3Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
Market entry through acquisition of Wavegen
Entry into Tidal Current Power through in-house development
Voith Hydro’s two step strategy to enter the wave and tidal sector
4
Voith HydroOcean Technologies
Ocean Technologies
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
Tidal:Voith Hydro Ocean Current
Technologies GmbH & Co. KG
Voith Hydro Tidal Co. Ltd., Seoul
Wave:Voith Hydro Wavegen Ltd., Inverness
8
Voith Hydro Wavegen
Inverness
• Headquarters.
• Wave tank.
• Turbine test rig.
Islay
• Limpet Test Facility.
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
9
Oscillating Water Column concept: Huge air pump drives Wells Turbine
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
10Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
Fixed pitch Wells TurbineOscillating Water Column
Oscillating Water Column conceptScheme
11
The concept is intensely tested on our test plant LIMPET on ISLAY
• 10 years grid connected operation
• World’s first commercial scale grid connected wave energy plant
• Reference plant and test bed
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
12
Availability of test Machines
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
64%70%
90%93%
96% 98% 98%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2005 2006 2007 2008 2009 2010 2011
13
• Client: Ente Vasco de la Energía (EVE)
• Power plant integrated into breakwater
• 300kW(16 x 18.5kW turbines)
• First grid-connected wave energy plant in Spain
First commercial plant officially opened: The Mutriku Wave Power Plant
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
14
A look inside the Mutriku plant
Damper
RunnerGeno
Diffuser
Runner
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
15
The plant room of the Mutriku plant
Mechanical and electrical equipment installed by VHTO from February to April 2011
Commissioning started by VHIN in mid May
• All machines operational within 4 weeks
• SCADA commissioning due to complete by end of June
Plant is running successfully since official opening
���� 30,000 turbine hours
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
16
Built-in simplicity as guiding design principle for our tidal technology
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
20
Project Update Jindo Korea
Project Location:
• Flow Speed Max. 3.5 m/s
• Water Depth 35.0 m
HyTide 110-5.3 Technical Data:
• Rated Power: 110 kW at 2.9 m/s
• Rotor Diameter: 5.3 m
• Direct drive, seawater lubricated bearings
• Permanently excited generator
• Gravity based concrete foundation
Project Status:
• Turbine installed in spring 2011
• 3 month on-going testing
• currently retrieved
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
21
Installation of Gravity Base Foundation
• 1600 ton floating Barge Crane
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
23
Site was used to test turbine under extreme conditions
Upstream (Ebb direction):
• Perfect orientation of turbine
• Low turbulence – no large scale eddies
Downstream (Flood direction)
• Very large turbulence – large scale eddy super-imposed
Very good test environment: If turbine can be controlled in both very extreme directions, understanding of technology is maximum
Due to site limitations theoretical capacity factor cannot exceed 17%
26
first test results are very promising
Power curve
Velocity [m/s]
P [k
W]
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.00
20
40
60
80
100
120
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
28Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
Prototype certificates for Jindo 110kW turbine
To our knowledge no competitor has so far achieved that
29
Project Update EMEC 01
Site Data EMEC01 / Scotland
• Flow Speed: 4.5 m/s
• Water Depth: 33.0 m
Technical Data HyTide 1000-16
• Rated Power: 1 MW at 3.5, 2.8 m/s
• Rotor Diameter: 13.0 m up to 16.0 m
• Direct drive, seawater lubricated bearings
• Permanently excited generator
• Drilled monopile foundation
Status:
• Turbine in Manufacturing
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
32
North Sea GiantMulti Purpose Offshore Construction Vessel
Dimensions:
• 160,9 m Length
• 2900 m² Deck Space
• 21 MW Power
• Konsberg DP III
• 5 Voith-Schneider Units
• 1x 400 to Crane
• 1x 50 to Crane
• Comfort Class 3
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
34
Working Principle of the BSD 3000
Idea: Work from above surface with flexible umbilical connection in order to cope with motion on the sea
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
35
Mobilisation and Sea Fastening of Drilling Equipment
North Sea Giant DP3 Vessel:
• 22 MW power
• 5 Voith Schneider Props
• 400 tn crane
• 2900 sqm deck space
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
38
Monopile
Length: 23,8 m
Weight: 98 to (incl. rigging)
Diameter: 2 m
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
41
z-drive VSP
Vessel motions in bow quartering waves
DP Performance
Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
55Ocean Energies at Voith Hydro | Brunsbüttel | 2012-11-30
Contact:Dr. Raphael ArlittHead of Basic DevelopmentTel. +49 7321 37-6072Raphael.Arlitt@voith.com
top related