PORTFOLIO COMMITTEE ON BASIC EDUCATION
Presentation on:Provincial Infrastructure
ProgrammeASIDI & SAFE
1
PRESENTATION OUTLINE
• Purpose
• National Development Plan
• Background
• Provincial Infrastructure Programme
• ASIDI
• SAFE
2
PURPOSE
To present a progress report onInfrastructure planning anddelivery as well as SAFE to thePortfolio Committee on BasicEducation.
3
NATIONAL DEVELOPMENT PLAN
“Ensure that all schools meetminimum standards forinfrastructure and commit toprogressively upgrading eachschool’s infrastructure to meetoptimum standards.”
National Planning Commission: National Development Plan, November 2011)
4
NATIONAL DEVELOPMENT PLAN…
“School infrastructure backlogs have been considerablyreduced over the past 10 years. But many schoolenvironments are still not conducive to learning.The Department of Basic Education has committed itself toeradicating 496 inappropriate structures, providing basicwater to 1 257 schools, providing basic sanitation to 868schools and providing electricity to 878 schools in the2012/13 financial year. To meet these commitments, thedepartment will have to:• Find ways to deliver infrastructure and services moreefficiently and cost-effectively
• Improve the quality of information used for planning.”
National Planning Commission: National Development Plan, November 2011)
5
NATIONAL DEVELOPMENT PLAN…
“Take learner safety intoaccount when planninginfrastructure.”
National Planning Commission: National Development Plan, November 2011)
6
BACKGROUND• The sector provides infrastructure through three programmes; viz, the provincial
programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) aswell as the Sanitation Appropriate for Education initiative (SAFE)
• The Provincial Schools Build Programme is implemented by provinces and ittargets the provision of basic services, new schools, additions to existing schools,new and upgrading of services and maintenance. It is funded through theEducation Infrastructure Grant and the Provincial contribution through theequitable share.
• The Accelerated School Infrastructure Delivery Initiative is a programme driven bythe DBE to address school's infrastructure backlog on schools that do not meet thebasic safety norms and standards. It is funded through the Schools InfrastructureBacklogs Grant. The purpose of the programme is for the eradication of schoolsmade entirely of inappropriate structures and the provision of basic level ofwater, sanitation and electricity to schools.
• The Sanitation Appropriate for Education initiative (SAFE) is a programme driven bythe DBE to eradicate all pit latrines and other forms of unacceptable sanitation,provide safe and appropriate ablution facilities as well as address insufficient orinadequate sanitation facilities and maintenance of all ablution facilities
7
KEY AREAS• Construction, maintenance, upgrading and rehabilitation of new and
existing infrastructure in education including district and circuit
accommodation;
• Provide infrastructure to match curriculum requirements;
• Replace inappropriate schools;
• Provision of basic services;
• Address damage to infrastructure caused by natural disasters;
• Extend existing schools with additional classrooms/facilities;
• Address achievement of the targets set out in the minimum norms and
standards for school infrastructure; and
• Enhance capacity to deliver infrastructure in education.
