST AWAY FROM DIRECTION OF TRAFFIC
PLACE M20 BOLT THROUGH HOLE IN TOP OF POST & LOCATING LUG IN TOPRAIL ENSURE THAT BOLT HEAD IS SAME SIDE AS POST
PLACE WASHER & NUT ON M20 BOLT
TIGHTEN M20 NUT TORQUE 40-50Nm
REPEAT FOR ALL POST POSITIONS ON TOP RAIL
WRENCH / SOCKET OR SPANNER TO SUIT M20 HEX SET
PARAPET POSTS
PARAPET TOP RAILS
FOR EACH POST TO TOP RAIL LOCATION
1No M20 X 110 HEX HEAD BOLT GALV
1No M20 FLAT WASHER GALV
1No M20 NUT GALV
LAYOUT DRAWING
PARTS LIST
-
Page 19- March 2018
PLACE & SECURE RAIL JOINT IN IMPACT RAILS
INSERT RAIL JOINT INTO OPEN END OF RAIL
ALIGN HOLES IN RAIL JOINT WITH HOLES IN RAIL
PLACE 1No M16 X 110 LOCK BOLT THROUGH HOLE IN RAIL/RAIL JOINT (HEAD & BOLT ON TOP OF RAIL)
PLACE WASHER ON M16 LOCK BOLT ON UNDERSIDE OF RAIL
TIGHTEN M16 NUT ONTO M16X LOCK BOLT ON UNDERSIDE OF RAIL TORQUE 40-50Nm
REPEAT FOR ALL POSITIONS IN RAIL JOINT
REPEAT FOR ALL RAILS
WRENCH / SOCKET OR SPANNER TO SUIT M16 HEX SET
PARAPET IMPACT RAIL
IMPACT RAIL JOINT
FOR EACH IMPACT RAIL JOINT
6No M16 X 110 LOCK BOLTS GALV
6No M16 FLAT WASHERS GALV
6No M16 GALV NUTS
LAYOUT DRAWING
PARTS LIST
PLACE & SECURE RAIL JOINT IN TOP RAIL
SLIDE JOINT PLATE INTO END OF RAIL
INSERT CATCH PLATE INTO THROUGH RAIL & INTO JOINT PLATE
SECURE CATCH PLATE TO JOINT PLATE WITH M20 X 50mm SETSREWS TORQUE 40-50Nm
WRENCH / SOCKET OR SPANNER TO SUIT M20 HEX SET
PARAPET TOP RAIL RAILS
FOR EACH TOP RAIL JOINT
1No TOP RAIL JOINT
2No CATCH PLATES
4No M20 X 50mm SETCREWS GALV
2No M20 FLAT WASHER GALV
LAYOUT DRAWING
PARTS LIST
FIT ADDITIONAL RAILS TO POSTS
RAILS ARE SLIDE ON PRE-CEEDING RAIL / RAIL JOINT
REPEAT OPERATIONS
FIT IMPACT RAILS TO POSTS
FIT TOP RAILS TO POSTS
PLACE & SECURE RAIL JOINT IN IMPACT RAILS
PLACE & SECURE RAIL JOINT IN IMPACT RAILS
WRENCH / SOCKET OR SPANNER TO SUIT M16 HEX SET
PARAPET POSTS
PARAPET IMPACT RAILS
PARAPET TOP RAIL RAILS
IMPACT RAIL JOINT
TOP RAIL JOINT
GALV FIXINGS
LAYOUT DRAWING
PARTS LIST
-
Page 20- March 2018
LINE & LEVEL PARAPET
IDENTIFY POST LOCATIONS WHERE POSTS ARE TO BE RAISED OR LOWERED TO CORRECT PARAPET LEVEL
AT POST LOCATION LOSSEN HOLDING DOWN FIXINGS ADJUST PACKING UNDER BASEPLATE TO CORRECT HEIGHT
TIGHTEN HOLDING DOWN FIXINGS TORQUE 50-60Nm
REPEAT AT REQUIRED POST LOCATIONS UNTIL PARAPET LEVEL
WRENCH / SOCKET OR SPANNER TO SUIT M24 HEX SET
PACKERS
INSPECT PARAPET
INSPECT TO ENSURE THE FOLLOWING
ALL FIXINGS LOCATED & TIGHTENED
POSTS INSTALLED AT CORRECT POSITIONS
RAILS INSTALLED AT CORRECT POSITIONS
ALL RAIL JOINTS INSERTED AT CORRECT POSITIONS
COMPLETE INSPECTION CHECK SHEET WITH CLIENT
TORQUE WRENCH
SOCKETS TO SUIT M16, M20 & M24 FIXINGS
LAYOUT DRAWING
PARTS LIST
ERECTION CHECK SHEET
-
Conformity, Maintenance and Repair
Page21- March 2018
General Information Where maintenance or repairs are required to be carried out, the installation procedure for installation in the forgoing paragraphs shall be followed unless otherwise stated.
