PROCEDURE - TUMUT
ISOLATION & LOCKOUT VPP9-09-9.4-OP-049
INTENT
This procedure defines the steps to be taken to isolate and lockout energy sources to manage the risks associated with working on mill plant and equipment
Why
It is a regulatory and risk management requirement to make sure that when personnel need to access plant for the purpose of maintenance, cleaning or repair and certain operational tasks that the plant is stopped, isolated
and locked and that safe systems of work are in place to ensure the work is performed safely.
How
1. Key Principles
There are some basic key principles underlying this lockout and tagging process, each in place to protect
people working on plant from sources of energy associated with the plant:
Assess plant and identify isolation points (considering the scope of work to be performed, the
nature of equipment and the sources and magnitude of energy sources)
Stop/shutdown the plant or machinery in a controlled manner.
Isolate, dissipate or restrain the energy sources;
Lock out the plant or machinery with appropriately secured isolators
Verify the isolation is effective
Apply individual personal locks
Perform the work
Remove locks and isolators
Verify plant and machinery safe to return to service
Re-energise the plant
2. When is isolation and lockout required?
Isolation and lockout is necessary whenever workers are performing service, maintenance or operational work
around any piece of plant where the worker(s) could be injured by the unexpected release of an energy source or process contents.
An example of situations when isolation and lockout is required includes:
work where removal or bypass of guards or safety devices is necessary to perform work;
when workers are required to place any part of their bodies where they could be caught by moving
machinery;
work on electrical equipment (including High Voltage)
work on mechanical equipment with potential for movement or auto starting eg conveyors, motors,
pumps, drives
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 2 OF 14
clearing jammed mechanisms
working on lines or vessels (including those containing chemicals and harmful contents)
entering confined spaces
working on natural gas lines
working on or in close proximity to radioactive sources
3. Isolation Procedure
3.1. Assess and identify energy sources and Isolation points
All energy sources likely to place people performing the work at risk, must be identified.
Operations are responsible for ensuring all the isolation points are identified, listed and locked out.
During this assessment the following things must be considered:
The scope of work to be performed
The nature of the equipment involved, including adjacent systems
The sources and magnitude of the energies involved.
During the assessment operations will also determine the most appropriate methods of controlling the
energy and the possibility that the plant might become re-energised or energy might re-accumulate whilst work is being conducted (eg static electricity).
P&ID’s, drawings, and or plant inspections must be used to ensure all isolation points are identified within
an energy system. An isolation list including all isolation points will be generated (see Section 3.2)
Energy/hazard sources may include:
Electrical (power supply, static charges, batteries, capacitators)
Mechanical (mechanical drives, moving and rotating equipment)
Pressure (steam, compressed air, vacuum, hydraulics)
Gravitational (counterweights, vehicle runaways)
Potential (springs, structural strain)
Thermal (hot or cold surfaces and substances, heat radiation)
Noise
Vibration
Ionising and Non-ionising radiation (lasers, welding, electro-magnetic fields, microwaves)
Hazardous substances or process chemicals.
3.2 Isolation lists
Where there is a need to isolate plant and equipment the Production Engineer will identify the plant and equipment to be isolated.
The plant and equipment to be isolated and the isolation points will be determined using the relevant
P&ID’s, plant knowledge and a physical check of the plant.
The plant, and equipment isolation points will be listed on the Isolation list.
Where an isolation list has already been developed for previous use then the Competent or Authorised Production Engineer shall review and ensure it is correct before use, and not automatically follow the
developed list. An Isolation Officer must also sign the list to validate the isolation.
Changes to the list must be authorised by an Isolation Officer.
If an isolation list does not exist for that apparatus then Authorised Production Engineer will develop the
list as described above, identifying all of the isolation points in sequence. Validation of a new isolation list is required by an Isolation Officer for that area.
The Isolation Officer for that area must verify the isolation list is correct and sign the Isolation list.
A Production Engineer shall ensure isolation of the system according to the isolation list and sign against
each isolation point on the list verifying that each point has been isolated.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 3 OF 14
The isolation list is placed on the lockout board or in a plastic sleeve attached to a lock box once the
isolations are completed.
