ship self def (engage: hard kill)€¦ · b. program change summary ($ in millions) fy 2011 fy 2012...
Post on 28-Jul-2020
3 Views
Preview:
TRANSCRIPT
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 1 of 23 R-1 Line #128
Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: Hard Kill)
COST ($ in Millions) FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total CostTotal Program Element 35.284 6.631 64.079 - 64.079 30.412 17.061 6.510 6.697 Continuing Continuing0167: 5in Rolling Airframe Missile 1.537 1.280 1.297 - 1.297 1.322 1.345 1.343 1.369 Continuing Continuing0173: NATO Sea Sparrow 11.747 5.351 32.005 - 32.005 29.090 15.716 5.167 5.328 Continuing Continuing3342: Griffin Missile 22.000 - 30.777 - 30.777 - - - - 0.000 52.777
A. Mission Description and Budget Item JustificationThis program element provides funding for the development of systems that fulfill a portion of the third phase of the Ship Self Defense: Engage Hard Kill. Developmentin this line will focus on hard kill capabilities in which missiles are used to intercept incoming Anti-Ship Cruise Missiles (ASCM). ENGAGEMENT: Missile and systemimprovements necessary to meet their requirements are being addressed via NATO SEASPARROW Missile System (NSSMS) (0173), 5" Rolling Airframe Missile(RAM) (0167), Phalanx CIWS SeaRAM (9853A), Griffin and Spike missile (3342). Missile improvements include improved kinematic performance plus advancedseeker and low elevation fusing/warhead capability improvements. System improvements include incorporation of Phalanx detection capability into RAM system(SeaRAM), future concepts studies and self-destructing ammunition, and Future Phalanx Next Generation Improvements. New system developments includeintegration of Griffin missile into Patrol Craft (PC) and development of Spike missile system. Missile systems demonstration to include Javelin, Spike and Griffin toassess weapons effectiveness in a maritime environment.
B. Program Change Summary ($ in Millions) FY 2011 FY 2012 FY 2013 Base FY 2013 OCO FY 2013 TotalPrevious President's Budget 5.860 6.631 4.059 - 4.059Current President's Budget 35.284 6.631 64.079 - 64.079Total Adjustments 29.424 - 60.020 - 60.020
• Congressional General Reductions - - • Congressional Directed Reductions - - • Congressional Rescissions - - • Congressional Adds - - • Congressional Directed Transfers - - • Reprogrammings 29.500 - • SBIR/STTR Transfer -0.046 - • Program Adjustments - - 60.052 - 60.052• Rate/Misc Adjustments - - -0.032 - -0.032• Congressional General ReductionsAdjustments
-0.030 - - - -
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 2 of 23 R-1 Line #128
Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: Hard Kill)
Change Summary ExplanationFY 2011 Reprogramming increase provides funding for Cyclone Patrol Craft (PC) integration with Griffin Missile System (GMS) and DEMO of Javelin, Spike andGriffin.
FY 2013 increase provides funds for Evolved Sea Sparrow Missile BLK1 (ESSM) Test, ESSM BLK 1 integration into SSDS MK2 upgrade on LHDs, risk reductionefforts for ESSM BLK 2,and Stalker Long Range Electro Optic(EO)/Infra Red (IR)/Laser Range Finder (LRF)System. Funding also increased for Cyclone PatrolCraft (PC) integration with Griffin Missile System (GMS) and development of Spike Missile System to support a CENTCOM requirement.