8
TOTAL INFRASTRUCTURE BUDGET – 2019/20 FY
EIG
73.8%
ES
12%
SIBG
14.2%
EIG, R 10.514 bn
ES, R 1.713 bn
SIBG, R 2.027 bn
Total Budget = R 14. 255bn
EIG = Education Infrastructure GrantES = Equitable ShareSIBG = Schools Infrastructure Backlog Grant
9
10
PROVINCIAL
INFRASTRUCTURE
PROGRAMME
2019 EIG MTEF ALLOCATIONSProvinces Allocation MTEF Estimates
2019/20 2020/21 2021/22
R'000 R'000 R'000
Eastern Cape 1 585 532 1 564 208 1 685 128
Free State 833 485 722 425 778 272
Gauteng 1 474 715 1 440 169 1 551 501
KwaZulu-Natal 2 187 162 2 013 405 2 169 050
Limpopo 1 050 160 1 175 467 1 266 336
Mpumalanga 731 792 819 111 882 432
Northern Cape 639 817 505 649 544 738
North West 902 484 1 010 169 1 088 260
Western Cape 1 109 331 1 031 186 1 110 902
Unallocated - 1 184 844 1 250 010
Total 10 514 478 11 466 632 12 326 629
11
INFRASTRUCTURE ALLOCATIONS 2019/20
12
Provinces EIG Equitable Share Total% of equitable share
to total budget
Eastern Cape 1,585,532 0 1,585,532 0%
Free State 833,485 16,378 849,863 1.9%
Gauteng 1,474,715 474,821 1,949,536 24.4%
KwaZulu-Natal 2,187,162 359,210 2,546,372 14.1%
Limpopo 1,050,160 1,826 1,051,986 0.2%
Mpumalanga 731,792 202,727 934,519 21.7%
North West 902,484 2,228 904,712 0.2%
Northern Cape 639,817 7,720 647,537 1.2%
Western Cape 1,109,331 648,843 1,758,174 36.9%
10,514,478 1,713,753 12,228,231
TARGETS FOR THE 2019/20 FY
13
No. PROGRAMME
Target 2019/20
EC FS GP KZN LP MP NC NW WC
1 Full Service Schools 0 0 0 1 1 0 0 5 0
2 Provision/replacement of Sanitation 178 73 13 150 13 85 14 12 14
3 Provision/upgrade of Water 178 10 13 150 22 3 9 10 14
4 Provision/upgrade of Electricity 5 10 13 100 1 1 11 0 14
5 Maintenance Projects 20 27 40 370 34 29 36 48 173
6 Libraries Project 5 1 13 12 2 3 4 7 0
7 Laboratories Projects 5 4 13 12 0 1 8 7 0
8 School Halls 0 1 13 0 2 0 5 7 0
9 Technical Workshops 0 0 0 0 0 0 2 0 0
10 Nutrition Centres 5 7 13 10 9 3 5 5 15
11 Additional Classrooms 285 39 350 210 22 104 43 26 68
12 Grade R Classrooms 13 18 200 50 23 3 8 10 73
13 Administration Blocks 5 4 13 10 3 5 4 7 15
14 Provision/upgrade of fence 302 9 13 40 0 1 15 5 15
15 Provision/upgrade of sport field 0 0 13 9 1 3 5 8 15
16 Special Schools 0 0 1 2 0 1 0 0 0
17 Boarding Schools 0 0 0 2 19 0 0 0 018 Guard House 0 0 13 9 4 1 0 7 019 Natural Disasters Projects 2 0 0 150 0 0 0 0 0
NEW & REPLACEMENT SCHOOLS –5 YEAR PERIOD
14
PROVINCE
FINANCIAL YEARS
TOTAL2019/20 2020/21 2021/22 2022/23 2023/24
Eastern Cape 0 1 5 3 0 9
Free State 6 3 2 4 2 17
Gauteng 7 8 7 6 6 34
KwaZulu-Natal 7 5 1 0 0 13
Limpopo 12 4 14 9 11 50
Mpumalanga 2 6 7 5 2 22
Northern Cape 3 2 11 3 5 24
North West 14 3 11 12 1 41
Western Cape 13 7 10 10 10 50
ASIDI 40 31 29 0 0 100
TOTAL 104 70 97 52 37 376
OVERALL INFRASTRUCTURE EXPENDITURE – SEPTEMBER 2019
15
Total Infrastructure Spending as at end September 2019
PROVINCE
Allocated Budget
2019/20
('000)
Total Spent as at
end September
2019 ('000)
% Spent of
Allocated Budget
Eastern Cape 1,585,532 876,882 55%
Free State 849,863 337,569 40%
Gauteng 1,949,536 476,773 24%
KwaZulu-Natal 2,546,372 1,281,619 50%
Limpopo 1,051,986 254,945 24%
