04/13/23 1
Software Engineering
scope
04/13/23 2
Project Management – Project Scope Function of
Functionality Resources Time
The Mythical Man-Month, Anniversary Edition : Essays on Software Engineeringby Frederick P. Brooks
Establishing Minimum User acceptance Reasonable probability of success
04/13/23 3
Cost estimation techniques
Techniques Expert Judgment Algorithmic
Model developed
04/13/23 4
Example of expert judgment
04/13/23 5
Typical Cost Estimation Roadmap1A. Use comparisons with past jobs to estimate cost & duration directly or to estimate lines of code (Expert Judgment).
and / or
1B. Use function point method to estimate lines of code
1B.1 Compute un-adjusted function points.
1B.2 Apply adjustment process.
2. Use lines of code estimates to compute labor and duration using COCOMO formulas.
04/13/23 6
Cost estimation
Techniques for expert judgment Estimation by analogy Parkinson’s law (work expands to fill the time
available) Time avail x people available (12 mo’s X 5
people = 60 person months) Not good can get in trouble big time
Pricing to win (Market Share) ditto
04/13/23 7
Estimate Task Durations Based on Expert Judgment
1. Estimate the minimum amount of time it would take to perform the task. We'll call this the optimistic duration (OD).
2. Estimate the maximum amount of time it would take to perform the task. We'll call this the pessimistic duration (PD).
3. Estimate the expected duration (ED) that will be needed to perform the task.
4. Calculate the most likely duration (D) as follows:
D = (1 x OD) + (4 x ED) + (1 x PD) 6
04/13/23 8
Assumptions Requirements are categorized as either Essential (needed to support 3 shifts, multiple
plants and more vehicle types) or Recommended. The requirements are interrelated. Omitting or changing a requirement may affect the
estimates for other requirements. The estimates are “rough order of magnitude” having a degree of accuracy of +100% to –
50%. Estimates are for planning/budgeting purposes. Engineering changes implemented on day boundary. Business system assigns system indicator and plant executes schedule. No dynamic
routing of vehicles by plant. Same model can be built at multiple plants with different part effectivity or part numbers. No shop calendar by model. Same model built on multiple system within a plant Plant operates 3 shifts, 5 days/week. Customer may require training for new tools and processes. Backups are taken during CICS downtime. (same as today) Applications support only English language. Estimates include requirements definition, design, specifications, coding, testing,
installation, project management, documentation and function points. Modifications to user developed applications (Focus) not included. Financial, Warranty, HR, and client server application modifications not included in estimate
04/13/23 9
RATING SCHEME FOR INTERFACE LEVEL OF EFFORT
Low Medium High Extra
Conversions Up to 15 days (A)
16 – 30 days 31 – 45 days 30-90 days
Interfaces Up to 15 days 16 – 30 days 31 – 45 days 30-90 days
Reports Up to 10 days 11 – 20 days 21 – 35 days 30-90 days
Enhancements Up to 15 days 16 – 30 days 31 – 45 days 30-30 days
04/13/23 10
Type
R/B
Description Size Comments
ANEMS
I B BOM - Vehicle part structure. Parts List (APO30)
EXTRA
Assumption is EIM for current and future. Include OPsheet data in interface file if needed to support LCCN
I B Unit BOM structures (axles, engines etc)
MEDIUM
Process code
I B Part master add information MEDIUM
From design changes, replaces ECW part add function. (mastered data)
I B Part master reconciliation for class, process code etc.
LOW Developing model segment data, balance out,/carry over/new, part description
Type: I = Interface into SAP, O = Interface out of SAP, E = Enhancement, A = Assumption R/B: R = Real time, B = Batch
Estimating Difficulty
04/13/23 11
ANEMSFunctions and Assumptions E/R Est. Hrs.
Internal Cleanup (100 pgms)-part number format-dead fields/screens-mis-labeled fields/data integrity-navigation-100 pgms
R 2,000
Activate multi-plant capability E 2,000
New BOM -feed from ANEMS-populate/reconcile new bill of material (ANEMS => DB2)
E 1,000
New BOM is facility specific-BOM unique at each facility-convert existing structures (one time extract)
E 400
New BOM functionality-stand alone bills (maintained in COPICS today)-easier maintenance-independent parts (Brazil, China, Mexico)-what if-where used-estimate 6 CICS pgms
E 1,000
Propagate new BOM to other systems-estimate 50 pgms to change
E 4,000
Implement the equivalent of a single EIPL per day (parts list) E 1,000
Implement more automatic releasing within ANEMSRelieve labor intensive input and release of design notes
R 400
Eliminate/replace ECW to eliminate duplicate data kept in ANEMS and Part Master-estimate 11 screens and 1 database
R 1,600
Total Hours 13,400
04/13/23 12
Assumptions
Stay with IMS/DC where possible
Anems remains and feeds new BOM
New BOM replaces COPICS
Engineering changes implemented on day boundary
Same model can be built at multiple plants with different parts or part effectivity
Customer Process Changes
Parts Arrangement owns and maintains new BOM
Total Hours 69,880 for 16 applications
04/13/23 13
Estimating LOE wuth Function Point Analysis FPA is a method to break systems into smaller
components, so they can be better understood and analyzed
Function Points measure software by quantifying its functionality provided to the user based primarily on the logical design
Function Point Analysis tries to understand the dynamic relationship between transactions and data stores. On a conceptual level, function point analysis helps
define two abstract levels of data - data at rest and data in motion.