3.3 Shutdown of Equipment
If equipment is operating, the person authorising the work shall verify that it is safe to shut down
the equipment. The plant shall then be stopped using established methods for that operation. The equipment must be allowed to run down completely before commencing the isolation
process.
3.4 Isolating Energy Sources
3.4.1 Single Point, Single Person Lockout (Operations tasks only):
Where there is a requirement to work on a piece of equipment fitted with a single point of
isolation and there is a single person work crew, then a personal lock may be used to lockout out the positive isolation point (where it is a full load current isolator, or cat 3 local isolator
mechanism)
3.4.2 Multiple Isolations (involving multiple points or multiple persons):
Single point, multiple person or multiple point, single person or multiple points, multiple person
isolations must follow the process described for system isolations.
Operations must ensure the isolation of all energy sources and potential hazards to those working
on the plant are completed before permission and access is provided to personnel to perform work, including work being performed by Operations personnel.
Persons deemed competent in the specific isolations shall perform the actual isolation.
Isolation of energy sources shall be achieved by physically interrupting the supply of energy. The means of isolation should be of a type that can be readily checked by visual inspection and it
should act directly on the supply line. It should not act through control circuits or emergency stop mechanisms, (unless they are Category 3 Safety mechanisms).
Specific personnel can only perform the following system isolations:
3.4.3 Electrical Isolations:
Electrical isolations must be completed by a qualified electrician or electrical engineer, with the
exception of Local Full Current Isolators.
3.4.4 High Voltage (HV) Isolations:
Isolation of HV equipment must be completed in accordance with the sites High Voltage Procedure and by personnel as detailed in the HV procedure
3.4.5 Radioactive equipment isolations:
Isolation of radioactive gauges or equipment must only be completed by an authorised Radiation Safety Officer.
3.4.6 Natural Gas isolations: Isolation of all natural gas lines will be under the authority of the Pulp Mill senior management,
including lines that run outside the pulp mill boundary. Permits to work on this system must be
issued by the Pulp mill operations.
3.4.7 Plant isolators
Plant and equipment shall be fitted with isolators on the main energy supply sources to provide a positive isolation of the energy source.
Plant that does not currently have isolators fitted should be assessed and based on risk, a determination by management should be made regarding installation of isolators.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 4 OF 14
3.4.8 Full load current Isolators (or Cat 3 Control Isolators)
Full load current isolation switches can be used for isolations. Where they are provided and clearly identified, operations may isolate and lock on at these points. The plant to be isolated
must first be stopped in a controlled manner via the operating system eg. DCS. When the piece of plant has completely stopped and all stored energy is exhausted a personal or system lock will
be applied. (See 3.4.1)
3.4.9 Isolation Equipment
Equipment used to prevent re-energisation should be durable, securely fastened and sufficient enough to prevent easy or accidental removal (without the use of a key or a tool)
Equipment used to restrain energy sources , (such as locking pins, chains, slings, blanking
plates), must be able to ensure the magnitude of energy can be retrained, must be certified to an appropriate load rating, and must be inspected and maintained.
Locks must comply with the following requirements:
Personal Locks:
Colour of the lock must be RED
Clearly marked with the identification of lock holder & contact details
Must be of a type with single unique key
System Locks: (Equipment)
Colour of the lock shall be GREEN
Lockset numbers shall be clearly marked on the locks
Keyed alike
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 5 OF 14
Operations Locks
Colour of locks shall be YELLOW
Must be a single key
Lockout Boards:
These are central lockout locations. They contain: Lockout identification card: the title identifying the isolation
Isolation list
Operations lock (for isolations that will extend over long periods and work may not be
continuous)
Remaining system locks and keys
Key locking device: This is used to hang unused locks for an area lock set and the key –
covered by a plate and sealed. Personal locks are then attached.
Isolation list: A list of isolation points for a piece of equipment. Isolation list also details
the seal number, lock set number, number of locks in a lock set and the number of isolation points.