Mpumalanga 934,519 545,389 58%
North West 904,712 183,984 20%
Northern Cape 647,537 263,316 41%
Western Cape 1,758,174 781,989 44%
TOTAL 12 228 231 5 002 466 41%
EDUCATION INFRASTRUCTURE GRANT SEPTEMBER 2019
16
Education Infrastructure Grant Expenditure as at end September 2019
PROVINCE
Allocated Budget
2019/20
('000)
EIG Transfers to
PEDs
('000)
Total Spent as at
end September
2019 ('000)
% Spent of
the
transferred
Amount
% Spent of
Allocated
Budget
Eastern Cape 1,585,532 990,958 876,668 88% 55%
Free State 833,485 520,928 330,546 63% 40%
Gauteng 1,474,715 921,697 428,981 47% 29%
KwaZulu-Natal 2,187,162 1,367,157 1,164,205 85% 53%
Limpopo 1,050,160 656,350 254,937 39% 24%
Mpumalanga 731,792 457,370 504,643 110% 69%
North West 902,484 564,052 183,139 32% 20%
Northern Cape 639,817 399,886 260,064 65% 41%
Western Cape 1,109,331 693,332 453,018 65% 41%
TOTAL 10 514 478 6 571 730 4 456 201 68% 42%
MAINTENANCE – SEPTEMBER 2019
17
Prov No. of
Maint’nce
Projects in
2019/20 FY
Overall
Adjusted
Infrastructure
Budget
('000)
Maint’nce
Budget
('000)
%ge
Maint’nce
Budget to
Total
Total
Expenditure as
at end
September
2019
('000)
%ge
Expenditure
on Maint’nce
Relative to
Maint’nce
Budget
Eastern Cape 454 R 1,585,532 R 255,716 16% R 130,786 51%
Free State 27 R 849,863 R 158,668 19% R 39,540 25%
Gauteng 144 R 1,949,536 R 1,083,137 56% R 240,909 22%
KwaZulu-Natal 445 R 2,546,372 R 944,228 37% R 304,308 32%
Limpopo 119 R 1,051,986 R 360,106 34% R 27,249 8%
Mpumalanga 118 R 934,519 R 131,468 14% R 94,759 72%
North West 62 R 904,712 R 114,097 13% R 33,575 29%
Northern Cape 113 R 647,537 R 181,294 28% R 79,729 44%
Western Cape 173 R 1,758,174 R 646,215 37% R 287,283 44%
TOTAL 1 655 12 228 231 3 874 929 32% 1 238 138 32%
PROGRESS – NEW AND REPLACEMENT SCHOOLS
18
SUMMARY OF PROJECTS COMPLTED FOR THE 2019/20 FINANCIAL YEAR
Province
TA
RG
ET
2018/1
9
NEW SCHOOLS
TA
RG
ET
2018/1
9
REPLACEMENT SCHOOLS
TO
TA
L S
CH
OO
LS
T
AR
GE
TE
D
TO
TA
L C
OM
PL
ET
ED
PR
OG
RE
SS
FIR
ST
QU
AR
TE
R
SE
CO
ND
Q
UA
RT
ER
TH
IRD
QU
AR
TE
R
FO
UR
TH
QU
AR
TE
R
TO
TA
L
FIR
ST
QU
AR
TE
R
SE
CO
ND
Q
UA
RT
ER
TH
IRD
QU
AR
TE
R
FO
UR
TH
QU
AR
TE
R
TO
TA
L
Number of Schools
Eastern Cape 1 0 0 0 4 0 0 0 5 0 0%
Free State 7 2 1 3 3 0 0 0 10 3 30%
Gauteng 4 1 1 2 1 0 0 0 5 2 40%
Kwazulu Natal 5 0 1 1 2 0 1 1 7 2 29%
Limpopo 4 1 5 6 4 1 6 7 8 13 163%
Mpumalanga 3 3 0 3 1 1 0 1 4 4 100%
Northern Cape 2 0 0 0 2 0 0 0 4 0 0%
North West 2 0 0 0 5 0 0 0 7 0 0%
Western Cape 4 2 0 2 9 0 1 1 13 3 23%
Total Number of
schools
32 9 8 0 0 17 31 2 8 0 0 10 63 27 43%
IDMS REPORT 2nd QUARTER OF 2019/20 PER PROVINCE
19
ProgrammeTotal Targets for
2019/20Q2
EC FS GP KZN LP MP NC NW WC Total
Number of New Schools 32 0 1 1 1 5 0 0 0 0 8
Replacement schools 31 0 0 0 1 6 0 0 0 1 8
Full Service Schools 13 0 0 0 0 0 0 2 0 0 2
Provision/replacement of Sanitation
776 0 2 2 19 46 23 11 0 0 103
Provision/upgrade of Water 515 0 2 2 64 17 5 1 0 0 91
Provision/upgrade of Electricity
133 0 0 2 2 0 0 1 0 0 5
Maintenance Projects 727 0 0 2 25 4 14 9 0 15 69
Libraries Project 45 0 0 2 4 7 1 0 0 14
Laboratories Projects 51 0 0 2 3 2 0 0 0 9 16
