ON THE JOB TRAINING REPORTArranged by : XII

TGB A

1. Arif Budi Kusuma (05)

2. Galih Prasetya (09)

3. Hesti Romadhoni (13)Svhs 2 wonogiri2014

PT. METROPOLITAN LAND TBk.

Metland Menteng Project

Metland Menteng is one of PT.

Metropolitand Land Tbk. Project. It is a

housing area in Ujung Menteng,

Cakung, East Jakarta. The wide of the

area is 120 ha.

“CARLA TYPE HOUSE69/96”

PT METROPOLITAN LAND TbK.Metland Menteng Project

PROJECT STRUCTURE Of METLAND MENTENG

First Stage

Metland Menteng

Second Stage

Tjikini Garden Harmoni Cluster·Gladiola

·Caliandra

·Mergareta

·Algania

·Cordia

Valeria Cluster·Regina

·Valbo

·Sienna

·Celsa

·Cascabella

·Calia

·Valeria

Teresta Cluster·Florice

·Jasmine

·Carla

·Stella

Site PlanIndonesia has tropical climate

character. Position of house in

common in facing east. But this

house desain is across north and

south, because this are position

and the arrangement of the doors

and windows can be done well. So

air can circulate fastly.

Wide of The Space

a. Prominent Bed Room = 100% x 3 x 6 = 18b. Bed Room = 100% x 3 x 3 = 9c. Living Room = 100% x 2,55 x 3 =

7,65d. Family Room = 100% x 3,3 x 3 =

9,9e. Kitchen & Dinning Room = 100% x 3,3 x 3

= 9,9f. Shared Bath Room = 100% x 1,43 x

2 = 2,86g. Front Porch = 50% x 1,2 x 2,1 =

1,26h. Back Porch = 50% x 0,8 x 1 = 0,4i. Balcony = 75% x 1,2 x 2,1 =

1,89j. Cartport = 50% x 3 x 5 =

7,5 68,4 69

Setting The Space

KETERANGAN :: RUANG PUBLIK: RUANG SEMI

PUBLIK: RUANG PRIVAT

: RUANG SERVICE

Building structure

FOUNDATIONFoundation is the bottom

structure of building that has

function the carry the burden of

the top of building’s foundation.

This house uses mini/strauss pile

type of foundation.

SLOOF

COLUMN

STAIR

Stair functioned like connector

between floor in storied building.

Finishing of the stair uses wood

floor. It is Parqued

BEAM

FLOOR

ROOF FRAMEWORK

WALLWall function as

structure element for

support burden. This

house uses ageed and

paint.

Any questions..?

THANK YOU...!

HESTI ROMADHONI/13/XII TGB A