Scissor clamps: A scissor type device which clamps onto a lockout point and is locked in
place by a worker positioning a personal lock onto the lock holes. Used when more than one worker may be involved in locking out a system.
Seal: A metal or plastic seal with an individual number imprinted on it and used to
provide visual indication of the integrity of an isolation.
It is attached to the key locking device or lock box to secure the remaining system keys and locks in place. The seal number is written on the Isolation list.
Lock Boxes:
Where it is not practicable for an isolation to be setup on an isolation lockout board and the isolation needs to be located in proximity to the field, then a portable lock box can be used.
The lock box contains the same information as an Isolation board.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 6 OF 14
3.4.10 System/Plant Isolations and lockouts
System isolation and lockout involves making safe single or multiple process systems or plant/machinery for work to be performed. System locks (from a set of locks), must be used for
all plant isolation lockouts.
System locks will be prepared and applied by the Authorised operator onto the isolation points
listed in the Isolation list.
System locks must be used for isolating equipment, and spare system locks and keys must be attached to the key locking device on the lockout board and must be secured by a plate and
numbered seal, in preparation for personal lock application.
3.5 Dissipating and controlling energy
3.5.1 Dissipating Energy: After the energy sources are isolated, any stored energy in the equipment should be dissipated.
This can be achieved by measuring including:
Opening valves to drain pipelines, pressure vessels and hydraulic accumulators
Depressurising equipment with potential to move and create a clamp or crush hazard (e.g.
hydraulic systems) Opening access hatches and inspection covers
Earthing electro static separators
Discharging electrical energy stored in capacitors
Releasing springs and
Lowering counterweights
The method of energy dissipation shall be selected to ensure that energy does not re-accumulate
over time or during the course of work.
3.5.2 Restraining plant, material and energy sources: If internal sources of energy can not be dissipated, they shall be adequately restrained by
measures such as:
Inserting mechanical locking devices such as chocks, pins or sprags
Securing items that can move such as fans and mechanical linkages with chains
Closing cover plates on radioactive gauges
Applying brakes
3.6 Verify Isolation
The person authorising the work shall ensure competent persons verify that all hazardous energies have
been effectively isolated, dissipated or restrained. This must be noted on the isolation list.
Verification may be done by visually checking the energy controls, by reading gauges and meters, by
attempting to start the plant or by other suitable tests. However, no attempt to start the plant shall be made if work has already started on the plant.
If the scope of the planned work changes at any time, then re-assessment of the energy isolation requirements may need to be conducted.
In the event of a test demonstrating that isolation has not been achieved then isolation must not proceed
until the isolation has been reviewed and approved by the Area Manager or their delegate.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 7 OF 14
3.7 Personal Lockouts
Personal locks are applied to a system lockout on an isolation board/box and must be connected to a
scissor clamp, to indicate persons working on the isolated equipment and to prevent inadvertent operation of the apparatus whilst persons are working on the equipment.
They can also be applied to a single point of isolation for a single person, single isolation point,
operational task. (Refer Section 3.4.1 and 3.4.2) Personal locks must be RED in colour and individually keyed.
All persons working on a system which is locked out are responsible for placing personal locks on the
associated isolation lockout board/box.
Each person is responsible for applying and removing their own locks.
Prior to placing personal locks onto isolations the person should: Review the permit and identify the equipment/system by the card identifying the lockout title.
Check the seal is intact and that the seal number corresponds with the seal number entered
on the isolation list.
Apply a personal lock to a scissor clamp on the key-locking device.
Sign onto the relevant work permit, indicating their lock number/details
Swapping locks and keys is not permitted.
Personal locks must be labelled with the persons name, phone number and where relevant contracting company.
Visy employees and permanent contractors will be provided one personal lock and associated key.
Temporary contractors must provide their own individually keyed locks that meet the following criteria:
Individually keyed Red Lock
Marked with printed legible information containing: the name of the person; the contracting
company and a phone number that is to be used whilst person is on site.
The locks must be approximately 38mm X44mm in dimension with a shackle clearance of
approximately 38mm, to physically accommodate shackling to a scissor clamp or lockout device.