School Halls 30 0 0 0 0 8 0 1 0 2 11
Technical Workshops 8 0 0 0 0 0 0 0 0 5 5
Nutrition Centres 51 0 0 0 4 0 1 0 0 0 5
Additional Classrooms 1020 0 12 0 69 34 21 7 0 15 158
Grade R Classrooms 266 0 3 4 4 5 4 4 0 2 26
Administration Blocks 52 0 0 1 6 55 1 2 0 65
Provision/upgrade of fence 387 0 1 1 30 16 2 3 0 0 53
Provision/upgrade of sport field
28 0 0 0 0 0 0 0 0 0 0
Special Schools 3 0 0 0 0 0 0 0 0 0 0
Boarding Schools 31 0 0 0 1 0 0 0 0 0 1
Guard House 30 0 0 0 2 0 1 0 0 0 3
Natural Disasters Projects 185 0 0 0 17 0 4 0 0 0 21
PROJECT DISTRIBUTION
20
Prov No. of Projects
Budgeted for
PROGRESS
Planning Construction Close-out
EC2,916 1,197 445 1274
FS152 40 112 0
GT 290 216 61 13
KZ 1,311 520 420 371
LP 682 174 387 121
MP 624 409 140 75
NC 405 235 140 30
NW 265 93 64 108
WC 98 69 26 3
TOTAL
6,743
2,953 1,795 1,995
37% 35% 28%
HUMAN RESOURCES
21
Provnce
No of Approved
Posts Filled Not Filled Progress %
Eastern Cape 63 42 21 67%
Free State 78 50 28 64%
Gauteng 101 83 18 82%
KwaZulu-Natal 74 71 3 96%
Limpopo 65 49 16 75%
Mpumalanga 113 97 16 86%
North West 54 30 24 56%
Northern Cape 81 43 38 53%
Western Cape 54 45 9 83%
Total Weight 683 510 173 75%
CAPACITATION PLANS – REQUIRED SKILLS SET
Quantity Surveyors
11% Architects9%
Elec.Engineers2%
Civil Engineers 3%
GIS Specialists1%
Town & Regional Planners
5%
Ed. Facility Planners
9%
Works Inspectors
33%
Finance and administration
27%
22
23
Reports Submission Date Compliance
Final U-AMP for 2019/20 Due 30 March 2019 This is the final plan for all programmes to be implemented over the
period of at least 10 years.
Monthly IRM reports 22 Day of each month This report captures all infrastructure projects being implemented in the
financial year and seeks to present the financial and non financial
progress of projects
End of Year Reports for 2018/19 Due 31 May 2019 The main purpose of the end-of-year report is to measure progress made
by the programme against the objectives and outcomes set, focusing
mainly on the previous financial year
Draft U-AMP 2020/21 Due 28 June 2019 This is a draft plan for all infrastructure programmes to be implemented
over the period of at least 10 years.
Infrastructure Programme Management
Plan (IPMP) & CPS
Due 30 August 2019 The IPMP & CPS is an infrastructure programme management plan
which includes the construction procurement strategy for infrastructure
programmes or projects envisaged to commence within the period for the
medium term expenditure framework (MTEF period). The plan specifies
how the infrastructure programme will be executed, monitored and
controlled.
Human Resource Reports 22 Days after end of each Quarter This report seeks to measure progress of the implementation of the
DoRA Human Resource Strategy. It report provides progress on the filling
of posts on the approved establishment for the infrastructure unit of the
affected provincial department
Non-Financial Performace Reports Due 30 days after end of each Quarter The purpose of this report is to measure quarterly progress made by the
programme against the objectives and outcomes set for the specific
financial year.
