PARK WEST DRAINPark Township, Ottawa County, Michigan
Project Information Meeting
August 4, 2011
Ottawa County Drain Commissioner
PARK WEST DRAIN
•Final Route•Project Schedule•Estimated Cost•Apportionment Methodology
FINAL ROUTE•Outlet at Winstrom Creek•Perry St•168th Ave•Riley St•Greenly St•Quincy St•Estate Dr•160th Ave
FINAL ROUTE•21 Easements•Project Length• Trunkline Pipe – 5.5 Miles• Branch Pipe – 2.5 Miles• Ditches – 7.5 Miles• Total – 15.5 Miles
PROJECT SCHEDULE
Three Phases
PROJECT SCHEDULE
Phase I•Spring 2012•Work Includes:• Perry St• 168th Ave• Power Line Easement• Portions of Riley St,
Greenly St, & 160th Ave
PROJECT SCHEDULE
Phase II•Winter 2012-2013•Work Includes:• Ottawa Beach Rd
Crossing• Sediment Basins
PROJECT SCHEDULE
Phase III•Spring 2013•Work Includes:• Inlets on 168th Ave• Riley St• Greenly St• Quincy St• Estate Drive• 160th Ave
ESTIMATED COST
$5.9 million•Construction•Engineering•Easement/Property Acquisition•Legal/Administrative Costs
APPORTIONMENT
METHODOLOGY
Costs paid by:
•Park Township at-large
•Ottawa County at-large
•Landowners
APPORTIONMENT
METHODOLOGY
Benefit Factors•Location•Land Use•Parcel Size•Stormwater Management
APPORTIONMENT
METHODOLOGY
Apportionment will be
based on:
•Acreage Within District
•Composite Benefit Factor