Document No : Samsung/WCC2/SCFT Quality Assurance/Guidelines/2015/07
Prepared By
Arjun Anand ( WCC2 & SCFT QA Engineer)
Reviewed by
Dhruvrajsinh Rana (WCC2 In charge / Central SCFT QA Manager)
Vikrant Tawade (National SCFT Manager)
Approved by
Satyendra Kumar Singh (Head- Deployment)
Distribution List:
• RRMs
• Circles RF leads & Circle Heads.
• HQ SCFT Team.
• SCFT Quality Assurance Team and NEO Team
Guidelines and Recommendations for SCFT
Version 1.0
1
INDEX:
1. Purpose and Objectives.
1.1. Purpose.
1.2. Reasons for SCFT Quality Implementation.
1.3. Objectives.
2. Guidelines.
2.1. Guidelines for Circles.
2.2. Guidelines for Central SCFT Optimizers.
2.3. Guidelines for Accepting Avg. UL/DL Throughputs Circles &
Central SCFT Team.
2.4. Guidelines for WCC2 Quality Assurance Team.
3. SCFT WCC2 Process Matrix.
4. SCFT Quality Escalation Matrix.
4.1. For Backhaul Issue/GTP Losses support.
4.2. For Actix One Issues support.
4.3. For FTP related Issues support.
4.4. For SCFT On field issues support.
2
1. Purpose and Objectives.
1.1. Introduction & Purpose.
Objectives and quality guidelines for SCFT is mandatory to be considered and to
be implemented at all levels of operations. Quality assurance is the key role in
execution of WCC for SCFT completion.
Purpose to release this guideline is to ensure the minimum errors in validation of
SCFT Reports. It will ensure the precautions and implementations of effective
methods to improve the quality of SCFT completion at the Circle/Zonal level as
well as the National level, so as to accelerate and increase the percentile of WCC
Approval. This is possible only when errors, lack of co-ordination, etc. will be
overcome and updated guidelines will be shared uniformly to all the Solpars,
Circle Head, RF Optimizers, RRMs, WCC Quality Assurance Team.
1.2. Reasons for SCFT Quality Implementation.
DL/UL throughput issues.
Main KPI failure issues ( Coverage objective ,Single Sector Swap, VoLTE call
Test, UE attach, Handover)
Re-drives.
Excessive or less drive issues.
Non-referral BSP & drive routes before conducting SCFT drive.
No pre-check to Backhaul Issue, GTP Losses, Alarm status, neighbor site
status (ON/OFF).
Azimuth and Tilt issues impacting main KPIs and Throughputs.
Lack of coordination with Field Engineers.
3
Mechanical Tilt must be 0o for all the eNBs before accepting the SCFT
Reports.
1.3. Objectives.
Avg. DL-UL throughput should be considered as main KPI effective from
16-June-2015.
For 2.3G:
Avg. DL throughput greater than/equal to 15MBPS, and
Avg. UL throughput greater than/equal to 1 MBPS
is only acceptable otherwise reject.
For 1.8G:
Avg. DL throughput greater than/equal to 5MBPS, and
Avg. UL throughput greater than/equal to 2.5 MBPS
is only acceptable otherwise reject.
Main KPI failures like
PROBLEM:
Coverage objective failure(COF) due to less than 80% samples
collected in main BSP of respective sectors.
CAUSE:
a.) Due to wrong PCI samples or poor RSRP collected within main BSP.
b.) Inaccessible/non-drivable roads for collecting samples.
RESOLUTION/HANDLING:
a.) BSP should be referred before conducting the SCFT drive.
b.) Drive route should be studied before conducting the SCFT drive.
4
c.) Samples should be collected within main BSP for respective eNB.
d.) Important roads should not be missed.
PROBLEM:
Sector swap KPI failure due samples more than 50% collected in
other sector BSPs.
CAUSE:
a.) Excessive drive done on the periphery of main BSP.
b.) Excessive drive in null zone b/w the sectors.
c.) Less separation b/w sectors.
d.) More samples collected out of BSP.
RESOLUTION/HANDLING:
a.) BSP should be referred before conducting the SCFT drive.
b.) Drive route should be studied before conducting the SCFT drive.
c.) Samples should be collected within main BSP for respective eNB.
