FOR LEASELos Angeles, CA

• New ownership: GI Partners

• 3 MW of power available immediately; 9MW currently in design process with LADWP

• 21 MW of utility power on site, expandable by 28 MW to a totalof 49 MW, supported by:

• 10 existing 2 MW generators with additional designed twelve 3 MW generators in N+1 configuration

• 4,400 ton central condenser water plant in 2N configuration

• Approximately 24,000 SF floorplates

• 13’ slab-to-slab heights, 90 lbs floor loading, 4” concrete slab

Alex Smith312 470 3841 alex.smith@cushwake.com

Katherine O’Hara312 470 3846 katherine.ohara@cushwake.com

Cushman & Wakefield Copyright 2015. No warranty or representation, express or implied, is made to the accuracy or completeness of the information contained herein, and same is submitted subject to errors, omissions, change of price, rental or other conditions, withdrawal without notice, and to any special listing conditions imposed by the property owner(s). As applicable, we make no representation as to the condition of the property (or properties) in question.

29th Floor LayoutJune 7, 2016

THE MOST INTERCONNECTED BUILDING IN THE WESTERN U.S. Gateway to Asia Pacific

Sample full floor cabinet layout