Robot AutomationTEAM 072017-2018
Nathan Casey (ECE)
Josh Tempelman(ME)
Michael Bissetta(ECE)
The Team
Alex Keizer(ME)
2Intro Old Project New Project Moving Forward
Presentation Outline
Overview
Initial mechanical design
Initial electrical design
Design Change
Final mechanical design
Final electrical design
3Intro Old Project New Project Moving Forward
The Customer
• Specializes in machining, assembly, inspection
• Serves wide variety of industries: automotive, office, medical, and more
• Currently uses little automation
4Intro Old Project New Project Moving Forward
Project overview
• Parts are currently being produced in a lathe operated by a worker.
• The pucks are put into a lathe twice, machined to precise dimensions, and measured.
• Our task was to automate this process, decreasing cost and increasing part quality.
5Intro Old Project New Project Moving Forward
Ethics and Design Norms
Delightful Harmony TransparencyTrust
6Intro Old Project New Project Moving Forward
Initial design requirements
• Manufacture parts with little to no human interference
• Operate robustly and reliably
• Manufacture 120 parts per hour
• Track dimensions of finished parts
• Comply with safety standards
• All designs are owned by Prefferred Quality Services, not Team07
7Intro Old Project New Project Moving Forward
Initial mechanical plan - indexing table
8Intro Old Project New Project Moving Forward
Initial mechanical plan – End of Arm Tool
- Electromagentic Gripping
- Simple Bracket Configuration
9Intro Old Project New Project Moving Forward
Initial electrical plan - Communication
10Intro Old Project New Project Moving Forward
Initial electrical plan - Block Diagram
11Intro Old Project New Project Moving Forward
Anticipated challenges
● Reliable measurements
● Consistent part grabbing
● Lack experience in networking and programming
12Intro Old Project New Project Moving Forward
Project Change
3+ years of production anticipated on the part created by the cell
November 16 the OEM notified PQS that the part will bediscontinued in Q1 of 2018
PQS has assigned a new project to the team to replace this one
OEM
SUPPLIER
PQS
Old Part New Part
13Intro Old Project New Project Moving Forward
New requirements
• New heavier part + how to machine it
• New table
• New electrical hardware and requirements
• No measurement system
14Intro Old Project New Project Moving Forward
Lessons learned
• Scrapped ideas (ex. Gantry robot, two motors for original table design)
• Engineering in industry can be volatile
• Must be able to adapt quickly
• It is important to research deeply as well as broadly
15Intro Old Project New Project Moving Forward
Safety
• Cage keeps employees away from moving parts
• Three Emergency stop buttons
• Safety Relay connects all E-stops and handles emergency procedure
• Safety mat and speaker ensures no one is near table when it rotates.
• Stack lights indicate machine state
16Intro Old Project New Project Moving Forward
Finances
• Cost savings was a important factor for our customer
• With the change of project costs increased significantly and that had to be communicated to the
customer
• We updated our budget regularly and kept the customer informed on all changes
• We saved a lot of the cost by going through several robot suppliers
• We can also save cost in the future by using parts that have long lifespans
17Intro Old Project New Project Moving Forward
New System Design
18 of 30
Key Components:-HAAS Lathe-Fanuc Arcmate 6-Axis Robot-Rotating Part Loading Table-Part Check Ramp-Finished Part Bin-Velox Safety Caging
Intro Old Project New Project Moving Forward
New mechanical plan - indexing table
Key Components:-Oriental Motor-Polycarbonate Shields-E-stop Switch-80/20 Framing
Key Metrics/Decisions:-Modular-Cost Effective-Portability-Safety-Manufacturability
19Intro Old Project New Project Moving Forward
Part Table Progress
20Intro Old Project New Project Moving Forward
New mechanical plan - parts slot
21
Key Components:-80/20 Framing-Low Friction Polycarbonate Slides-Housing for Electrical Hardware-Touch Screen Display
Intro Old Project New Project Moving Forward
New mechanical plan – End of Arm Tool
22
Key Components:-Machined Aluminum Plumbing-Venturi Vacuum Pumps-Two Laser Distance Sensors-Proxy sensor-Homing Rods
Intro Old Project New Project Moving Forward
FEA and Calcs
23
0 0.5 1 1.5 2-60
-40
-20
0
20
40
60
t [s]
To
rqu
eta
ble
[N
*m]
Intro Old Project New Project Moving Forward
New electrical design plan - power distribution
24Intro Old Project New Project Moving Forward
New electrical design plan - Communication
25Intro Old Project New Project Moving Forward
New electrical design plan - software
26Intro Old Project New Project Moving Forward
New electrical design plan - software
27Intro Old Project New Project Moving Forward
New electrical design - Progress
28Intro Old Project New Project Moving Forward
Lessons learned
- Working with distributors can be difficult
- Software can have a lead time
- Inter-team communication is important
- Don’t assume things about the customer
- Solid plans make work go much faster
29Intro Old Project New Project Moving Forward
Moving Forward
• Finish programing
• Wire and power all components once drops are installed
• Finish installation of arm and cage
• Begin working through test plan
30Intro Old Project New Project Moving Forward
Questions