PROBLEM:
Handover KPI failure b/w the sectors.
CAUSE:
a.) Sectors not covered properly.
b.) Alarm ON if any.
c.) HO not defined on enB.
RESOLUTION/HANDLING:
a.) Drive clockwise & anticlockwise to meet HO.
b.) Pre-check the alarm from LSMR.
c.) Ensure the HO defined within PCIs.
5
PROBLEM:
VoLTE calls KPI failure & UE attach KPI failure.
CAUSE:
a.) UE functioning issue.
b.) Improper PCI latching, etc.
c.) IMS/Core registration failure.
d.) HW/SW/Link Issues.
RESOLUTION/HANDLING:
a.) Ensure proper PCI latch.
b.) Need to ensure UE is working proper before SCFT.
PROBLEM:
Low Avg. UL and Avg. DL throughputs.
CAUSE:
a.) FTP space not available.
e.) Backhaul and Packet Losses.
f.) Alarm running on site.
g.) Excessive drive at the periphery of main BSP.
h.) Excess drive done in null zone.
RESOLUTION/HANDLING:
a.) Pre check Alarm status, Backhaul Issue, Packet Losses and FTP space
status before SCFT.
b.) Refer hard copy of BSP, and study the drive route map before SCFT.
Plan SCFT drive to be executed in first time right (FTR), just to avoid re-
drives.
6
Ensuring these objectives implementation on the front will improve the
Quality of SCFT. These objectives will ensure the acceleration in WCC2 process
to the end point. Issues will be minimum; SCFT validation ratio will be
improved. Main objective to implement SCFT QUALITY GUIDELINES is to bring
the rejections to null point.
2. Guidelines.
Implementation of quality guidelines is to be processed and to be distributed
uniformly and at all the levels of Operations, so as to extract the best result.
2.1 Guidelines for Circles.
ISSUE ACTION TO BE TAKEN
BY CIRCLE ACCEPTANCE
CRITERIA/EXCLUSIONS LOCAL RJIL APPROVAL
1. Coverage Objective fail
1.)Drive in complete BSP area. 2.)Don’t do excessive drive in periphery of BSP. 3.)Important roads should not be missed. 4.)Circle Head/SCFT Lead/SCFT Coordinators ensure that Solpars carry BSPs hard copy & drive routes before conducting SCFT drive.
No exclusion if fails.
For cases like road blockages,
inaccessible roads, Circle team
ensures instructing the DT
Engineers to collect the proper
snapshot with GPS Lat./Long.,
BSP plot, Google snapshots,
proofing the scenario and for
same mail approval from RJIL
CTO with SAP ID can be given.
2. Handover failure.
1.)Do walk test below site. 2.)Drive clockwise & anticlockwise to meet HO. 3.)Do neighbor check from LSMR before SCFT.
No exclusion if fails. No RJIL Approval if fails.
7
3. Sector Swap failure.
1.)Drive more roads in main lobe to improve coverage samples. 2.)Do not drive excessively in null zone and periphery of the main BSP. 3.)Pre-check the site plan, and accordingly cover the roads to avoid azimuth mismatch issues.
Exclusion available if sector swap fails in only
1 sector (excluding azimuth mismatch
issues).Need to give reasonable justification
along with BSP plots and Google snapshots.
No exclusion if fails in more than 1 sector.
No RJIL Approval if fails in more than 1 sector.
4. VoLTE MtoM Call failure
1.)Need to ensure UE is working proper before SCFT.
2.)Should stand below the enB within 5m radius, ensure the proper PCI latch, and then carry out the test.
No exclusion if fails. No RJIL Approval if fails.
5. UE attach failure.
1.)Need to ensure UE is working proper before SCFT. 2.)Should stand below the enB within 5m radius, ensure the proper PCI latch, and then carry out the test.
No exclusion if fails. No RJIL Approval if fails.
6. Cell Overshooting and Undesired lobes failure.
1.)Avoid excessive drive in periphery of main BSP. 2.)Pre-check the neighbor site is turned OFF. 3.)Ensure the M/E Tilts according to ATP11A.