MONITORING OF THE PROVINCIAL PROGRAMME
24
PBS 2019/20 ASSESSMENT PROCESSWeighting for the 2019/20 assessment process (R1.185 billion)
Focus Area Documents / Reports Weight
End of the year evaluation report 20%
Human Resource Capacitation 5%
Infrastructure Reporting Model 40%
User-Asset Management Plans 15%
Infrastructure Programme Management Plans
and;
Construction Procurement Strategy
Performance
Planning20%
TOTAL WEIGHT 100%
PROJECT COMPLETIONS | STORMS RIVER PRIMARY
25
Implementing Agent: Department of Public Works
Allocated budget: R 51.1 million
Construction Period: 33 monthsProject completed: January 2019
PROJECT COMPLETIONS | SIVE SPECIAL SCHOOL
26
Implementing Agent: Independent Development Trust
Allocated budget: R124 million
Construction Period: 54 monthsProject completed: June 2018
NOKUTHULA LSEN SCHOOL
27
OLIVENHOUTBOSCH SECONDARY SCHOOL
28
MANDLA MTHETHWA SCHOOL OF EXCELLENCE
29
Thembisa Special School
• Project experiencing intermittent stoppages
30
COMMUNITY DISRUPTIONS
31
32
2019/20 2020/21 2021/22
R'000 R'000 R'000
ASIDI 1 327 048 996 036 1 038 937
SAFE 700 000 800 000 1 300 000
TOTAL 2 027 048 1 796 036 2 338 937
MTEF BUDGET ALLOCATIONS
OVERALL PERFORMANCE
33
2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 TargetedCompleted Q1 Q2 Q3 Q4 Deviation
Inapp
Structures- 17 36 59 52 16 14 21 229 40 14 8 6 -26
Sanitation 41 89 161 152 38 41 32 207 834 311 73 46 27 -238
Water 16 64 135 317 90 35 42 205 957 432 53 39 14 -379
Electricity 148 101 39 18 0 66 0 372
Past Performance
Electricity Scope Completed
Current Financial Year 2019/20
Sub-
Programme
Complete
d since
Inception
DU NOON PRIMARY
34
PHOTOS : CLARKSON/AMAMFENGU
35
| 3
6
CONSTRUCTION PROGRESS – ASIDI 15
Siyavuya JPS
Sihlahleni JSS Mbekweni HS
Sifonondile JPS
| 3
7
CONSTRUCTION PROGRESS – ASIDI FREE STATE
BHEKIZULU JSS
HERMANA PS EBENHAUSER
INTERMEDIATE
TWEESPRUIT PS
2019/20 APP : PROGRAMME 4Strategic Objective Programme Performance
Indicator Medium-term targets
2019/20 2020/21 2021/22
4.2 Provide basic infrastructure services (water, sanitation, electricity) and replace schools built using inappropriate materials on an annual basis in order to improve the conditions under which learners are taught
4.2.1 Number of new schools built and completed through ASIDI 40 31 29
4.2.2 Number of schools provided with sanitation facilities through ASIDI. 717 691 995
4.2.3 Number of schools provided with water through ASIDI. 225 125 0
38
2019/20 APP : PROGRAMME 4QUARTERLY TARGETS
39
Quarterly Targets
Programme Performance IndicatorAnnual Target
2019/201st 2nd 3rd 4th
Number of new schools built and completed through ASIDI 40 8 5 12 15
Number of schools provided with sanitation facilities through
ASIDI717 120 147 210 240
Number of school provided with water through ASIDI 225 147 25 35 18
INAPPROPRIATE STRUCTURES
40
<25% 25%-49% 50%-74% >75%
DBSA 114 3 4 5 2 2 13 98
IDT 31 3 0 0 5 3 8 20
CDC 31 0 2 2 1 2 7 24
DRPW 16 0 0 0 0 0 0 16
NDPW 20 1 3 2 2 7 14 5
DBE# 29 29 29
DBE# 57 57 27 5 8 4 8 25 5
Sub-Total - 298 63 14 17 14 22 67 168
IDT 6 - - - - 2 2 4
DBSA 19 - - - 1 1 18
FSDoE 5 - 0 2 3 - 5 0
Sub-Total - 30 0 0 2 3 3 8 22
KZN Adopt-A-School 3 - - - - - - 3
WC WCED 25 - - - - - - 25
MP DBSA 5 - - - - - - 5
NW DBSA 2 - - - - - - 2
NC DBSA 1 - - - - - - 1
LP DBSA 3 - - - - - - 3
Total 367 63 14 19 17 25 75 229
Projects in
Construction
No of
Projects
Complete
d
FS
Provinces
Implementing
Agents (IA)
Projects
being
Implement
ed
Construction ProgressDesign
&
Procur
ement
EC
Tender Cancelled. Projects to be Re-Tendered
SANITATION PROGRESS
41
<25 % 25% - 49% 50% - 74% >75%
LP 437 - - 2 18 37 57 380
