palm-3000 management update a. bouchez, j. roberts team meeting #15 10/29/09
Post on 19-Dec-2015
215 Views
Preview:
TRANSCRIPT
PALM-3000
Management Update
A. Bouchez, J. Roberts
Team Meeting #15
10/29/09
PALM-3000
2
Why are we building this again?
• Take a look at the recent NSF ATI proposalhttp://www.oir.caltech.edu/twiki_oir/bin/view/Palomar/Palm3000/NsfAti10
QuickTime™ and a decompressor
are needed to see this picture.
QuickTime™ and a decompressor
are needed to see this picture.
PALM-3000
3
Since the last team meeting
We are now 2/3 of way through the project (in terms of budget…further in terms of schedule!)
Changes since last meeting• First light move back to February 2011, with the system
tear-down and rebuild beginning in July 2010• All component designs are complete. All PDRs have
been held.• External interim cost review was held in February
PALM-3000
4
Management Status
• The biggest concerns are the completion funding and staying on schedule
• Funding– FY10 funding is secure at both JPL and Caltech– JPL MOU report strongly recommended funding the MOU for
another 5 years and specifically funding AO in FY10 and FY11• JPL has funded AO for FY10
– NSF ATI proposal to be submitted by Monday. Would cover 100% of COO FY11-12 funding, and 50% of JPL FY11.
• Schedule– Due to funding concerns, we must push to meet the schedule
• Control of requirements creep will be important• Identify especially challenging requirements and discuss with
management before spending months working on them
PALM-3000External Review
• External Interim Project Review – February 2009– Review of the management plan, scientific
competitiveness and cost to completion– From review committee report:
• “The committee was impressed with the management and commitment of the PALM-3000 team.”
• “The past experience of the team in deploying the existing Palomar AO system gives us confidence that they can achieve the ambitious goals of the system.”
– Only significant technical concern was the 3000-actuator deformable mirror (DM) delivery, which we have addressed
PALM-3000
6
FY10 effort distribution
JPL FY10 LaborPalmer Guiwits Burruss Troy Roberts Truong Angione Shelton
Set FTE's 0.46 1.00 0.65 0.05 0.83 0.75 0.50 0.03Oct 1 0.85 1.00 0.65 0.05 0.65 1.00 0.50 0.1Nov 2 0.85 1.00 0.65 0.05 0.85 1.00 0.50 0.1Dec 3 0.85 1.00 0.65 0.05 0.85 1.00 0.50 0.1Jan 4 0.50 1.00 0.65 0.05 0.85 1.00 0.50 0.1Feb 5 0.50 1.00 0.65 0.05 0.85 1.00 0.50 0Mar 6 0.50 1.00 0.65 0.05 0.85 1.00 0.50 0Apr 7 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0May 8 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0Jun 9 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0Jul 10 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0Aug 11 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0Sep 12 0.25 1.00 0.65 0.05 0.85 0.50 0.50 0
PALM-3000
7
FY10 effort distribution
COO Personnel• Baranec - 5%• Bouchez - 80%• Bui - 25%• Croner - 50%• Dekany - 15%• Hale - 50%• Zolkower - 15%• Palomar - 25% FTE
PALM-3000
8
FY10 Schedule Issues
Critical Path(s)• High-order deformable mirror procurement and testing• Software development
– High Order Wavefront Processor
• Electronics assembly and testing– Especially DM & motor cabling.
Strategies• Will need to track progress on these particular tasks closely.• Management needs to clearly spell out when subsystems must be
ready for integration into the testbed & final system.• Team must inform us when unexpected problems arise.
PALM-3000Schedule Overview
PALM-3000
10
Milestones
• Close servo-loops on I&T testbed: March 2010• Pre-ship review: June 2010.• Decommission PALMAO: July 2010.• First light: February 2011.