3.8 Operations (Yellow) Locks
Where equipment is being worked on and is going to extend over more than one shift or cease for some reason, but may not be continuous, then an Operational lock must be used to maintain the integrity of
the isolation during the time between the working parties leaving and returning to the isolation point. Formal sign over of the Operations lock between (Area or Operations Engineers and/their delegates) will be via an attachment of a Identification tag on each yellow lock.
For example a crew of maintenance personnel may be working on an isolated plant during a day shift and the work will take several days. Over the night shift there is no work on the isolated plant. To ensure
the plant is not inadvertently de-isolated before the work is completed the Operations lock signifies the
system is not safe to start up.
The Operations lock communicates to all personnel that work is in progress and not yet finished,
and that de-isolation cannot commence, even though no personal locks are in place (as the work crew may have finished for the day/shift)
The key to the Operations locks can be stored in the Operational Control rooms (in a designated key
box), and can only be applied and removed by the Operations Engineer or the level of operational management above them (or their authorised delegate).
The same checks required for work that is completed within a shift must be verified before the Operations lock is remove, including:
check the system and plant integrity
ensure all work is completed
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 8 OF 14
Equipment is clear of people, tools and materials.
An identification tag must accompany each operational lock with the Area or Operational Engineers name and contact phone number listed on it.
3.9 Removal of Personal locks
At the completion of work individuals must sign off the work permit and remove their own personal locks.
Where a person has left site and failed to remove their locks the following steps will be taken: Effort will be made to contact the worker to return to site to remove the lock.
where circumstances prevent the worker from returning to site, or where a worker cannot be
contacted then the Senior Production Engineer will contact the Weighbridge to check the site
access database to ensure the name of the worker is registered as having swiped off site The Senior Production Engineer will ensure the Lock Removal Checklist/Form (VP9-09-9.4-
FM-0049) is followed and a physical check has been made of the area before removing the
lock.
If the worker is not able to be contacted his/her site access card will be cancelled preventing
access to site and requiring them to present for approval for re-access. All lock removals completed under this section require the completion of a Lock Removal Checklist form.
(VP9-09-9.4-FM-0049) and record the incident into Vault. In the event that a person loses their keys to their personal lock, then the Senior the persons manager or
supervisor must be informed. The lock(s) must be destroyed and a new lock(s) and key(s) issued.
3.10 De-Isolation and re-energising plant/Verify safe return to Operation
Before removing the last isolation locks, the worker or group of workers involved shall:
Check and ensure that the plant is clear of tools, equipment, materials and persons;
Check and ensure that all guards have been replaced, and the plant is fit for use.
Restore and verify all safety devices that have been removed or bypassed
After the last worker removes their personal locks, the Authorised Production Engineer must
check the system and plant integrity prior to re-energising the plant and ensure all work is
completed and equipment is clear of tools and materials. Where an Operational Lock has been applied then the designated Operations Engineer shall
remove
Plant shall be restarted in accordance with standard operating procedures.
3.11 Variances
Variations to isolation must be approved by the Isolation Officer for the area before the variation is
implemented. Where a variance to an isolation is required:
All permits issued to work on the system must be cancelled after all personnel have signed
off the permit Personal locks must be removed from the lockout board
The variance can then be made by an Authorised Production Engineer
Changes must be written on the Isolation list and approved by an isolation officer
Authorised Production Engineer will apply a red Variance sheet to the Isolation board to alert
work crew members of the variation in isolation.
The system lock sets and a new seal is reapplied to the key locking device
A new permit is issued referencing the new isolation list and the work party reviews and signs
onto the new permit
Individual locks can then be reapplied once the details of the variation are explained and
understood
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 9 OF 14
3.12 Out of Service Tags Where an item of plant, equipment or machinery is defective or inoperable then an Out of Service
tag must be used to advise potential users that the use of the apparatus would create an unacceptable level of risk.
