Small Bridges Conference Melbourne, November 2015
DISCUSSION OF AN EMERGENCY RECOVERY IN A METRO AREA
RAIL OVER ROAD BRIDGE STRIKES -
Thanks to…
This presentation will cover:
• Background context of Bridge Strikes
• General concepts of Cost Recovery
• Lessons learned from a typical emergency
recovery
This is not a technical presentation – no time to
make things complicated in an emergency!
• The railway often older than the road
• Many low clearance rail over road bridges
• Average of 34 strikes per year
• Usually at least 1 catastrophic strike a year
• Likely bridge strikes are unreported
Background
The damage can
be catastrophic
but…
The bridge
usually wins!
In New Zealand:
• The driver of the vehicle is liable
• If a hit and run – the local authority is liable
• Insurance companies used to agreeing costs
before expended – Not possible for Bridge
Strikes
General Concepts of Cost Recovery
General Concepts of Cost Recovery
• Engineers lead initial response if catastrophic
• Dedicated cost recovery team manages
interfaces beyond initial response
• Short term aim is to record and recover ALL
costs - Average cost to KiwiRail is NZD$18,000
• Long term aim is to reduce bridge strikes
General Concepts of Cost Recovery
It is not just physical repair costs that can be
recovered:
• Internal staff time and external Consultants
• Disbursements (hotels, flights, meals)
• Revenue losses
• Speed restrictions
• Alternative transport (buses, road bridging)
General Concepts of Cost Recovery
Pitfalls;
• Must be able to prove costs – Good
documentation!
• Never discuss costs unless based on evidence
• Insurers will not pay for betterment
• Large claims likely to be contested and may
take years to recover
General Concepts of Cost Recovery
• Cost recovery is a worthwhile process
General Concepts of Cost Recovery
Financial Year
Costs incurred by KiwiRail
Costs recovered by KiwiRail
Number of Strikes
10/11 $1,063,898 Nil 32
11/12 $319,677 $126,931 33
12/13* $341,912 $99,147 28
13/14 $429,598 $1,290,339 29
14/15 $1,087,203 $1,053,772 49
* Formal cost recovery process implemented
Br 30 WL – Bridge Strike on 7th January 2015
• 220 passenger train movements per week
• Eastern Hutt road is a vital link
Br 30 WL – Bridge Strike on 7th January 2015
• Forklift hit impact beam and cartwheeled up
into the span
Br 30 WL – Bridge Strike on 7th January 2015
Br 30 WL – Bridge Strike on 7th January 2015
Br 30 WL – Bridge Strike on 7th January 2015
Timeline:
• Bridge hit at 2pm on Wed 7th Jan
• Temporary repairs and propping in place and
bridge re-opened at 4pm on Fri 9th Jan
• Temporary replacement span and full line
speed restored at 4pm on Sun 18th Jan
Br 30 WL – Bridge Strike on 7th January 2015
Lessons learned:
• Don’t panic
• Consult with you customer
• Internal resource and experience that can be
mobilized immediately is vital
• Good working relationships with consultants
and contractors crucial
Br 30 WL – Bridge Strike on 7th January 2015
Lessons learned:
• Recognize the limits of your knowledge
• Assess and mitigate risks (design, fatigue,
unknowns)
• Reinforced the value of BOL planning
• Don’t compromise – impact beam was hit
within 72hrs of the bridge re-opening
Thank you