Exclusion available for COS and USL. Can be
justified providing the failure sectors details
with reasonable remarks.
No RJIL Approval required.
8
7. Low UL/DL throughputs
1.)Ensure pre-checks for any Backhaul Issue, GTP Losses, Neighbor site status (ON/OFF), Alarm ON if any before SCFT. 2.)Avg. DL and Avg. UL throughput for both 2.3G & 1.8G must meet the threshold. (For throughputs target details: Refer section 2.3) 3.) Ensure pre-check for FTP space availability before SCFT.
No exclusion if fails. No RJIL Approval if fails.
Circle Team need to ensure to execute the SCFT Drive first time right(FTR)
just to minimize requirement of re-drive.
If any Lat/Long of eNB is mismatching the actual plan of Site Forge, should
be escalated at the same time to the responsible team.
Mechanical Tilt must be 0o for all the eNBs before accepting the SCFT
Reports.
2.2 Guidelines for SCFT Field Engineer.
Field Engineer needs to ensure to carry safety equipment before SCFT.
Ensure pre-check to UE and Tools performance before SCFT.
Carry hard copies of BSP and refer drive routes before SCFT.
Collect Alarm status for eNB before SCFT.
Ensure to cover main BSP to collect good samples.
Excessive drive at the periphery of main BSP should not be carried out.
Do walk test wherever necessary if drivable roads is inaccessible/missing.
9
Capture the snaps with GPS Lat/Long for road blockages & in accessible
roads for demonstration and intimate the same immediately to Circle
Head/RF Lead/SCFT Coordinator.
Need to ensure to upload all the log files (if auto upload not functioning)
properly. Nomenclature for log files should be actual and proper.
Mechanical Tilt must be 0o for all the eNBs before accepting the SCFT
Reports.
Handling of Log files
After completion of SCFT Drive, FE needs to upload all log files immediately
and turn OFF the UE and only then should leave the site.
*Note:
SCFT Reports will not trigger on Site Forge/Actix if
Incomplete log files available.
Nomenclature for files is improper. So, Naming the log files should be
correct.
FE will ensure that all log files
(.drx format) are uploaded
through XCAL to FMS
Actix One will generate SCFT
report from log files will be
uploaded on Site Forge.
FMS will convert all log files from .drx
to .drm format and will upload the files
to Actix One server
10
2.3 Guidelines for Central SCFT Optimizers.
SCFT Optimizers have to effectively validate the SCFT Reports. They are
responsible for providing proper analysis remarks for each case where
justification is required. Below the main parameters are provided where SCFT
Optimizers’ attention is required.
Optimizers can accept the reports without any remarks only when :
a.) All the Main and Info KPIs meet the threshold, and
b.) All the plots are available for further analysis at WCC2 final validation
level.
Targets for accepting Avg. Throughputs:
Category Avg. DL Throughput Avg. UL Throughput
1.8G >=5MBPS >=2.5MBPS
2.3G >=15MBPS >=1MBPS
**GTP/I-perf snapshots are not under consideration temporarily as NEO &
RANCORE is performing test on Backhaul & GTP Losses. Once any update
releases, will be circulated to all immediately.
**GTP/Iperf is to demonstrate Low Avg. DL TPT due to packet loss. It cannot
justify Low Avg. UL TPT.
Any value less than the provided targets are not acceptable for Low avg.
UL/DL throughputs.
Mechanical Tilt must be 0o for all the eNBs before accepting the SCFT
Reports.
11
For Low Avg. DL TPT cases, acceptable attachment scenario:
Attachment type1: Only Original GTP Losses screenshot is
considerable reflecting SAP ID and date (Should be exactly same as of
SCFT drive done date) and packet loss should be greater than 0.02 in
the attached file.
Attachment type2: Only Original Iperf screenshot is considerable
reflecting IP Address of eNB and packet loss %age in the screenshot
along with eNB IP details screenshot from Site Forge (Path provided
below for eNB IP details screenshot from Site Forge).
Path for Site Forge to extract eNB IP Details:
Samsung Viewer Site Forge Login>Sites>Filter SAP ID>RAN>eNodeB
IP Details>Capture Screenshot.
