Samsung SDI EV Battery Manufacturing Plan

Edmond KwokChris Suk

SJSU ENGR297G

Overview• Mission statement• Demand forecast• Product information• Process flow• Bill of material• Equipment selection• Plant layout• Labor• Yields and uptime• Ramp plan• Cost of goods• Cost analysis: manual vs full automation assembly

SJSU ENGR297G

Mission Statement

Samsung SDI will build a third battery production line dedicated to automotive applications to meet increasing EV demands.

Location: Ulsan, South KoreaCapacity: 5 GWh per yearOperation: 24/7/365, 3 shiftsLabor: Semi-automatedSupply capacity by 2020: ~100,000 EV per year

SJSU ENGR297G

SDI supplies batteries for…

BMW i3 – 22 kWhBMW i8 (HEV) – 7.1 kWhBMW X5 eDrive (future) – 9.0 kWhBMW i5 (future?)Chrysler Fiat 500e – 24 kWh

BMW CEO says they will make 100,000 electric vehicles a year by 2020SJSU ENGR297G

EV Range• 3-4 miles range per kWh• 200 miles range is ideal

SJSU ENGR297G

Demand Forecast

200𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚4𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑝𝑝𝑚𝑚𝑝𝑝 𝑘𝑘𝑘𝑘𝑘

= 50 kWh

SJSU ENGR297G

Demand Forecast

200𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚4𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑝𝑝𝑚𝑚𝑝𝑝 𝑘𝑘𝑘𝑘𝑘

= 50 kWh

100,000 EVs x 50 kWh = 5 GWh per year

SJSU ENGR297G

Product

Form factor: Large format prismaticCathode: LiNiMnCoO2

Anode: GraphiteSizes: 28Ah, 40Ah, 60Ah, 64Ah

SJSU ENGR297G

NCM: ~160 Wh/kg

SJSU ENGR297G

Process Flow

SJSU ENGR297G

Mixing Coating

Calendaring Slitting

Electrode Fabrication

Viscosity Percent Solids

Loading Check

Thickness check Assembly

Cathode:LithiumNickelManganeseCobaltOxalic AcidNMPPVDF

Anode:GraphitePVDFNMP

Cathode:Aluminum Foil

Anode: Copper Foil

SJSU ENGR297G

Winding InsertionGang

Welding Tabs

Electrolyte Fill

Laser Welding

EnclosureDegassing

Formation

Assembly

Jelly Roll (9x)

Prismatic Enclosure

Cathode

Anode

Separator

Tab Stock

Cap

SJSU ENGR297G

Formation

Initial Charge

Full Discharge

Check Voltage

Partial Charge

Sorting & Shipping

Hold for 21 days

Remove Bad Cells

SJSU ENGR297G

Bill of MaterialsSamsung SDI Large Format Prismatic Cell BOM

BOMLevel Part name Units Cost per unit Cost per cell Supplier

1 Cover 1 $0.15 $0.22 In-house2 Pressure Vent 1 $0.15 $0.22 In-house2 Battery Terminals 2 $0.20 $0.58 In-house2 Current Collector 2 $0.20 $0.58 In-house2 Polystyrene insulator 4 TBD TBD TBD

1 Metal prismatic can 1 In-house1 Jelly roll 9 N/A N/A In-house

2 Al Tabs (2mm width) 9 $0.05 $0.65 Samsung2 Ni Tabs (2mm width) 9 $0.05 $0.65 Samsung2 Tape 2 $0.01 $0.02 Samsung2 Anode 1 N/A N/A

3 Oxalic acid kg $0.65 $0.05 Alibaba3 PVDF (Indirect) kg N/A N/A Alibaba3 NMP (Indirect) kg $5.00 $0.60 Alibaba3 Graphite kg $18.00 $5.21 Samsung3 Cu Foil kg $10.00 $2.63 Samsung

2 Cathode 1 N/A N/A3 LiNiCoMnO2 active kg $20.00 $9.85 Samsung3 Carbon kg $0.60 $0.05 Samsung3 PVDF kg N/A N/A Alibaba3 Al Foil kg $5.00 $0.61 Samsung