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 3 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
COST ($ in Millions) FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost0167: 5in Rolling Airframe Missile 1.537 1.280 1.297 - 1.297 1.322 1.345 1.343 1.369 Continuing ContinuingQuantity of RDT&E Articles 0 0 0 0 0 0 0 0 0
A. Mission Description and Budget Item JustificationThe purpose of this program is to develop a surface-to-air self-defense system utilizing a dual mode, passive Radio Frequency/Infrared 5" RAM. The baseline system(Block 0) provides a self-defense capability against active radar-guided anti-ship missiles and was developed on an equal cost share basis with the Government of theFederal Republic of Germany. The RAM Block 1 provides a capability against passive anti-ship missiles, very low altitude missiles, and maneuvering missiles throughthe incorporation of an infrared all-the-way mode seeker and improved fuze. The RAM Block 1 MOD 3 upgrade program, which provides an additional capability againsthelicopters, aircraft and surface craft, is a Cooperative requirement of the U.S. and Federal Republic of Germany agreed to in a Memorandum of Agreement (MOA)signed by both parties. FY 2011-2017 funding continues development and testing of a Block 2 upgrade to the RAM. This upgrade will allow RAM to regain battle spacelost to emerging, more maneuverable ASCM threats. This system is designed to counter anti-ship cruise missile raids and other threats to provide for ship survivabilitywith accurate terminal guidance, proven lethality, and no shipboard post launch dependence.
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013Title: 5in Rolling Airframe Missile Block 2 Development and Test
Articles:FY 2011 Accomplishments:FY 2011 funds continued development and support of RAM Block 2 upgrade.FY 2012 Plans:FY 2012 funds test effortsFY 2013 Plans:FY 2013 funds test efforts
1.4520
1.1650
1.1840
Title: 5in Rolling Airframe Missile Block 2 TravelArticles:
FY 2011 Accomplishments:FY 2011 funds travel.FY 2012 Plans:FY 2012 funds travelFY 2013 Plans:
0.0850
0.1150
0.1130
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 4 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013FY 2013 funds travel
Accomplishments/Planned Programs Subtotals 1.537 1.280 1.297
C. Other Program Funding Summary ($ in Millions)
Line Item FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost• OPN 5238: RAM 6.763 3.128 1.185 0.000 1.185 0.502 0.761 1.768 1.542 Continuing Continuing• WPN 2242: RAM 99.649 66.197 66.769 0.000 66.769 67.652 82.923 84.345 85.799 Continuing Continuing
D. Acquisition StrategyThe RAM Program uses directed sole source contracts with Raytheon Missile Systems Company, Tucson, AZ.
E. Performance MetricsSuccessfully achieve Milestone C. Successfully achieve Development/Operational Milestones.
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 5 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
Product Development ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Primary HardwareDevelopment SS/CPFF Raytheon:Tucson/
Louisville 7.434 - - - - 0.000 7.434
Primary Hardware DevSupport WR China Lake:CA 1.266 - - - - 0.000 1.266
Block 1 Eng/Interface Support SS/CPFF Raytheon:Tucson/Louisville 0.400 - - - - 0.000 0.400
Block 1 MOD 3 InterfaceSupport C/CPFF JHU/APL:MD 0.981 - - - - 0.000 0.981
Block 2 Upgrade SS/CPAF Raytheon:Tucson/Louisville 134.529 - - - - 0.000 134.529
Block 2 Upgrade WR China Lake/ NRL/Dahlgren:CA/VA 15.244 - - - - 0.000 15.244
Block 2 Upgrade C/CPFF JHU/APL:md 1.300 - - - - 0.000 1.300
Block 2 Product Support WR China Lake/NRL/Dahlgren:CA/VA 3.577 - - - - Continuing Continuing Continuing
Subtotal 164.731 - - - -
Support ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Studies and Analyses Various various:various 1.210 - - - - Continuing Continuing ContinuingSubtotal 1.210 - - - -
Test and Evaluation ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
