program for replacing earthen levees with megamold ...€¦ · by. frank k. johnson, p.e. /dr....

Post on 07-Aug-2020

2 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

ByFrank K. Johnson, P.E. /Dr. Minhaj Kirmani, P.E.

Program for Replacing Earthen Leveeswith

MegaMold® Monolithic Composite Concrete & Steel Flood Control Structures

State of LouisianaOffice of Coastal Protection and Restoration

Louisiana Applied Coastal and Engineering Sciences Division

1

Presented to

MegaMold® Levee Replacement Program

Louisiana Coastal Master Plan Objectives

Reduce economic and community losses due to storm based flooding

• Protect concentrated assets• Protect distributed assets• Protect strategic assets

CPRA Plan

Seeking comprehensive solutions that achieve the dual objectives of • Coastal restoration• Hurricane protection

2

Current Earthen Levees Fail to Protect Against Catastrophic Flooding

3

Earthen Levee

Overtopping due to limited heights

Breached by surface erosion

Security dependent on maintenance

Levee Failure During Hurricane Katrina

4

I-Walls

Overturned due to limited passive pressure with additional unanticipated hydrostatic pressure in gaps along face

Overtopping causing erosion contributed to the loss of passive pressure

Levee Failure During Hurricane Katrina

5

Increase the height of existing earthen beams;

Long history of use;

Relatively Inexpensive materials;

Stable configuration

Conventional Means for Protecting Community Against 100-Year Storm

6

T-Walls to replace I-Walls

Strong

Resists Erosion

Limited footprint

Flood Walls Constructed atop Existing Earthen Levees to Provide Protection Against 100-Year Storm

7

HWL

CanalExisting Levee

Raised Levee

Existing Width

Increased Width

Requires Land

Significant weight may cause settlement problems

Urban truck traffic

And still erodible

Earthen Berm Disadvantages

8

Very expensive construction

Time consuming construction

Requires pile support

T-Wall Disadvantages

9

Flood Control

Permanently eliminate the threat of catastrophic flooding in low lying urban areas

Coastal Restoration

Prevent erosion and facilitate restoration of coastal areas

MegaMold® Objectives

10

MegaMold® Monolithic Composite

Concrete & Steel Flood Control Structure

11

Ideal for replacing either earthen levees or flood walls

Possible to design for 500 year storm

Stronger and more durable than earthen structures

Faster more economical construction

Multi-functional

MegaMold ®Monolithic Concrete & Steel Composite

Flood Control Structures

12

A Simplified Means for Constructing Composite Monolithic Cast-in-Place Concrete Flood Control Structures Underwater

Introduction

The MegaMold® AdvantageModular Stay-in-Place Construction MoldsModular Structural Steel Molds for Constructing Monolithic Concrete Structures

13

Pilot Project Installing MegaMold ® Stay-in-Place Flood Control Construction Mold Module

14

Pilot Project Casting Concrete into MegaMold ® Stay-in-Place Flood Control Construction Mold Module

15

Pilot Project Casting Roof Slab Concrete into MegaMold® Stay-in-Place Flood Control Construction Mold Module

confidential

Pilot Project Completed Construction: Monolithic Composite Concrete and Steel Flood Control Segment

(in less than 8 hours)

17

Accelerate construction of cast-in-place concrete works;

Increase productivity at work site using off-site fabrication of modular structural components;

Simplify planning and scheduling of field operations;

Reduce weather related delays;

Minimize traffic disruption during construction;

Reduce infrastructure development costs;

Provide long term protection against corrosion and deterioration;

Reduce long term maintenance costs;

Meet or exceeds FHWA and AASHTO standards.