The tag should be applied directly to the operating controls or starting mechanisms, and
preferably these mechanisms should be rendered inoperable (e.g. removal of key) Removal of the Out of Service tag can only be performed by the person who repairs or reinstates
the equipment to its safe working state, or by the person who applies the tag or by the relevant Operations manager once safe operation is verified.
All instances where apparatus is faulty and tagged out, must be reported to the Senior Production Engineer immediately so that a work order can be raised for its repair. Incident reports must be
raised in the event of damage so that an investigation into the cause can be conducted.
3.13 Work Extending over One or more shifts
Where work extends over one day or shift, workers must remove all personal locks at the completion of
the work day or shift and sign off the work permit. The system isolation and locks stay in place. An Operations lock must be used to maintain the integrity and provide information regarding the status of
incomplete work where work is not continuous. Permits may remain open/active for a designated period extending over one or more shifts where the
work is continuous, and this will be specified and recorded on the permit at the time of issuing the
permit. The permit must be signed over to the incoming Supervisor of the new crew coming in, workers must apply their personal locks and sign on to the permit.
3.14 Working on energised equipment
In some circumstances, it may be necessary to work on plant when the source(s) of energy have not
been isolated. Work such as adjustment, monitoring, fault tracing, may require the plant to be energised. In all cases if the plant can be isolated to complete the work then it shall be.
Tasks that require plant to be energised must be identified and any such work on live plant shall only be carried out in strict accordance with a documented risk assessment with adequate controls to ensure the
safety of the workers involved. Work on energised equipment must be approved by the relevant Operations Senior Manager. Personnel who perform work on energised plant must be authorised in
writing to perform this work. Relevant training must also be provided to ensure work is performed safely
and in accordance with any relevant standards.
3.15 Maintenance of System Locks
The Isolation Officers will be responsible for the maintenance and inspection of systems locks.
Each set of system locks will have an identification tag attached indicating the total number of locks in the set and the lock identification number.
When new system lock sets arrive on site, 1 key will accompany the lock set and the remaining keys will be provided to and secured in Stores.
System locks will be stored in the control rooms in designated areas and must be regularly inspected and
cleaned by operations or as required by the isolation officers.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 10 OF 14
3.16 Long term isolations
For plant and equipment, still in situ and operable, but out of the process, a long term isolation maybe required.
Plant that is decommissioned (i.e. de-energised from an MCC or energy source) does not require a long term isolation.
Long term isolations will be carried out as a normal isolation, with all relevant procedural checks in place.
Long term isolations will be listed in a Long term Isolation Register that will be kept by the Isolation Officers for their areas.
The following information shall be recorded:
Asset number
Type/model number
Location
Energy source
Isolation mechanism
Expected duration of isolation
Lock description (colour/tag information)
4 Training
All personnel involved in the execution of the plant and equipment isolations and lockouts must have completed relevant training and refresher training on this procedure. A list of trained personnel will be
kept in the sites training register.
Training shall be categorised as:
4.1 Basic training (level 1): for all personnel who will or may potentially work under a permit or isolation. This level of training is undertaken at induction.
4.2 Operational (Level 2): for Operational personnel conducting isolations and lockouts
and issuing permits to permit holders. Assessments will be undertaken to determine competency in isolating plant and equipment in mill areas.
4.3 Records of competency training will be kept in training files
4.4 Refresher training shall be conducted every 2 years or whenever there are significant
changes to the sites isolation procedures
5 Contractors
Contractors who are required to work under work permits and on plant and equipment, must be provided
instruction on Visy’s isolation and permit procedures and must comply with all of the outlined requirements
Contractors are responsible for correctly identifying, applying and removing their own personal locks from
isolation points within the mill.
6 Documentation Completed Isolation lists and work permits must be filed and kept for a period of 1 month following
completion of the works.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 11 OF 14
7 Compliance/Breaches
All employees and contractors are required to comply with the requirements of this procedure and the restrictions imposed upon them during the lockout.
The following actions will result in disciplinary action:
Removing another persons lock
Energising and or operating equipment that has an isolation lock or other isolation device.