DT&E/OT&E/FOT&E/ SS/CPAF Raytheon:Tucson/Louisville 13.787 1.113 Jan 2012 0.591 Nov 2012 - 0.591 0.000 15.491
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 6 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
Test and Evaluation ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
FOT&E WR China Lake/PHD:CA/CA 4.674 - - - - 0.000 4.674
Test Support WR China Lake/PHD:CA/CA 11.059 0.052 Jan 2012 0.593 Oct 2012 - 0.593 Continuing Continuing Continuing
Miscellaneous Various various:various 5.733 - - - - 0.000 5.733 Subtotal 35.253 1.165 1.184 - 1.184
Management Services ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Travel Allot Program Office:VA 0.998 0.115 Jan 2012 0.113 Oct 2012 - 0.113 Continuing Continuing ContinuingDefense AcquisitionWorkforce Development Fund Various various:various 0.147 - - - - 0.000 0.147
Subtotal 1.145 0.115 0.113 - 0.113
Total PriorYearsCost FY 2012
FY 2013Base
FY 2013OCO
FY 2013Total
Cost ToComplete Total Cost
TargetValue ofContract
Project Cost Totals 202.339 1.280 1.297 - 1.297
Remarks
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 7 of 23 R-1 Line #128
Exhibit R-4, RDT&E Schedule Profile: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 8 of 23 R-1 Line #128
Exhibit R-4A, RDT&E Schedule Details: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0167: 5in Rolling Airframe Missile
Schedule Details
Start EndEvents by Sub Project Quarter Year Quarter Year
Proj 0167MS C/LRIP 2 2012 2 2012IOC 1 2014 1 2014FRP 3 2016 3 2016GTV-1 Firing 4 2011 4 2011GTV-1A Firing 1 2012 1 2012GTV-2 Firing 1 2012 1 2012GTV-3 Firing 4 2012 4 2012DT/OT-IIC 4 2012 2 2013OT-D-1 Firing 4 2012 1 2013MSST Testing 1 2015 4 2015ECPs/Improvement Studies 3 2016 4 2017
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 9 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
COST ($ in Millions) FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost0173: NATO Sea Sparrow 11.747 5.351 32.005 - 32.005 29.090 15.716 5.167 5.328 Continuing ContinuingQuantity of RDT&E Articles 0 0 0 0 0 0 0 0 0
A. Mission Description and Budget Item JustificationThis project encompasses three (5) primary efforts to enhance ship self defense:1. Evolved SEASPARROW Missile (ESSM): A cooperative effort among 10 NATO SEASPARROW Nations and the U.S., to improve the capability of theSEASPARROW Missile to counter the low altitude, highly maneuverable Anti-Ship Cruise Missile (ASCM) threat. The program consists of evolving the SEASPARROWMissile through the development of a new rocket motor with tail control; thrust vector control and ordnance (warhead) upgrade; modifications to the MK 41 VerticalLaunch System (VLS) to fire from a single cell with 4 ESSM (QuadPack); and modifications to the NSSMS to provide ESSM capability.
2. NATO SEASPARROW - MK 91 Rearchitecture: The MK 91 Rearchitecture Program integrates NSSMS into the Ship Self Defense System (SSDS) Architecture toprovide ship missile defense utilizing an open architected system Technical Design Agent.
3. NATO SEASPARROW Objective Configuration (OC). The OC Program consists of segmenting and automating the existing MK 57 NSSMS radars (MK 9 Trackilluminator System) and launchers (MK 29 Guided Missile Launching System). The program eliminates all MK 57 watch stations, reduces the required systemhardware.
4. STALKER LONG RANGE Electro Optic(EO)/Infra Red (IR)/Laser Range Finder (LRF) SYSTEM: Detects, acquires, classifies, identifies and determines intent ofconventional,asymmetrical and advanced threats supporting Anti-Air Warefare (AAW), Anti-Surface Warefare (ASUW), Anti-terrorism/Force Protection (AT/FP) andGlobal War on Terrorism. Long Range Visible/Infra Red Sensors and Laser Range Finder provide multi-spectral target imagery and accurate range data in non-benignenvironments. Classification to the horizon, visual resolution of 1ft @ 10 nm and range resolution/rate within 1 ft/1kt/nm.