SCFT Optimizer need to attach RJIL CTO approval mail for cases like
inaccessible roads, roads blockages, where KPIs impacted due to fewer
1.SAP ID
2
3 4.eNB IP Details
12
samples collected. In addition, Google snapshots for available roads, BSPs
with drive plots should be attached in the report.
** Approval mail must have the SAP ID in the mail body, else it will be
treated invalid and site will be rejected.
For cases like Cell overshooting and Undesired side lobes failure, Optimizers
have to give justification remarks with particular sectors in analysis tracker.
For E.g. a) Cell overshooting failure in Alpha/Beta/Gamma/All sectors.
b) Undesired side lobes failure in Alpha/Beta/Gamma/All sectors.
Single sector swap failure case can be accepted under exclusion criteria,
but analyzer must provide the reason behind swap occurred (like less
drivable area, small BSP, excessive drive, less separation between sectors
only where applicable).
Single sector swap due to azimuth issues, samples collected completely
outside BSP are not acceptable at all.
Optimizers do not have to accept any Main KPI failure. Though exceptions
can be considered if mail approval from RJIL CTO with respective SAP ID is
attached.
Central SCFT Team need to take care of the rejected sites from WCC2 ,and
have to resolve the rejection cause. Once the case is resolved, priorly need
to update to WCC2 QA Team within the TAT provided.
For any pending cases, regular follow up is to be taken, same status to be
shared to WCC2 QA Team within TAT.
If plots in the report are missing, Optimizer needs to provide Unique
remarks in analysis sheet for the missing plots with reference attachments.
13
Turn Around Time to revert on the Issue Tracker.
Responsible Tasks Responsibility TAT
Internal & External rejection of site
list is to be shared with Central SCFT
Lead
WCC2 QA Team. 1 DAY.
SCFT Rejection site resolution/To
Justify or provide required input to
pass rejected sites.
Central SCFT Team 3 DAYS.
2.3 Guidelines for Accepting UL/DL Throughputs for
Circles/Central SCFT Team.
These guidelines should be treated as valid and should be uniformly circulated
among all the Circles, Central SCFT Optimizers. This is mandatory to bring this in
immediate effect.
Targets for accepting Avg. Throughputs:
Category Avg. DL Throughput Avg. UL Throughput
1.8G >=5MBPS >=2.5MBPS
2.3G >=15MBPS >=1MBPS
**GTP/I-perf snapshots are not under consideration temporarily as NEO &
RANCORE is performing test on Backhaul & GTP Losses. Once any update
releases, will be circulated to all immediately.
**GTP/Iperf is to demonstrate Low Avg. DL TPT due to packet loss. It cannot
justify Low Avg. UL TPT.
14
2.4 Guidelines for WCC2 Quality Assurance Team.
WCC2 Quality Assurance Team is responsible for checking the quality of
validated sites and eligible for Accept and Reject the sites which are approved
from RJIL CTO, before final submission for WCC2.
WCC2 QA Team has to accept the Avg. DL/UL throughput according to
the threshold decided (Refer section 2.3).
Single sector swap can be justified where justification is been provided
by SCFT Optimizers.
Any main KPI failure is not acceptable unless mail approval for the
reason caused from RJIL CTO with respective SAP ID is attached to the
report.
KPI Info like DL Throughput and UL Throughput, where threshold is not
meeting, and Related snapshots like GTP Losses snapshot and RSSI
snapshot with proper SAP ID, Loss percentage, and Date are not
attached, should not be accepted at any cases.
WCC2 QA Team must analyze the drive plots before rejection of failure
cases.
Mechanical Tilt must be 0o for all the eNBs before accepting the SCFT
Reports.
15
3. SCFT WCC2 Process Matrix.
SCFT Drive completed by FE
SCFT Optimizers Accept/Reject
the SCFT Reports
RJIL CTO Accept/Reject the SCFT
Reports
WCC2 QA Team pre validates the SCFT Reports and
Accept/Reject the Reports before WCC2 final submission.
RANCORE Approves the submitted BATCH for WCC2. If
needed rejection is done by RANCORE.
RANCORE Approved sites are submitted as hard copy to
Billing Dept. for processing billing.
Uploading log files (C1,C2,C3….)