Working on equipment that has been isolated or locked without signing onto the permit and
applying their personal isolation device to the isolation
Failing to isolate and lock out equipment which leads to others working on energised
equipment
When an employee or contractor is found to be in breach of the Isolation/Lockout procedures the
following actions are to be taken.
Notify the Senior Production Engineer on shift and/or the relevant Area Manager
The Senior Production Engineer and/or the Area Manager are to ensure the notification
process is followed and all relevant management are notified as per Visy Standard 402
Notify the person’s supervisor.
Enter the incident and investigation details into The Vault data base and if required an SSO
is to be raised within 24 hours following the breach. If required ensure disciplinary action is recorded and actions are carried out in a timely
manner.
8 Audits
During peak periods of activity involving permits and isolations, formalised regular audits shall be conducted. Findings from audits will be collated and used in the annual review process to ensure that the
procedures and their application are continually monitored and improved.
Supervisors and area managers must also regularly check compliance with these procedures to ensure rigorous adherence.
9 Definitions
Plant Isolation
Isolation is the physical rendering safe of any energy source through disconnection, physical separation of energy, removal of source or physical blocking/blanking to allow personnel to work on or near plant or
machinery without risk of exposure to the process or energy source.
Production Engineer Person employed to operate an area of the mill production. Eg Fibreline Production Engineer
Authorised Production Engineer A Production Engineer who has completed the sites required training and assessment process or has
been given written authorisation by the Pulp/Paper Mill Manager.
An operator can be authorised by an Area Manager but must meet the following criteria.
Operator must be enrolled into the training program for the area
Where relevant the operator must be competent in “like” equipment
Must have 12 months operational experience in the area
Must have completed the site Isolation Lockout Training (level 2)
A data base will be kept on H drive of Competent Authorised persons to sign isolation lists for each area.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 12 OF 14
Isolation Officer
As Tumut is a 24/7 operation the Isolation Officer can be an Area Engineer, Operational Engineer or a
Competent/ Authorised Production Engineer and can be responsible for the following:
Ensuring long term isolations are effective and maintaining the long term isolation register.
Ensuring group isolations lists are correct
Producing isolation lists and reviewing procedures
Participating in audits as required
Participating in incidents investigations of isolation breaches
Appling Operational (yellow) locks to isolations that will extend past a working shift (Area
Engineer or their Designee) Advised of and approved a variance made to an isolation in their area.
Maintaining the system lock sets for their area.
Work Permit: A document providing operational approval to enter into an area to perform work.
Permit Holder:
The person who receives and holds the work permit. The permit holder is typically the person who is responsible for supervising the work to be undertaken.
Dissipate: Release and discharge of energy stored or contained in plant.
10 References
VP9-09-9.4-OP-031 Work Permit Procedure
VP9-09-0.4-WI-049 Isolation Lists VP9-09-9.4-FM-0049 Lock removal checklist/form
Visy Code of Practice: Isolation and Lockout 2010 AS/NZ 3873-2001 Pressure Equipment –Operation and Maintenance
AS/NZ 4024.1-2006 Safeguarding of Machinery AS 4145.4-2002 Padlocks
Work Health & Safety Regulation 2001
Visy Standard V402 Incident Management
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM | UNCONTROLLED WHEN PRINTED - VERSION 16 PAGE 13 OF 14
version
Key
Responsibilities Mill Manager
Production
Manager
Pulp Mill & Paper
Machine Manager
Area Engineers
Operations
Engineers
Senior
Production
Engineers
Isolation
Officer
Maintenance
Engineers
Contractor
Supervisors
Production
Engineers Contractors
Isolation
Methods
Ensure Accurate
transmission of
information on the
COP and make
certain the COP
and Site
Procedures are
implemented and
followed.
Ensure Accurate
transmission of
information on the
COP and make
certain the COP
and Site
Procedures are
implemented and
followed.
Ensure Accurate
transmission of
information on the
COP and make
certain the COP and
Site Procedures are
implemented and
followed.