2 Separator sq m $1.00 $2.89 Polypore1 Electrolyte kg $40.00 $3.51 Samsung

2 Additives kg TBD TBD Samsung1 Top insulator 1 $0.02 $0.031 Bottom insulator 1 $0.02 $0.03

SJSU ENGR297G

Mixer SelectionLiNiCoMnO2 active: 12,268,034 kg per yearGraphite: 7,202,896 kg per year

Equipment Supplier: AsadaCathode prep: 4 x 1000 gallon mixersAnode prep: 2 x 1000 gallon mixersCathode mix: 4 x 1000 gallon mixersAnode mix: 2 x 1000 gallon mixers

12 operators2 engineers2 QC1 supervisors

SJSU ENGR297G

Coater Selection

Equipment Supplier: HiranoCathode coater: 7 x 30 meter drying zone7 x NMP abatement Anode coater: 10 x 30 meter drying zone

26 operators2 engineers2 QC2 supervisor

SJSU ENGR297G

Calender Selection

Equipment Supplier: HitachiCathode: 3 x 1000mm web calenderAnode: 3 x 1000mm web calender

6 operators2 engineers2 QC1 supervisor

SJSU ENGR297G

SlittingEquipment Supplier: NishimuraCathode:3 x slitter (50m/min)Anode: 3 x slitter (50m/min)

6 operators2 engineers2 QC1 supervisor

SJSU ENGR297G

Winding

Equipment Supplier: TBD

8 x large format winders

6 operators2 engineers2 QC1 supervisor

SJSU ENGR297G

Dry Room

1 x 30,000 square foot

SJSU ENGR297G

Automated Assembly

Equipment Supplier: Hitachi

3 x full automation line

3 operators2 engineers2 QC1 supervisor

SJSU ENGR297G

FormationChannelsCapacity: 60A maxCost: 500$ per channel# of Channels: 79,621

41 operators2 engineers2 QC3 supervisors

Cell charge/discharge: 20 hoursExtended hold: 21 days

SJSU ENGR297G

Plant Layout

Material Stores

Finished Goods

Mixing

Coating

Cathode

Anode

Con

verti

ng

Dry Room

Cathode Calendaring and Slitting

Anode Calendaring and Slitting

Offices

Asse

mbl

y

Form

atio

n

1” = 30m 339,770 sq ft557’ x 610’

SJSU ENGR297G

Labor

Average wage – Ulsan, South KoreaOperator: $14.77 per hourManufacturing Supervision: $22.24 per hourManufacturing Engineer: $31.79 per hour

Overhead: 38%

Direct labor cost: $18,208,516Indirect labor cost: $11,075,320

SJSU ENGR297G

Yields and Uptime

Capacity: 27 million cells per year

SJSU ENGR297G

Ramp PlanProduction capacity2016 – 47%2017 – 53%2018 – 73%2019 – 80%2020 – 100%

SJSU ENGR297G

Ramp Plan

SJSU ENGR297G

Material Costs

SJSU ENGR297G

Capacity: 27 million cells per year

Cost of Goods

SJSU ENGR297G

Capacity: 27 million cells per year

Cost of Goods

BMW i3: 96 cells x $30.62 = ~$3000

SJSU ENGR297G

$1715.60 x 8 = ~$13,725 SJSU ENGR297G

Assembly: Manual vs AutomationManual assembly7 assembly lines$1.75 million capital49 operators90% process yield

Automated assembly3 automated lines$9 million capital3 operators97% process yield

SJSU ENGR297G

Assembly: Manual vs AutomationManual assembly7 assembly lines$1.75 million capital49 operators90% process yield

Automated assembly3 automated lines$9 million capital3 operators97% process yield

SJSU ENGR297G

Assembly: Manual vs AutomationManual assembly7 assembly lines$1.75 million capital49 operators90% process yield

Automated assembly3 automated lines$9 million capital3 operators97% process yield

SJSU ENGR297G

Assembly: Manual vs AutomationManual assembly7 assembly lines$1.75 million capital49 operators90% process yield

Automated assembly3 automated lines$9 million capital3 operators97% process yield

SJSU ENGR297G

Assembly: Manual vs AutomationManual assembly7 assembly lines$1.75 million capital49 operators90% process yield

Automated assembly3 automated lines$9 million capital3 operators97% process yield

$53.5 million per year difference! SJSU ENGR297G