5. ESSM Block 2 Risk Reduction: ESSM Block 2 upgrade is a cooperative effort between U.S Navy and NATO SEASPARROW Consortium Nations. ESSM Block 2upgrade replaces the largely obsolete guidance section with a dual mode Active/Semi-Active X-Band seeker capable of defeating future threat capabilities within theexisting envelope, including; smaller signatures, increased raid sizes, and adverse environments including countermeasures. Threat types include; advanced Anti-ShipCruise Missile (ASCM)s, Anti-Ship Ballistic Missiles (ASBMs), surface and asymmetrical.
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013Title: NATO Sea Sparrow integration testing
Articles:FY 2011 Accomplishments:
4.0000
5.0960
9.3560
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 10 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013Continue ESSM SSDS integration testing on CVN platforms. Conduct US-unique DT/OT firings from SDTS and carriers (DT/OT-D2, DT/OT-D3). Conduct ESSM Aegis integration testing and DT/OT firings on Cruisers and Destroyers and SDTS (DT/OT-D4, DT/OT-D5, DT/OT-D6) in support of Aegis Modernization Program. Conduct ESSM DT/OT firings on SDTS (DT/OT-D7) insupport of SSDS Open Architecture integration and uplink development. This provides for the U.S. share of cooperative effortsassociated with ESSM engineering studies and other development initiatives.FY 2012 Plans:Continue ESSM SSDS integration testing on CVN platforms. Conduct US-unique DT/OT firings from SDTS and carriers (DT/OT-D2, DT/OT-D3). Conduct ESSM Aegis integration testing and DT/OT firings on Cruisers and Destroyers and SDTS (DT/OT-D4, DT/OT-D5, DT/OT-D6) in support of Aegis Modernization Program. Conduct ESSM DT/OT firings on SDTS (DT/OT-D7) insupport of SSDS Open Architecture integration and uplink development. This provides for the U.S. share of cooperative effortsassociated with ESSM engineering studies and other development initiatives.FY 2013 Plans:Continue ESSM SSDS integration testing on CVN platforms. Conduct US-unique DT/OT firings from SDTS and carriers (DT/OT-D2, DT/OT-D3). Conduct ESSM Aegis integration testing and DT/OT firings on Cruisers and Destroyers and SDTS (DT/OT-D4, DT/OT-D5, DT/OT-D6) in support of Aegis Modernization Program. Conduct ESSM DT/OT firings on SDTS (DT/OT-D7) insupport of SSDS Open Architecture integration and uplink development. This provides for the U.S. share of cooperative effortsassociated with ESSM engineering studies and other development initiatives.Title: NATO SEASPARROW Objective Configuration
Articles:Description: NATO SEASPARROW Objective Configuration (OC). The OC Program consists of segmenting and automating theexisting MK 57 NSSMS radars (Mk 9 Track illuminator System) and launchers (Mk 29 Guided Missile Launching System). Theprogram eliminates all MK 57 watch stations, reduces the required system hardware.
FY 2013 Plans:Begin engineering development of the OC. Specific efforts in 2013 will include requirements definition, completion of therequirements review followed by design definition with the preliminary design review completing in the 4th Quarter of FY 13.