Ensure
Compliance with
Isolation
Methods
Ensure
Compliance with
Isolation
Methods
establishing and
complying with
isolation
methods
Ensure
Compliance with
Isolation Methods
Ensure Compliance
with Isolation
Methods
Compliance
with Isolation
Methods
Compliance
with Isolation
Methods
Authorised
isolation
Devices
Ensure Compliance
with site isolation
requirements
Ensure
Compliance with
site isolation
requirements
Provide isolation
devices in
accordance with key
requirements
Provide Locks in
accordance with
key
requirements
Provide Locks in
accordance with
key
requirements
Responsible for
performing
isolations
Use of locks in
accordance with
key requirements
Use of locks in
accordance with
key requirements
Use of locks in
accordance
with key
requirements
Use of locks in
accordance
with key
requirements
Competency
and Training
Ensure compliance
with key
requirements
Ensure compliance
with key
requirements
Ensure compliance
with key
requirements and
have input into the
training material. and
assessment process
Participate in
and verify
training or
competency
level of
employee prior
to isolation
Participate in
training as
required
Participate in
level 2 operator
training program
Participate in and
verify training or
competency level
of employee prior
to isolation
Participate in level
1 isolation lockout
and work permit
training program.
Participate in
level 2 operator
training
program
Participate in
level 1
isolation
lockout and
work permit
training
program.
PROCEDURE - TUMUT
ISOLATION & LOCKOUT
LAST PRINTED 8/07/2013 12:49:00 PM UNCONTROLLED WHEN PRINTED VERSION 16 PAGE 14 OF 14
Key
Responsibilities Mill Manager
Production
Manager
Pulp Mill & Paper
Machine Manager
Area Engineers
Operations
Engineers
Senior
Production
Engineers
Isolation
Officer
Maintenance
Engineers
Contractor
Supervisors
Production
Engineers Contractors
Energised
Equipment
Ensure Compliance
with key
requirements
Ensure
Compliance with
key requirements
Ensure training has
occurred for
authorised
individuals and only
those authorised are
to work on energised
equipment
Ensure only
authorised
personnel are
working on
energised
equipment
Ensure only
authorised
personnel are
working on
energised
equipment
Supervise
persons working
on live energised
equipment
Ensure only
authorised
personnel are
working on
energised
equipment
Supervise
persons working
on live energised
equipment
Ensure training
has occurred for
authorised
individuals and
only those
authorised are to
work on energised
equipment
Ensure training has
occurred for
authorised
individuals and only
those authorised
are to work on
energised
equipment
Comply with
working on
energised
equipment
requirements
Comply with
working on
energised
equipment
requirements
Audits and
investigations
Ensure audits are
conducted and
documented
Ensure corrective
actions from audits
are reviewed and
documented and
where required
implemented
Ensure corrective
actions from audits
are reviewed and
documented and
where required
implemented
Participate in
audits where
required
Participate in
audits where
required
Participate in
audits where
required
Participate in
audits where
required
Participate in audits
where required
Participate in
audits where
required
Participate in
audits where
required
Isolation Plans
and Procedures
Ensure compliance
with key
requirements
Ensure compliance
with key
requirements
Ensure compliance
with key
requirements
Produce
isolation plans
and procedures
as required by
key
requirements
Ensure
employees
comply with
isolation plans
and procedures
Produce
isolation plans
and procedures
as required by
key
requirements
Produce isolation
plans and
procedures as
required by key
requirements
Ensure employees
comply with
isolation plans and
procedures
Comply with
isolation plans
and procedures
Comply with
isolation plans
and
procedures
Incidents and
isolation
Breaches
Ensure system for
investigation and
breaches
Ensure all
breaches are
investigated
Investigate any
breaches, incidents,
issues and
determine corrective
actions
Investigate any
breaches,
incidents, issues
and determine
corrective
actions
Investigate any
breaches,
incidents, issues
and determine
corrective
actions
Report all
incidents and
issues and
participate in
investigations
Report all
incidents and
issues and
participate in
investigations
Report all incidents
and issues and
participate in
investigations
Report all
incidents and
issues and
participate in
investigations
Report all
incidents and
issues and
participate in
investigations
top related