overview of bangladesh preparation for interconnection with...

Post on 25-Mar-2018

228 Views

Category:

Documents

6 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Overview of Bangladesh Preparation

for Interconnection with India

Arun Kumar Saha DGM Planning ( In Charge)

PGCB

Dated 19th Sept 2011

The issue Cross Border Electrical Interconnection between

India and Bangladesh have been discussed from long

before but it has got momentum during the visit of Four

member’s Indian delegations headed by Joint Secretary

Power to Bangladesh from 22nd November to 26th

November 2009.

After that MOU was signed between the Governments of

Bangladesh & India for Cooperation in Power Sector on 11

Jan 2010.

Overview:

Keeping in view the technical consideration and reliable operation of both the

System Baharampur (India)–Bheramara (Bangladesh) option was taken for

implementation after several visit & study by the joint technical committee.

Total Scope of the Project:

1. Establishment of 400kV Switching Station at Baharampur (India)

by LILO of Farakka-Jeerat 400kV single circuit line

2. Baharampur (India) – Ishurdi/Bheramara (Bangladesh) 400kV

double circuit line (85km in Indian part & 30km in Bangladesh)

3. Installation of HVDC back-to-back station (400/230 kV) at

Ishurdi/Bheramara (Bangladesh).

Proposed Interconnection with

Bheramara Bahrampur

BOGRASOUTH

BHERAMARA

NAOGAON

NIAMATPUR

FARRAKA

SUBHASGRAM

KATWA

GOKARNA

JEERAT

KHULNA(SOUTH)

BOTTAIL

BAHARAMPUR

CH. NAWABGANJ

RAGHUNATHGANJ

KA

HA

LG

AO

N

SAGARDIGHI

RAJSHAHI

BAHARAMPUR

ISHURDI

NATORE

KHEJURIA

FARIDPUR

BAGHABARI

GHORASAL

MA

DH

OP

UR

SHAHJAD

PABNAPUR

SIRAJGANJ

BOGRA

INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS

400 kV230 kV132 kV

THE PROJECT

LEGEND

BAKRESHWAR

KOLAGHAT

BANGLADESH

INDIA

400kV D/c

(400 KV)

MALDA

DHULIAN

DURGAPUR

Existing

Under Constr. / Future

JAYPURHAT BARAPUKURIA

Schematic Diagram of Grid Interconnection between Bangladesh

(Bheramara) and India (Baharampur)

230 kV

Bheramara

400 kV from

India

Bangladesh (Bheramara)-India (Baharampur) Grid

Interconnection with HVDC

a) Objectives : (i) To Facilitate exchange of electricity between Bangladesh & India.

(ii) To establish a Grid Interconnection with India.

(iii) To minimize the power crisis in Bangladesh to some extent..

b) Main Components (BD part): i) 30 km 400 kV double ckt transmission line

ii) 400 kV Back-to-Back HVDC station at Bheramara.

c) Project Cost (BD Part) : Total =Tk 1,078.69 Crore

F. E = Tk 700.00 Crore

L. C = Tk 378.69 Crore

d) Financing : ADB : Tk. 700 Crore

GOB : Tk. 277.24 Crore

PGCB: Tk. 101.45 Crore (FC : Tk 34.54 Cr.)

e) Project Completion Year : 2012-13

Proposed Land

for HVDC Station

Location of Proposed HVDC Station (in Google Map)

Bangladesh India Grid Interconnection Project:

Update of Bangladesh part:

Transmission line (400kV: 30km & 230kV: 05km):

• Tender Invited on 28-Feb-2010

• Contract awarded on 30-Dec-2010 (effective from 01-March- 2011)

• Completion time: August 2012.

• Contractor: Cobra (Spain)

• Contract value : FC –9.428 MUSD,

LC–Tk 35.996 Cr.

• Route Alignment Survey completed

• Plan Profile Approved (excluding the termination towers).

• Work Plan submitted & work is going on as per work plan.

• Planned profile for LILO of 230kV Ishurdi Khulna Line under

verification

• Overall physical progress 17%

Bangladesh India Grid Interconnection Project:

Update of Bangladesh part:

HVDC Station (400-230kV, 500 MW) at Bheramara, Bangladesh:

• Tender Invited on 28-Feb-2010

• Contract awarded on 29-March-2011 (effective from 01-June-2011)

• Completion time: May 2013.

• Contractor: Siemens ,Germany.

• Contract value : FC -76.622 MEURO,

LC – Tk 156.97 Cr

• Single Line Diagram approved

• Draft Layout approved

• Drawing Submission started

• Some Drawings approved

• Soil Resistivity Test started

• Overall physical progress 16.5%

Bangladesh India Grid Interconnection Project:

Update of Bangladesh part:

Land Acquisition & Development for HVDC Station at Bheramara:

• Total Land Area: 113 Acre

• Land Acquisition: Completed

• Land Development : Under way (67% Completed)

• Approach Road: Completed.

Grid Interconnection Between Bangladesh-India Project

Soil Testing for Transmission Line

Grid Interconnection Between Bangladesh-India

Project

Dredging From Padma River

(For Land Filling of HVDC Substation site)

Grid Interconnection Between Bangladesh-India

Project

Earth Filling

Grid Interconnection Project

04 / 07 / 2011

Earth Filling

Grid Interconnection Between Bangladesh-India

Project

04 / 07 / 2011

Land Development

Grid Interconnection Between Bangladesh-India

Project

04 / 07 / 2011

Land Development

Grid Interconnection Between Bangladesh-India

Project

04 / 07 / 2011

Land Development

Grid Interconnection Between Bangladesh-India

Project

04 / 07 / 2011

Land Development

Thank you all

top related