EC 298 17 6 1 14 17 38 243
FS 39 27 - - - - - 12
KZN 116 - 3 3 4 - 11 105
NC 13 - - - - - - 13
NW 18 8 - - - - - 10
GP 14 - - - - - - 14
MP 38 - - - - - - 38
WC 19 - - - - - - 19
TOTALS 992 52 9 6 36 54 106 834
No of
Projects
Completed
Construction ProgressPlanning,
Design &
Procurement
Projects
being
Implemented
PROVINCESProjects in
Construction
WATER PROGRESS
42
<25 % 25% - 49% 50% - 74% >75%
EC520 21 1 - 7 150 158 341
MP36 - - - - - - 36
FS67 14 - - - - - 53
GP0 - - - - - - -
KZN224 6 3 1 - - 4 214
LP364 - 2 14 12 35 62 302
NC5 - - - - - 5
NW3 - - - - - - 3
WC3 - - - - - 3
TOTALS 1 222 41 6 15 19 185 224 957
No of
Projects
Completed
Construction ProgressPlanning,
Design &
Procurement
Projects being
implementedPROVINCES
Projects in
Construction
• Effective monitoring of the provision of infrastructure Professional ServiceProviders (PSP’s) and Implementing Agents (IA’s) that the Department ofBasic Education and provinces are utilizing for the implementation of theinfrastructure programme.
• Monitoring addresses planning, budgeting, expenditure, procurement andproject management. These are interrogated and a sample of projects arevisited. Based on the findings from these visits, remedial actions aredevised with the province and monitored by the DBE.
• Monitoring deals with both programme and project matters;• Programme matters include:- The pattern of overall expenditure being achieved;- Comparisons of expenditure to projected cash flows;- Progress being made with key groups of projects [eg. Water, sanitation,
libraries, laboratories, Grade R]- Management of the portfolio of projects [ie evidence that the programme
of projects is being managed effectively through the project cycle];
MONITORING
43
• At the Project level the focus is on ensuring:
- that PSP appointments are being made;
- that planning and design processes are progressing;
- that the tender process for the appointment of contractors is progressing, that
construction is progressing satisfactorily, [i.e. on programme, on budget, at
acceptable quality…]; and
- that projects are being handed over and closed out and that final accounts are
being wrapped up.
MONITORING (CONT.…)
44
CHALLENGES & REMEDIAL ACTIONS
45
CHALLENGE NATURE OF CHALLENGE
REMEDIAL ACTION
1.
• Declining/ no allocation of the Equitable Share toward Infrastructure Delivery poses pressure on the Education Infrastructure Grant.
• Delay payment to contractors resulting in sites been abandon.
Budget/ Finance • PEDs are to allocate Equitable Share.• Delay projects on pre-construction stage to
commence to construction, whilst awaiting for adjustments.
• Monitor the submission of the invoices of the work done by the IA to ensure that work on ground is equivalent to the expenditure.
• PEDs and the IA to reconcile figures on monthly bases.
2.
• Lack of Programme Management System with reliable data information to enhance the planning and delivery of the required Infrastructure timeously
IT • Deployment and the implementation of a transversal system (EFMS) by all the PEDs to manage the data.
• PEDs to increase the IT capacity to house the system.
3.
• Excessive number of schools requiring maintenance
Planning • Re-alignment and reprioritisation of all the projects earmarked for maintenance to comply with the DoRA condition of the 30% allocation towards the programme.
• PEDs to ensure that projects are assessed to avoid duplications or over emphasis on the same schools.
4.
• Non- compliance with SCM processes resulting in irregular expenditure by the Implementing Agent
Procurement • PEDs to conduct quarterly audits to ensure compliance on all the process.