- - 8.9030
Title: NATO Sea Sparrow Combat System Integraton Technical Direction Agent (TDA)Articles:
FY 2011 Accomplishments:Provides funding for the Combat System Integration TDA who will provide engineering support for combat system performanceand risk mitigation. The TDA will leverage it's technical expertise & leadership to cover a broad range of activities such as
0.2470
0.2550
0.2630
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 11 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013defining near-term and future requirements for current systems and future upgrades, maintain system performance models toevaluate system improvements, threat changes and operational environment conditions, verify models and simulations to promoteprogram success through application of rigorous and disciplined systems engineering principles and practices in a consistentmanner across system elements over the program life cycle, make prudent use of authoritative technical expertise for advice andindependent review, identify a range of technically acceptable alternatives to resolve engineering issues, assist in development ofT&E planning, and continue to maintain NSPO essential research and engineering capabilities and corporate memory.FY 2012 Plans:Provides funding for the TDA who will provide engineering support for combat system performance and risk mitigation.FY 2013 Plans:Provides funding for the TDA who will provide engineering support for combat system performance and risk mitigation.Title: STALKER LONG RANGE EO/IR/LRF SYSTEM
Articles:Description: Description: STALKER LONG RANGE EO/IR/LRF SYSTEM: Detects, acquires, classifies, identifies and determinesintent of conventional,asymmetrical and advanced threats supporting AAW, ASUW, AT/FP and GWOT. Long Range Visible/InfraRed Sensors and Laser Range Finder provide multi-spectral target imagery and accurate range data in non-benign environments.Classification to the horizon, visual resolution of 1ft @ 10 nm and range resolution/rate within 1 ft/1kt/nm.
FY 2011 Accomplishments:N/AFY 2013 Plans:FY 2013 Plans:Productize and test Stalker Long Range EO/IR/LRF system for LLTV replacement in the fleet.
7.5000
- 5.4830
Title: Evolved SEASPARROW Blk 2 Risk ReductionArticles:
FY 2013 Plans:Perform Risk Reduction with consortium partners to reduce technology risk, determine and mature the appropriate set oftechnologies to be integrated into a full system.
- - 8.0000
Accomplishments/Planned Programs Subtotals 11.747 5.351 32.005
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 12 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
C. Other Program Funding Summary ($ in Millions)
Line Item FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost• WPN 2307: ESSM 45.260 48.486 58.194 0.000 58.194 70.822 121.908 197.768 119.778 0.000 1,417.745• OPN 5237: NATO SEASPARROW
10.106 8.926 8.960 0.000 8.960 36.229 28.520 40.606 31.586 0.000 304.047
D. Acquisition StrategyESSM is a directed sole source contract to Raytheon Missile Systems Company. The MK 29 ESSM Launcher Upgrade and REARC/SSDS Integration effort was adirected sole source contract to Raytheon Company Integrated Defense System.
E. Performance MetricsSuccessfully complete Developmental Test/Operational testing.
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 13 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
Product Development ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
ESSM-Primary HardwareDevelopment C/CPAF Raytheon:Tucson 143.356 - - - - 0.000 143.356
ESSM-Primary HardwareDevelopment C/CPAF Raytheon:Tuscon 3.746 - - - - 0.000 3.746 3.746
Amphib Self-Defense PRAImp Various various:various 1.996 - - - - 0.000 1.996 11.200
Ancillary HardwareDevelopment SS/CPAF Lockhead/
UDLP:various 46.706 - - - - 0.000 46.706 46.706
Systems Engineering Various various:various 22.622 - - - - 0.000 22.622 22.622MK 29/ESSM Launcherupgrade C/CPAF Raytheon Sys:Tucson 8.521 - - - - 0.000 8.521 8.521
