Presented by: Smt. Jopilin L. NonglaitProgramme Manager, FFDADirectorate of Fisheries, Shillong
MAWTHADRAISHAN & MAIRANG C&RD BLOCK
FIELD VERIFICATION OF THE SCHEME SPA (2010-11), VALUE CHAIN (2010-11) & RKVY CORPUS FUND (2011-12) IMPLEMENTED UNDER
MSAM
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2531391254
Bundh
Crest width >1.5M
Bottom width < 3 M
Slope 1:1
Depth < 1 M
Overflow pipe 2-4 inch
Drain pipe 8 inch
Percentage of completion 100
Remarks:They will try to raise the pond depth. Previously the pond size is less but now they have constructed another two small ponds to meet the specification.
1. Christian UP School, Nongkasen
MAIRANG BLOCK
Remarks:He has already constructed 6 ponds but 3 are meant for value chain. Seed had been stocked with own expenditure, still waiting for the Departmental fish seed.
2. Shri Emkwingshon Marngar, NongkasenName of the scheme
Value Chain
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.12 Ha
Pond identification Number (PIN)
2530991254
Bundh
Crest width 1-1.5M
Bottom width < 5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe No overflow
Drain pipe 8 inch
Percentage of completion 100
MAIRANG BLOCK
3. Shri Bankitbok Lyngkhoi, Nongkasen
Remarks:Work is in progress, only first installment received.
Name of the schemeValue Chain
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.12 Ha
Pond identification Number (PIN)
2531091254
Bundh
Crest width > 1.5M
Bottom width > 5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 50
MAIRANG BLOCK
4. Smti. Triansinoris Iawphniaw, Langlew
Remarks:Fish seeds had been stocked borne from her own expenditure. Still waiting for the Departmental fish seed.
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2528591256
Bundh
Crest width > 1.5M
Bottom width < 3 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAIRANG BLOCK
5. Shri. Kesparlin Syiemlieh, Marngor
Remarks:Fish seeds had been stocked with own expenditure, 2nd installment received, loan has not clear yet.
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.15 Ha
Pond identification Number (PIN)
2527491256
Bundh
Crest width > 1.5M
Bottom width > 5 M
Slope 1:1
Depth > 1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAIRANG BLOCK
6. Shri Hoben Sohshang, Marngor
Remarks:Fish seeds had been stocked with own expenditure, 2nd installment received, pond constructed through diversion of the river.
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2527691259
Bundh
Crest width > 1.5 M
Bottom width > 5 M
Slope 1:1
Depth > 1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAIRANG BLOCK
Remarks:There is no water in the pond due to leakage, therefore he constructed with cemented wall and work is in progress.
7. Shri Finder Lyngdoh, LanglewName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.2 Ha
Pond identification Number (PIN)
2528991254
Bundh
Crest width > 1.5 M
Bottom width 3-5 M
Slope 1:1
Depth > 1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAIRANG BLOCK
Remarks:He conveyed the message to the Department to extend the supply of feed and fertilizers in the second year also.
8. Shri Welphang Marngar, LaitksehName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2530191246
Bundh
Crest width > 1.5M
Bottom width > 5 M
Slope 2:1
Depth 1-1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Date of stocking 5-09-2013
Percentage of completion 100
MAIRANG BLOCK
Remarks:The water quality is good since he followed what he learnt from the training given to him. He is ready to construct another pond with his own expenditure.
9. Shri Ristarkhos Marngar, LaitksehName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2530091244
Bundh
Crest width 1-1.5M
Bottom width < 3 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 4-5 inch
Drain pipe 4-6 inch
Date of stocking 5-09-2013
Percentage of completion 100
MAIRANG BLOCK
Remarks:The pond is situated in the market place; his interest is to convert it into a tourist spot.