CHALLENGES & REMEDIAL ACTION (….CONTINUE)
46
CHALLENGE NATURE OF CHALLENGE
REMEDIAL ACTION
5.
• Late appointment of service providers(contractors) by the Implementing Agentfor projects that were already planned anddesigned in previous financial years.
• IA’s lack of capacity resulting in extensionof times, variations orders and delayedoccupation of the asset,
• Inaccurate reporting and poor project andprogramme management.
• Contractors lack of capacity resulting inpoor quality of infrastructure.
• The IAs not meeting the milestone andexpenditure targets as per IPIPs
• The contractual obligations not carried outas per the signed SLA with theimplementing agents
Programme/ Project Management
• Approval of projects for implementation by the PED’s prior to the commencement of implementation.
• The internal capacity through works inspectorsclosely monitors the projects under implementation.
• Monthly progress meeting with IA’s to improve on reporting and to mitigate any challenges.
• Stricter enforcement of timeframes as proposed by FIPDM schedule and the projects reassigned to IA’s that have the capacity to delivery.
• Amendment of the SLA’s to ensure that all engagements are regulated in order to be able to enforce of penalties on non-performing.
• Withdrawing and re-allocation of projects to other performing Implementing Agents.
• Project disruptions by Business Forumsand Local Communities
• Volatility of the construction industry leading to many companies going under and others filing for Business Rescue
Programme/ Project Management
• Continuous engagement with Local Community and Political Leadership to address the identified challenges.
• Effective and close project monitoring and forecasting of trends
BACKGROUND• The audit revealed that 3898 (desktop study) schools
still have inappropriate sanitation facilities.
• An allocation of R2.8 billion has been allocated for the SAFE Initiative over the MTEF as follows:
– 2019/20 : R700 000 000.00
– 2010/21 : R800 000 000.00
– 2021/22 : R1 300 000 000.00
• The SAFE Initiative will be implemented through:
– Provincial EIG allocation
– Partnerships/Donations
– SAFE Initiative Allocation
48
49
AUDIT (PIT LATRINES)
AUDIT: KWAZULU-NATAL
AUDIT: EASTERN CAPE
FINANCIAL REPORT – SAFE ALLOCATION
52
IA No. of Projects
Estimated Total Budget
Paidto date
Invoice at hand Comments
DBSA 240 R 256, 197,789.95 R 0 R 126 410 728.11 Awaiting supporting documents from the IA. (Tranche payment)
DEA 58 R 63 729 187.69 R 0 R0 DEA is awaiting for National Treasury to approve deviation from normal procurement process before any invoice can be generated.
The MvulaTrust
187 R 268 531 197.17 R 0 R 11 847 646.58 Awaiting supporting documents from the IA.(Assessment reports - Planning)
NECT 121 R 100 685 316.15 R 0 R 40 274 126 .46 Awaiting National Treasury approval to extend the scope of work for NECT. (Tranche payment)
TOTAL 606 R 689 143 490.96 R 0 R 178 532 501.15 26% of invoice at hand
PROGRESS ON VERIFICATION
53
Province No. ofSchools
Verification Balance Comments
Verified PIT ProperSanitation
EC 1598 359 305 54 1239 Further verification to commence mid October.
FS 156 0 - - 156* No verification will be carried-out as theprovince is implementing all the projects.
KZN 1365 335 255 80 668 (1030)
362 Schools will not be verified, the provincehas allocated the projects to be implementedwith EIG allocation.
LP 507 259 217 42 248 All the schools will be verified by the end ofOctober
MP 127 88 - - 39* 39 Schools will not be verified, the province isimplementing all the projects with EIGallocation.
NW 145 137 66 71 8 Verification to be completed by 8 October.
TOTAL 3898 1205 843 247 2136
• FS & MP all the schools will be implemented with the EIG.
• 606 of the 843 schools are currently under implementation.
PROJECTS UNDER IMPLEMENTATIONSAFE ALLOCATION & EIG
54
Province No. of Projects Planning Construction
EC 262 262 0
FS 148 80 68
KZN 402 372 30
LP 162 162 0
MP 33 4 29
Total 1007 880 127
• 880 Projects are currently under planning and design phase.
• 127 Projects are currently under construction.