NATO-Primary Hdw Dev SS/CPAF Raytheon Sys:Tucson 30.627 - - - - 0.000 30.627 30.627Software Development/Test SS/CPAF Raytheon Sys:Tucson 7.691 - - - - 0.000 7.691 Systems Engineering/FiringSpt WR Corona:CA 6.640 0.600 Nov 2011 0.685 Dec 2012 - 0.685 0.000 7.925
NATO OC - Hardware SS/CPAF Raytheon:RI - - 1.000 Nov 2012 - 1.000 0.000 1.000 NATO OC SystemEngineering SS/CPAF Raytheon:RI - - 1.653 Nov 2012 - 1.653 0.000 1.653
NATO OC - Software SS/CPAF Raytheon:RI - - 4.938 Nov 2012 - 4.938 0.000 4.938 Stalker System Engineering TBD TBD:TBD - - 3.233 Nov 2012 - 3.233 0.000 3.233 Stalker Hardware Engineering TBD TBD:TBD 7.500 - 1.250 Nov 2012 - 1.250 0.000 8.750 Stalker Software Engineering TBD TBD:TBD 2.000 - 0.500 Nov 2012 - 0.500 0.000 2.500 ESSM Blk 2 Risk reduction WR various:various - - 8.000 Nov 2012 - 8.000 0.000 8.000
Subtotal 281.405 0.600 21.259 - 21.259 0.000 303.264
Support ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Integrated Logistics Support WR NSWC PHD:CA 3.568 - - - - 0.000 3.568
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 14 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
Support ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Engr Support1 WR various:various 4.207 - - - - 0.000 4.207 MK 29/ESSM LauncherSupport WR Dahlgren/PHD:VA/CA 0.375 - - - - 0.000 0.375
Engr Support2 WR various:various 0.195 - - - - 0.000 0.195 0.195NATO-MK 91/SSDS Integ WR Dahlgren/PHD:VA/CA 0.834 - - - - 0.000 0.834 Engr Support3 WR various:various 6.364 - - - - 0.000 6.364 NATO System TDA SS/FP APL:MD 1.220 0.255 Dec 2011 0.263 Nov 2012 - 0.263 Continuing Continuing ContinuingNATO OC SS/FFP APL:MD - - 0.300 Nov 2012 - 0.300 0.000 0.300 Stalker -ISEA/TDA/RM&A SS/FFP various:various - - 0.300 Nov 2012 - 0.300 0.000 0.300 NATO Engr Support OC WR various:various - - 0.400 Nov 2012 - 0.400 0.000 0.400
Subtotal 16.763 0.255 1.263 - 1.263
Test and Evaluation ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Developmental Test &Evaluation WR NSWC CL:CA 15.698 1.217 Oct 2011 1.568 Dec 2012 - 1.568 Continuing Continuing Continuing
OPEVAL/TECHEVAL/TestFirings WR Corona, IHD, Dahlgren,
SNSWC, PHD):various 11.878 - 2.310 Nov 2012 - 2.310 0.000 14.188
Developmental Test &Evaluation SS/FFP APL:MD 2.979 0.510 Oct 2011 0.659 Oct 2012 - 0.659 Continuing Continuing Continuing
ESSM Test & Evaluation C/CPAF Raytheon:Tuscon 7.998 2.026 Nov 2011 3.056 Nov 2012 - 3.056 Continuing Continuing ContinuingDevelopmental Test &Evaluation WR Dahlgren:VA 0.418 - - - - 0.000 0.418 0.836
ESSM Test & Evaluation WR Dahlgren/PHD:VA/CA - 0.543 Nov 2011 0.560 Nov 2012 - 0.560 0.000 1.103 NATO OC - Test & Evaluation WR Dahlgren/PHD:VA/CA - - 0.469 Nov 2012 - 0.469 0.000 0.469 Stalker - Test & eval WR TBD:TBD - - 0.200 Nov 2012 - 0.200 0.000 0.200
Subtotal 38.971 4.296 8.822 - 8.822
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 15 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
Management Services ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
ESSM-ENGR SPT WR various:various 4.913 - - - - 0.000 4.913 ESSM-PM SPT WR various:various 0.498 - - - - 0.000 0.498 0.498ESSM-Support andPerforming Activity Allot PHD/NAWC CL/
APL:CA/MD 13.951 - 0.256 Dec 2012 - 0.256 Continuing Continuing Continuing
ESSM-Travel Allot Program Office:VA 2.782 0.200 Nov 2011 0.205 Oct 2012 - 0.205 Continuing Continuing ContinuingESSM-Misc Various various:various 2.065 - - - - 0.000 2.065 2.065NATO Travel/Misc Various various:various 1.831 - 0.200 Oct 2012 - 0.200 0.000 2.031 Defense AcquisitionWorkforce Development Fund Various various:various 0.047 - - - - 0.000 0.047
Subtotal 26.087 0.200 0.661 - 0.661
Total PriorYearsCost FY 2012
FY 2013Base
FY 2013OCO
FY 2013Total
Cost ToComplete Total Cost
TargetValue ofContract
Project Cost Totals 363.226 5.351 32.005 - 32.005
RemarksVarious used for multiple vendors and location under threshold.