If accepted
If accepted
If accepted
If accepted
If rejected, SCFT
Coordinator will
follow up with
Solpar to
overcome the
rejection.
If rejected,
Optimizers will follow
up with circle/ Other
project team to
overcome the
rejection.
If rejected
If rejected
If rejected
If rejected, Issue
tracker will be
acknowledged to
Central SCFT Team.
SCFT Team needs to
revert on issue
tracker within TAT.
If rejected
If rejected, It will be
added in issue
tracker and will be
circulated to the
respective Circles to
revert back on same
within TAT.
16
4. SCFT Quality Escalation Matrix.
4.1 For Backhaul Issue/GTP Losses support.
I&C Contact details and Escalation Matrix
ZONE
LEVEL1 REPORTI
NG
CIRCLE
CONTACT DETAILS
LEVEL 2
REPORTING
CONTACT DETAILS LEVEL 3 REPORTING (I&C
Managers)
NZ Prasun
Chakravorty
DL 9990110899 p.chakravort@samsung.com
Samir Ranjan Mahar
ana
9953497869 samir.ranjan@sa
msung.com
Vivek Kamboj vivek.kamboj@samsung.com;8527389988;0124-6625005
NZ Ajay
Singh Rawat
UP-E
7838593247 ajay.rawat@samsung.com
Surendra
Singh Baghel
e
9582997731 s.baghele@samsu
ng.com
NZ Amit Jain UP-W
7838795967 amit.jain02@partner.samsung.com
Sanjay Warath
e 9582307415
s.warathe@samsung.com
NZ Abhishek Jaiswal
PJ 7838380790 abhi.jaiswal@samsung.com
Nikunj Pandey
8800417690 nikunj.p@partner
.samsung.com
NZ Abhishek Pandey
HR
7838591891 abhi.pandey1@samsung.com
Manoj Sharma
7838652773 manoj.mishra@s
amsung.com
NZ Naveen Kumar Sharma
HP
8930053509 naveen.sh@partner.samsung.com
Shyam Naraya
n Gupta
9560899052 sn.gupta@samsu
ng.com
NZ Puneet
Khanduja J&K
8860089649 pk.khanduja@samsung.com
Bhaskar
Sharma 9891117507
bk.sharma@samsung.com
If not resolved
For any Backhaul
Issue/GTP Issues
SCFT Engineer / Circle RF Lead
will escalate the issue to
respective LSMR Engineer
(Circle wise)
LSMR Engineer will raise the Ticket to CISCO
to get the issue resolved in 24 hours (1 day)
and once issue is resolved need to revert to
Circle RF Lead for same.
LEVEL 1
Only if issue is not resolved within 24 hours
by LSMR Team, Level 2 Escalation can be
processed to the respective LEVEL 2
Reporting Team.
LEVEL 2
17
EZ Yogesh Chorage
Kol
9821591720 yogesh.dc@samsung.com
Nilanjan Das
Chowdhury
9830911774 n.chowdhury@sa
msung.com
Pravin Kokate p.kokate@samsung.com
9324285806;022-44759617
EZ Krishnendu Das
WB
9987517897 krishnendu.d@samsung.com
Yogesh Chorag
e 9821591720
yogesh.dc@samsung.com
EZ Swayam Sambit
Das
OR
7718990660 swayam.das@samsung.com
Vipin Singh
Sisodiya
9560599513 v.sisodiya@sams
ung.com
EZ Chandan
Das JHK
9004970293 chandan.das@samsung.com
Navneet
kumar pandey
7033807895 navneet.pandey
@ril.com
EZ Modassir Mukhtar
BH
7666952121 modassir.m@partner.samsung.com
Gajanan dipak
Patil 7710048424
g.patil@samsung.com
EZ Manoj Patil
A&NE
7498864359 manoj.patil@samsung.com
Jayant kanubhai Patel
7715037962 jk.patel@samsun
g.com
WZ Jatin
Harioudh MU
9769865444 j.harioudh@samsung.com
Ahtesham
Ahmed 7489448110
a9.ahmed@samsung.com
Kunal Gandhi kunal.gandhi@samsung.com 9920922019;022-44788045
WZ Madan Mohan Singh
RJ 7718032285 madan.m@partner.samsung.com