COMPLETED PROJECTS Province No. of Projects Donor EIG & ASIDI
EC 11 4 7
FS 29 29
KZN 93 2 91
LP 35 3 32
MP 20 9 11
TOTAL 188 18 170
55
• To date 188 Schools have been provided with adequate sanitation.
CHALLENGES / REMEDIAL ACTIONSCHALLENGES REMEDIAL ACTION
• Planning and implementing within the same year is the major cause of delay.
• All the projects for the next financial year will be allocated to the IAs at the beginning of the fourth quarter, for planning to commence within the current financial year.
• To ensure that implementationcommences at the beginning of the financial year.
• The procurement process is delaying the commencement of construction.
• Project monitoring to ensure that all projects are completed in time and the quality is up to standard.
• Increase the capacity to monitor project implementation.
57
SEKANEKAMOYI PRIMARY SCHOOL
PROJECT PHOTOS
58
MAMAILA PRIMARY SCHOOL
PROJECT PHOTOS
59
PAAPA PRIMARY SCHOOL
PROJECT PHOTOS
60
TSHINANGE PRIMARY SCHOOL
PROJECT PHOTOS
61
RAMOTLHATSWANE PRIMARY SCHOOL
PROJECT PHOTOS
62
SEKANEKAMOYI PRIMARY SCHOOL
PROJECT PHOTOS
DEDENI JSS - SANITATION
63
64
ASSUPOL DONATION
Ntlhodumela PS
Maaphoko LPS Govani
Govani PS
PLANNING, DELIVERY AND MAINTANANCE
▪ Integrated National School Infrastructure Sector Plan: All schools in the country profiled in
terms of their infrastructure needs in line with Norms and Standards;
▪ Revise Education Infrastructure Delivery Model: This delivery model will address:
▪ Expediting delivery of infrastructure projects,
▪ Controlling the cost of providing education infrastructure and;
▪ Improve Contracts Management Processes;
• Standard Floor Layout Plans and Technical Specifications : Develop standardised plans
and specifications for all Education Facilities (Primary Schools, Secondary Schools, Learner
Boarding Facilities, District and Circuit Offices);
• Establishment of an Education Infrastructure Planning & Management Agency / Bureau:
Infra Bureau/Agency to be set up at national level to centrally facilitate and co-ordinate all the
macro and micro planning processes, implementation, monitoring and evaluation of all
infrastructure projects in the Basic Education Sector.
PLANS TO IMPROVE INFRASTRUCTURE PLANNING AND DELIVERY
65
• Revise project prioritization model to use condition
assessment as a determinant for Project Priority List.
• Utilization of data from STATS SA , like population trends
at a local level, to ensure that size of schools built
addresses the current and future population dynamics;
• Review of SLA’s/MOA’s with IA’s to impose penalties for
non-compliance with progress delivery, deduct management
fees for non compliance or withdraw projects as a result of
poor performance.
• Strengthen Contract Management and Monitoring
processes on infrastructure delivery.
PLANNING, DELIVERY AND MAINTANANCE
66
• Strengthen internal Technical Capacity to implement projects, ensuring:
- Qualified and Professionally Registered key personnel;
- Accredited Project Managers;
• Employee retention strategies for attracting and retention of built
environment professionals:
– Revise remuneration scales for professionals;
– Improve working conditions and provision of tools of trade;
• Increase the use of alternative building technologies for quicker
construction;
• Benchmark with other role players like independent schools to reduce
the cost of building schools;
PLANNING, DELIVERY AND MAINTANANCE
67
FUNDING AND PARTNERSHIPS• Provinces to ensure that sufficient funding is allocated to the Equitable Share
and ring fence such funding for infrastructure;
• Condition Grant allocations (EIG) to be ring-fenced and used solely for the
intended purpose, as a condition of the grant;
• EIG Funding allocations to be per project on the basis of an approved Business
Case and progress on projects implemented;
• Diversified funding modalities for school infrastructure:
• Public-Private Partnerships (Build, Operate & Transfer – BOT);
• Donor and Grant funding;
• Rand-for-Rand Public-Private Partnerships;
• Partnerships with Institutions of Higher Learning and Non-governmental Organizations.
68
RECOMMENDATION
It is recommended that thePortfolio Committee discussesthe progress report onInfrastructure planning anddelivery as well as SAFE.