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 16 of 23 R-1 Line #128
Exhibit R-4, RDT&E Schedule Profile: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 17 of 23 R-1 Line #128
Exhibit R-4A, RDT&E Schedule Details: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT0173: NATO Sea Sparrow
Schedule Details
Start EndEvents by Sub Project Quarter Year Quarter Year
Proj 0173Platform Intergration DT/OT 1 2011 2 2016Expiration of Production MOU 1 2012 1 2012MOU Extension 2 2012 3 2014Page/Group/Row: FY 07FRP DELIVERIES 3 2011 3 2011Page/Group/Row: FY 08 FRP DELIVERIES 3 2011 1 2012Page/Group/Row: FY 09 FRP DELIVERIES 1 2012 3 2012Page/Group/Row: FY 10 FRP DELIVERIES 3 2012 3 2013Page/Group/Row: FY 11 FRP CONTRACT AWARD 4 2011 4 2011Page/Group/Row: FY 11 FRP DELIVERIES 4 2013 1 2014Page/Group/Row: FY 12 FRP CONTRACT AWARD 1 2012 1 2012Page/Group/Row: FY 12 FRP DELIVERIES 1 2014 3 2014Page/Group/Row: FY 13 FRP CONTRACT AWARD 1 2013 1 2013Page/Group/Row: FY 13 FRP DELIVERIES 1 2015 1 2016Page/Group/Row: FY 14 FRP CONTRACT AWARD 1 2014 1 2014Page/Group/Row: FY14 FRP DELIVERIES 1 2016 3 2016Page/Group/Row: FY 15 FRP CONTRACT AWARD 1 2015 1 2015Page/Group/Row: FY15 FRP DELIVERIES 1 2017 3 2017Page/Group/Row: FY 16 FRP CONTRACT AWARD 1 2016 1 2016Page/Group/Row: FY 17 FRP CONTRACT AWARD 1 2017 1 2017
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 18 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
COST ($ in Millions) FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost3342: Griffin Missile 22.000 - 30.777 - 30.777 - - - - 0.000 52.777Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0
A. Mission Description and Budget Item JustificationPEO IWS 3.0 established a new program office IWS 3S for Surface Missions which is primarily focused on developing and delivering Counter-Swarm Small Boatdefense cpabilities for the Surface Fleet. IWS 3S has three (3) efforts supporting this mission area listed below:
1. Rapid Deployment Capabilities (RDCs):- Cyclone Patrol Craft (PC) with Griffin Missile System (GMS)
2. DEMO (Javelin-Spike-Griffin)
3. NAWC China Lake Spike Shoulder Launched Missile System
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013Title: Cyclone Patrol Craft (PC) with Griffin Missile System (GMS)
Articles:FY 2011 Accomplishments:Preliminary system requirements determination, market research and team development.FY 2013 Plans:Complete lead PC design, develop training and logistics support, obtain safety approvals for system deployment and formulate theOCONUS AIT plan. Procurement planning for forward deployed PC hardware.
17.0000
- 8.1000
Title: DEMO (Javelin-Spike-Griffin)Articles:
FY 2011 Accomplishments:Test planning, test article procuremeent, target allocation, range coordination and developed data collection plan.
5.0000
- -
Title: Spike Shoulder Launched Missile SystemArticles:
FY 2013 Plans:
- - 22.6770
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 19 of 23 R-1 Line #128
Exhibit R-2A, RDT&E Project Justification: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2011 FY 2012 FY 2013Missile modifications, launcher development, architecture and warhead upgrade analysis. Plan environmental and safetyqualification testing.