The MegaMold® AdvantagesModular Stay-in-Place Construction Molds

18

The MegaMold ® AdvantageModular Stay-in-Place Construction Molds

Eliminate Costly Conventional Construction Practices

No Rebar Work on Site No Formwork and Shoring Work on Site

No Incremental Construction

Panelized Encasement Component Structural Steel

Component

Composite Module

MegaMold®Modular Stay-in-Place

Construction Mold

20

Presenter
Presentation Notes
Combine an Encasement Assembly component with Structural Steel Grillage component to Form a Modular Unit of a Steel-Framed construction Mold for forming, casting and permanently encasing a Monolithic Composite Concrete & Steel Structure In Situ

Typical Applications

FRP Buildings

Bridge Decks

Platforms and Walkways

Bridge Enclosure Systems

Tank Covers

Cellular Enclosures

Secondary Containment

MegaMold®Fiber Reinforced Plastic (FRP) Panelized Encasement

Elements

21

Existing Channel Bottom

Existing Condition

MegaMold® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

22

Dredging to Base Soil

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

23Dredging

Place Leveling Pad

Install MegaMold ® Modular Construction Mold

Module Installation

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

24

Place Gravel Subgrade

Backfill Base Material

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

25

Cast Concrete Foundation Slab

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

26Tremie Concrete Construction

Controlled Concrete Fill

Continue Casting Concrete Walls

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

27

Final Concrete Placement

Dewater for Backfilling

Continue Casting Concrete Roof Slab

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

28

Place Backfill

Final Condition

MegaMold ® Monolithic Cast-in-Place Concrete Flood Control Structure

Typical Construction Sequence

29

Monolithic concrete construction

Lightweight

Stable configuration

Compatible with sheet pile cutoff

Additional Benefits

Rapid construction

Versatile configuration

Construction in the wet

Multi-functional

MegaMold ®Monolithic Cast-in-Place Concrete & Steel Composite Flood Control Structures

Combine the Advantages of Earthen Berms and T-Walls

30

MegaMold ®Monolithic Cast-in-Place Concrete & Steel Composite

Flood Control Structures

Permanently eliminate the threat of catastrophic flooding from 500-year storms or greater;

Are more durable and reliable than earth, sand and rock structures;

Are not subject to overtopping, breaching or undermining;

Are more economical to construct than repairing and upgrading existing earthen levees;

Are custom-engineered to serve as all-weather roadways, protected utility corridors, and/or foundation structures for commercial and residential buildings.

Are constructed quickly without stressing the environment or local community

31

Analysis of a Typical Gulf Coast Condition17th Street Outfall Canal

32

Composite Concrete Cofferdam

Feasibility Study

New Orleans

Levee Replacement Program

Weidlinger Associates, Inc. Cambridge, MA

33

MegaMold®

Typical Section and Soil Profile of Existing17th Street Outfall Canal Levee

35

Proposed MegaMold® concrete cofferdam

Existing levee

FILL

ORGANIC GRAY CLAY

SAND

Finite Element Model

Existing Levee and MegaMold® Flood Control Structure

36

Finite Element Mesh

Existing Levee and MegaMold® Flood Control Structure

37

Original Condition

ORGANIC SOILSGRAY CLAY

SAND

Stage by Stage Analysis

38

Construction of Present Levee

Tot

al D

isp

lace

men

t (f

t)

Stage by Stage Analysis

39

Dredging at toe prior to installation ofMegaMold ® Flood Control Structure

Tot

al D

isp

lace

men

t (f

t)

Soil to be removed

Stage by Stage Analysis

40

Tot

al D

isp

lace

men

t (f

t)

Construction of MegaMold ® Flood Control Structure

Completed concrete cofferdam

Stage by Stage Analysis

41

Tot

al D

isp

lace

men

t (f

t)

Removal of existing levee

Stage by Stage Analysis

42

Dewater and Fill between Levee and MegaMold ® Cofferdam

Tot

al D

isp

lace

men

t (f

t)

Proposed backfill soil after completion of MegaMold ® concrete cofferdam

Stage by Stage Analysis

43

Final condition

Tot

al D

isp

lace

men

t (f

t)

Stage by Stage Analysis

44

A

B

Predicted Horizontal Displacement Increment at Flood Level

45

Predicted MegaMold® Concrete Cofferdam Displacement Increments

at Flood Level

46

” Hmax =0.42 in

” Vmax =0.03 in

The MegaMold® Solution

Prevent Catastrophic Flooding

Contain Waters of Outfall Canal Between Two MegaMold ®

Monolithic Concrete & Steel Flood Control Structures

47

top related