Prakash
Somidi 9819052235
pr.somidi@partner.samsung.com
WZ Manoj Patidar
GJ 7738150335 manoj.p2@samsung.com
Irfan Ahmed Siddiqu
i
7498480407 ia.siddiqui@sams
ung.com
WZ Rahul Bansal
MP
7718851730 rahul.bansal@samsung.com
Rahul Goyal
7738056715 rahul.goyal@ril.c
om
WZ Yogesh Ugale
MHnG
9867952733 yogesh.ugale@partner.samsung.com
Mohit Pandya
8860661930 mohit.pandya@s
amsung.com
WZ Uday Patil
CHG
9987577811 u.patil@partner.samsung.com
Mukesh
Pandey 8452882850
pandey.mu@partner.samsung.com
SZ Manish Kumar
KL 9561094870 manish.kr2@partner.samsung.com
Madhav
Vyawhare
7498480569 m.vyawhare@sa
msung.com
Abhijit Lokhande ABHIJIT.L1@samsung.com
9867698548; 022-44759635
SZ Pravin
Sharma AP
8080045345 pravin.s@samsung.com
Prafull Kumar
9321183532 prafull.kumar@partner.samsung.c
om
SZ Satish C
Jain TN
9987755051 satish.jain@samsung.com
Manoj Tiwari
9323460952 manoj.rp@partne
r.samsung.com
SZ Ganesh Mankar
KTK
9987908577 g.mankar@samsung.com
Shivaraj Seena
9916149655 shivaraj.s@samsu
ng.com
18
4.2 For Actix One Issues support.
Level Reporting Contact Details
1st Level
1. Nasheer Mohammad.
2. Tabrez Khan
3. Subhash Yadav.
4.Suresh Thakur-(Also provides XCAL & FTP support)
1. nasheer.mohammad@ril.com.(08454888008)
2. tabrez.khan@ril.com.(07738000988)
3. subhash.ch.yadav@ril.com(08898514550)
4. suresh.k.thakur@ril.com.(09004599988)
2nd Level Madhuraj Y. Madhuraj.y@samsung.com(07718881698)
If not
resolved
For Actix related
Issues
SCFT Analyzer will escalate the
issue to respective LEVEL 1
Dedicated Helpdesk.
1. Nasheer Mohammad. 2. Tabrez Khan
3. Subhash Yadav. 4.Suresh Thakur
LEVEL 1
madhuraj.y@samsung.com
LEVEL 2
19
4.3 For FTP related Issues support (Specifically for FTP Health
issue impacting Avg. DL/UL throughputs).
Level Reporting Contact Details
1st Level Suresh Thakur (suresh.k.thakur@ril.com.(09004599988)
2nd Level
1. East – Purna Chandra Biswas.
2. West – Srinivas Ghule.
3. North – Amit Kundra.
4. South – Satish Shenoy.
1. 09830080867
2. 09004663178
3. 09971522749
4. 09620921362
If not
resolved
For FTP server related
Issues.
Circle RF Lead will escalate the
issue to Suresh Thakur
(suresh.k.thakur@ril.com.(090045
99988)
East – Purna Chandra Biswas.
West – Srinivas Ghule.
North – Amit Kundra.
South – Satish Shenoy.
LEVEL 1
Regional EPC RRMs will take follow up with
RJIL EPC Circle Leads to get the resolution
and to revert back to Circle SCFT Team.
Regional EPC RRMs will take follow up with
RJIL EPC Circle Leads to get the resolution
and to revert back to Circle SCFT Team.
LEVEL 2
20
4.4 For SCFT On-field issues support.
For any on field support during SCFT drive like UE issue/
Tools issue (XCAL, Net Velocity, etc.)/ eNodeB/ VoLTE/FTP
Issues –
War-room Helpdesk is available for online support from
Mon-Sat between 9AM-11PM. Engineers are available on
Helpline numbers provided below for supporting any type
On field queries/issues along with Cisco and Cerragon Team
(10AM-7PM) related to SCFT.
Helpline Numbers (9AM-11PM):
022-44787680;
022-44787742.
In addition, For XCAL and FTP support:-