Accomplishments/Planned Programs Subtotals 22.000 - 30.777
C. Other Program Funding Summary ($ in Millions)
Line Item FY 2011 FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total FY 2014 FY 2015 FY 2016 FY 2017Cost To
Complete Total Cost• WPN/2264: Griffin 0.000 0.000 0.000 0.000 0.000 8.000 0.500 0.500 0.500 0.000 9.500• OPN/5421: Griffin 0.000 0.000 0.000 0.000 0.000 13.200 17.000 0.000 0.000 0.000 30.200
D. Acquisition StrategyThe RDC'S will use a sole contract via the U.S. Army Joint Program Office to procure in production Griffin B Block II Missles. In addition, the NSWC DD BattleManagement System (BMS) will be integrated as the Weapon Control and Launcher Control System. IWS 3L will support 3S in developing and delivering launcherswith gas management systems.China Lake will develop a shoulder launcher for Spike missile.
E. Performance MetricsSuccessful completion of DT/OA for Griffin missile. Continued development of shoulder launcher and integration of Spike missile.
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 20 of 23 R-1 Line #128
Exhibit R-3, RDT&E Project Cost Analysis: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
Product Development ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
PC Integration WR PHD:CA - - 3.113 Nov 2012 - 3.113 0.000 3.113 Spike Development WR China Lake:CA - - 21.777 Nov 2012 - 21.777 0.000 21.777 PC Integration WR Dahlgren:VA - - 4.687 Nov 2012 - 4.687 0.000 4.687
Subtotal - - 29.577 - 29.577 0.000 29.577
Management Services ($ in Millions) FY 2012FY 2013
BaseFY 2013
OCOFY 2013
Total
Cost Category Item
ContractMethod& Type
PerformingActivity & Location
Total PriorYearsCost Cost
AwardDate Cost
AwardDate Cost
AwardDate Cost
Cost ToComplete Total Cost
TargetValue ofContract
Program ManagementSupport Various various:various - - 1.200 Oct 2012 - 1.200 0.000 1.200
Subtotal - - 1.200 - 1.200 0.000 1.200
Total PriorYearsCost FY 2012
FY 2013Base
FY 2013OCO
FY 2013Total
Cost ToComplete Total Cost
TargetValue ofContract
Project Cost Totals - - 30.777 - 30.777 0.000 30.777
Remarks
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 21 of 23 R-1 Line #128
Exhibit R-4, RDT&E Schedule Profile: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 22 of 23 R-1 Line #128
Exhibit R-4, RDT&E Schedule Profile: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
UNCLASSIFIED
PE 0604756N: Ship Self Def (Engage: Hard Kill) UNCLASSIFIEDNavy Page 23 of 23 R-1 Line #128
Exhibit R-4A, RDT&E Schedule Details: PB 2013 Navy DATE: February 2012APPROPRIATION/BUDGET ACTIVITY1319: Research, Development, Test & Evaluation, NavyBA 5: Development & Demonstration (SDD)
R-1 ITEM NOMENCLATUREPE 0604756N: Ship Self Def (Engage: HardKill)
PROJECT3342: Griffin Missile
Schedule Details
Start EndEvents by Sub Project Quarter Year Quarter Year
Proj 3342Missile Modifications Spike 1 2013 4 2014Launcher Design and EDM Fabrication 1 2013 4 2014Test Planning 1 2013 4 2014System Requirements PC 1 2012 2 2012Launcher Design 2 2012 4 2012Restrained Fire Testing 3 2012 4 2012WCS/BMS Dev and SW Mods 2 2012 4 2012E3 Testing 4 2012 1 2013INCO 1 2013 1 2013GTV/STF 2 2013 2 2013DT/OA 2 2013 2 2013Complete PC Design, Trng, Safety, AIT Plans, Proc Planning 2 2013 4 2013
top related