If not subjected to impact damage, special corrosion conditions such as a chemical spillage, vandalism or theft of components, relatively little maintenance will be required. It is encouraged that the following is regarded as the minimum level of attention that will be afforded the system.
Conformity New works will be initially inspected to ensure the system has been installed to the correct specification and ‘signed off’ by the installer in accordance with Sector Scheme Document 5B. All fasteners are tightened to the specified torque and that random checks of torques have been made with a calibrated torque wrench. System heights, with an accepted tolerance of ± 30mm (+30 -0 for railways) are to be confirmed with relevant the drawings. Post spacing tolerances must not, however, become cumulative. Remove any old / unused fittings from fencing installations.
Maintenance Repairing damaged galvanised coatings Damaged areas of galvanised protective coatings can be repaired by removing any rust from the steel and applying of a 150 micron coat of zinc enriched spray paint. This procedure complies with EN ISO 1461, 1999 clause 6.3 and does not apply to components that are damaged or thinned in such a way as to affect their integrity should an impact occur.
Routine Inspection For the Highway England network, a weekly drive - past conducted by the ISU crews will highlight unreported impact damage. More frequent inspections may be needed in areas of high risk and if so, these should be dealt with on a local basis. Detailed inspections on foot should be undertaken every 5 years for systems less than 10 years old, for older systems a 2 yearly check should be conducted in order that instances of significant corrosion can be noted and acted upon. For other roads, an inspection should be carried out in accordance with the Local Authorities standing procedure but should not exceed 6 monthly. For other roads, an inspection should be carried out in accordance with the Local Authorities standing procedure but should not exceed 6 monthly.
Repair The straightening of damaged components is not allowed and such components will be replaced. All fasteners in the area of the impact shall be replaced with new fasteners irrespective of their apparent condition.
A check / inspection of the system, either side of the area of impact will be conducted to ascertain if further damage has resulted. If damage is seen, or suspected, then the area of repair should be extended to encompass this. Posts in this area should be inspected with the inclusion of the anchorage. If the anchor has failed or is suspected of having failed, a test should be conducted in accordance with Anchor Testing Method & recorded on GQF-54 Iss2 June 09 to ascertain if anchor replacement is required.
Where fasteners at damage interface are found to be problematic at the time of replacement, suitable means shall be employed to remove the offending fixing in such a way as to ensure that where possible the undamaged components remain serviceable
-
Dragonby V
ale Enterprise Park
North Lincolnshire, D
N15 8
XFTel: 0
1724 2
89119 Fax: 0
1724 2
81478
Mannaberg W
ayScunthorpe
Total Num
ber of Posts:-Total N
umber of R
ails/Panels:-
Total Length:-
DRAW
ING
NO
T TO B
E SCALED
ALL D
IMEN
SIO
NS IN
MILLIM
ETRES
UNLES
S N
OTED
OTH
ERW
ISE
IF IN D
OUBT, A
SK
Sicuro Installation Test Parapet
Sicuro Test 0
1A3
L. Lomax
01
/09
/14
Not to S
cale
15,6
20 lm
86
-
Dragonby V
ale Enterprise Park
North Lincolnshire, D
N15 8
XFTel: 0
1724 2
89119 Fax: 0
1724 2
81478
Mannaberg W
ayScunthorpe
Total Num
ber of Posts:-Total N
umber of R
ails/Panels:-
Total Length:-
DRAW
ING
NO
T TO B
E SCALED
ALL D
IMEN
SIO
NS IN
MILLIM
ETRES
UNLES
S N
OTED
OTH
ERW
ISE
IF IN D
OUBT, A
SK
Sicuro Instillation Test Parapet Joints
Sicuro Test 0
2A3
L. Lomax
01
/09
/14
Not to S
cale
Product introductionThis manual does not include design criteria, and is therefore to be used only to demonstrate competence in handling and installation.Personal Protective Equipment RequiredSafety zones during installation reminderOnly leave the work area when it is absolutely essential. Installers must not store materials in the Safety Zone.
LIFTING EQUIPMENTWORKING AT HEIGHTWorking at height on parapetsMobile Elevated Work Platform (MEWP)Prior to erection of the parapet the anchors will be tested & results recorded on Site test report sheet GQF-54 Iss 2 June 09Test anchorsInstallation of ParapetGeneral InformationConformityMaintenanceRoutine InspectionRepair