PAUD PROJECT PROGRESS - MAY 2017

A1 BUILDING

A1 PROGRESS STATUS

• External plaster work completed

• Toilet Dado work in progress

• OHWT work in progress

• Flooring work started at ground floor

• Waterproofing work Completed

• Door shutter fixing work in progress

A1 EXTERNAL PLASTER

A2 BUILDING

A2 PROGRESS STATUS

• Block work completed at all Floors

• External plaster work in Progress– 20% Done

• Internal plaster completed till 5th Floor

• Water proofing completed till 4th Floor

• Electrical conduting work in progress

A3 BUILDING

A3 PROGRESS STATUS

• Staircase & Passage area painting work in progress

• External plumbing completed

• Lift installation completed

• Sanitary fixing work in progress – 30% Done

B1 BUILDING

B1 PROGRESS STATUS

• External Plaster – 100% Completed

• Concealed electrical conduiting done at all Floors

• Internal gypsum plaster done at all Floors

B2 BUILDING

B2 EXTERNAL PLASTER WIP

B2 PROGRESS STATUS

• Concealed electrical conduting work in progress, Completed till 6th

Floor

• Internal gypsum plaster activity in progress Completed till 5th Floor

• External plaster started

B3 BUILDING

B3 TOILET DADO STARTEDB3 ROOF FABRICATION

B3 PROGRESS STATUS

• Aluminum window work in progress – 70% Done

• Toilet Dado work in progress

• Staircase railing fabrication completed at all Floors

• Internal ceiling painting work started

• Roof fabrication work in progress

A3 APPROACH ROAD WORKSTP AREA PCC DONE

DEVELOPMENT ACTIVITIES

• STP area PCC done

• D4 side retaining wall casting done

• Road work started for Phase A & B

• External storm line work in progress

C1 BUILDING

C1 4TH SLAB SHUTTERING

C1 PROGRESS STATUS

• RCC Done till 3rd Slab

• 4th Slab RCC work in Progress

C2 BUILDING

C2 FOOTING CASTING

C2 PROGRESS STATUS

• 30 % Footing work completed

• 80% PCC work for footing completed

C3 BUILDING

C3 PROGRESS STATUS

• All Slab RCC work done till Terrace Slab

• Block work in progress at 3rd Floor

D3 BUILDING EXCAVATION

D4 BUILDING EXCAVATION

D4 ROAD EXCAVATION

D4 SIDE PLUM WALL

DEVELOPMENT ACTIVITIES

• D4 side retaining wall casting done

• Excavation at road near D4

THANK YOU