Pre cast concrete hollow core slabs in fireTom LennonPrincipal Consultant, Centre for Structural Engineering

BackgroundNatural Fire Safety Concept - adverse press reportsSpallingShear failure - European research Consultation with industryRevised experimental programme

Revised test schedule

Slab A All joints filled. Structural toppingconsisting of 50mm (minimum) depth ofconcrete and a mesh reinforcement (A98mesh with 300mm lap between sheets)

Slab B All joints filled. Hooked reinforcing barsplaced in the joints over the supports.

Fire design scenarioDesign fire load of 570MJ/m²thermal inertia of 945J/m²s½Kopening factor of 0.065m½ based on a single opening 3.6m wide by 2m highapplied static load of 3.66kN/m²floor and walls lined with a single layer of fire resistant plasterboard

Predicted time-temperature response for fire tests on hollowcore slabs (b=945, O=0.065)

0

200

400

600

800

1000

1200

0 10 20 30 40 50 60 70

time (mins)

tem

pera

ture

(deg

C)

Test 1

Results from test 1 - slab AMaximum temperature in excess of 1200ºCmaximum vertical displacement of 100mmresidual deflection of 32mm

precast hollowcore fire test 17.9.01 - average compartment temperature

0

200

400

600

800

1000

1200

0 10 20 30 40 50 60 70

time (mins)

tem

pera

ture

(deg

C)

comparison between average measured temperature and Eurocode prediction - test number 1

0

200

400

600

800

1000

1200

0 10 20 30 40 50 60 70

time (mins)

tem

pera

ture

(deg

C)

average prediction

precast hollowcore fire test 17.9.01

0

20

40

60

80

100

120

0 200 400 600 800 1000 1200

temperature (deg C)

cent

ral d

efle

ctio

n (m

m)

Test 2

Results from test 2 - slab BMaximum vertical deflection of 115mmresidual displacement of 40mmMaximum temperature in excess of 1200ºC

precast hollowcore fire tests - average atmosphere temperatures

0

200

400

600

800

1000

1200

0 10 20 30 40 50 60 70

time (mins)

tem

pera

ture

(deg

C)

average test 1 average test 2

precast hollowcore fire tests - comparison of central deflection

-20

0

20

40

60

80

100

120

140

0 10 20 30 40 50 60 70

time (mins)

defle

ctio

n (m

m)

test 2 test 1

ConclusionsNo evidence of significant spallingLimited cracking along the length of the slab for test 2No integrity failureNo insulation failureNo premature shear failure of the units