10. Shri Spailin Sohlang, MarkasaName of the scheme
Value Chain
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2531891259
Bundh
Crest width > 1.5 M
Bottom width > 5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 4-5 inch
Drain pipe 4-6 inch
Percentage of completion 100
MAIRANG BLOCK
11. Shri Planningstar Lyngdoh Mawnai, Mawroh
Remarks: The farmer takes interest on pond construction even though the subsidy could not meet his excess expenditure. Pond reconstructed with cement since the wall collapse due to penetration of water.
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2536191388
Bundh
Crest width 1-1.5 M
Bottom width 3-5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 2-4 inch
Drain pipeNot yet installed
Percentage of completion 80
MAWTHADRAISHAN BLOCK
Remarks:Water quality is good since application of cow dung is followed up properly. She wanted to expand her pond little bit bigger. Waiting for the departmental seed.
12. Smt. Drelin Jana, MawrohName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2536091385
Bundh
Crest width 1-1.5 M
Bottom width 3-5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 4-5 inch
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
Remarks:Stocked with 2 quintal of Fish seed purchased from Umsning. Still waiting for the departmental seed since the pond is already exceed 0.1 ha.
13. Smt. Mali Nongbri, MawlumkohkhrangName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.4 Ha
Pond identification Number (PIN)
2535091333
Bundh
Crest width > 1.5 M
Bottom width 3-5 M
Slope 1:1
Depth > 1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
Remarks:Stocked with 2 quintal of Fish seed from own expenditure.
14. Smt. Jrolmai Jana, Phudbah
Son in photo
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.38 Ha
Pond identification Number (PIN)
2535991341
Bundh
Crest width > 1.5 M
Bottom width > 5 M
Slope 2:1
Depth > 1.5 M
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
Remarks:He cleared up the bank loan immediately.
15. Shri Stendro Rani, PhudbahName of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2536191341
Bundh
Crest width > 1.5 M
Bottom width > 5 M
Slope 1:1
Depth > 1.5 M
Overflow pipe 2-4 inch
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
Remarks:Fish seeds had been stocked borne from own expenditure. Still waiting for the departmental seed.
16. Shri Richardpower Lyngdoh Mawnai, Mawshut
Grand father in photo
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2535091369
Bundh
Crest width > 1.5 M
Bottom width 3-5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 2-4 inch
Drain pipe 8 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
Remarks:Fish seeds had been stocked borne from her own expenditure, repayment of loan is completed.
17. Smt. Patricia Lyngdoh Mawnai, Mawshut
Husband in photo
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
253509136
Bundh
Crest width > 1.5 M
Bottom width > 5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe > 5 inch
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
18. Smt. Krossmolin Ryntathiang, Langstiehrim
Remarks: 250 kg of Fish seeds had been stocked borne from her own expenditure, now there many fingerlings hatched from the old brood fish; she also contributed table sized fish during the 1st Aqua fest. Water quality is good.
Husband in photo
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2534291376
Bundh
Crest width 1-1.5 M
Bottom width 3-5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 2-4 inch
Drain pipe No drain pipe
Percentage of completion 100
MAWTHADRAISHAN BLOCK
19. Smt. Wahidir Wahlang, Sangshong
Remarks:
Fish seeds had been stocked borne from her own expenditure, repayment of loan is completed.
Husband in photo
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.1 Ha
Pond identification Number (PIN)
2533291379
Bundh
Crest width 1-1.5 M
Bottom width 3-5 M
Slope 1:1
Depth 1-1.5 M
Overflow pipe 4-5 inch
Drain pipe 4-6 inch
Percentage of completion 100
MAWTHADRAISHAN BLOCK
20. Shri Bakerlang Marbaniang, Sangshong
Remarks:
Repayment of loan is completed; the cost of labour is more since the pond is quite big.
Name of the scheme SPA
Area of the pond to be Constructed
0.1 Ha
Actual area of the pond constructed
0.88 Ha
Pond identification Number (PIN)
2532991379
Bundh
Crest width -
Bottom width -
Slope -
Depth -
Overflow pipe No overflow
Drain pipe 4-6 inch
Percentage of completion 80
MAWTHADRAISHAN BLOCK