See www.ifpug.com (International Function Point Users Group web site)
04/13/23 14
Steps in FP method
Identify functions in the system Compute each functions contribution Apply difficulty factors to each function Compute the general characteristic
contributions (weights) Calculate the adjusted function point
total
04/13/23 15
Step 2 Function Point Computation for a Single Function (IFPUG)
Function
External Inputs (EI)
External Inquiries (EIN)
External Outputs (EO)
fileExternal Logical Files (ELF)
filefile
Internal Logical Files (ILF)*
* Internal logical grouping of user data into files
Logicalgroup ofuser data
Logicalgroup ofuser data
Logicalgroup ofuser data
04/13/23 16
Definitions
EI External Inputs (EI) - is an elementary process in which data crosses the boundary from outside to inside.
EIF External Interface Files (EIF) - a user identifiable group of logically related data that is used for reference purposes only
EO External Outputs (EO) - an elementary process in which derived data passes across the boundary from inside to outside
EQ External Inquiry (EQ) - an elementary process with both input and output components that result in data retrieval from one or more internal logical files and external interface files.
ILF Internal Logical Files (ILF) - a user identifiable group of logically related data that resides entirely within the application boundary and is maintained through External Input
04/13/23 17
Function Point Computations (IFPUG) (Unadjusted -- to be followed by applying adjustment process)
Ext. inputs EI … 3 or… 4 or ... 6 = ___
Ext. outputs EO … 4 or … 5 or ... 7 = ___
Ext. inquiries EIN … 3 or … 4 or ... 6 = ___
Ext. logical files ELF ... 5 or …7 or ... 10 = ___
Int. logical files ILF ... 7 or …10 or ... 15 = ___
PARAMETER simple complex
countTotal
04/13/23 18
Unadjusted Function Point Computation for First Encounter Functions:“Set up”
Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.
04/13/23 19
Unadjusted Function Point Computation a set of processes
Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.
04/13/23 20
General Characteristics for FP Adjustment 1-7
1. Requires backup/recovery? 0-2
2. Data communications required? 0-1
3. Distributed processing functions? 0
4. Performance critical? 3-4
5. Run on existing heavily utilized environmt.? 0-1
6. Requires on-line data entry? 5
7. Multiple screens for input? .... continued 4-5
0 incidental average essential
1 2 3 4 5none moderate significant
04/13/23 21
8. Master fields updated on-line? 3-4
9. Inputs, outputs, inquiries of files complex? 1-2
10. Internal processing complex? 1-3
11. Code designed for re-use? 2-4
12. Conversion and installation included? 0-2
13. Multiple installation in different orgs.? 1-3
14. Must facilitate change & ease-of-use
by user? 4-5
0 1 2 3 4 5
General Characteristics for FP Adjustment 8-14 incidental average essential
none moderate significant
04/13/23 22
Costs - productivity
Object Counts When 4gl and higher level language used Count objects (not to be confused with object classes)
Object points Screens produced - 1-3 Number of reports 2/5/8 Number of 3GL modules to be developed to support 4GL 10
points
Function point + Code estimation Code size = AVC x FPC
4GL 2-40 loc/fp Assembler 200-300 loc/fp Java 53 loc/fp
04/13/23 23
Computation of Adjusted Function Points (IFPUG)
(Adjusted) Function points =
[ Unadjusted function points(41) ]
[ 0.65 + 0.01 ( total general characteristics ) ]
41 x [0.65 + 0.01 x (24 to 41))] = 36 to 43
Loc = (36 to 43) x 53 =1.9 to 2.3 kloc (java)
04/13/23 24
Basic COCOMO Formulae (Boehm)
Effort in Person-months = aKLOC b
Duration = cEffort d
Software Project a b c d
Organic 2.4 1.05 2.5 0.38
Semidetached 3.0 1.12 2.5 0.35
Embedded 3.6 1.20 2.5 0.32
Due to Boehm [Bo]
Organic – stand aloneEmbedded – hardware software systemsSemi detached - mix
04/13/23 25
Computing COCOMO Case Study ModelsVERY EARLY ESTIMATES
Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.
04/13/23 26
Later revisions to estimate
Need to account for Product reliability and complexity (RCPX) Reuse required (RUSE) Platform difficulty (PDIF) Personnel Capability (PERS) Personnel Experience (PREX) Schedule (SCED) Facilities (FCIL)
Effort =a x Kb x M M=(RCPX)(RUSE)(PDIF)(PERS)(PREX)(SCHED)(FCIL)
04/13/23 27
Use Case size and effort estimation
Count key aspects of the requirements Unadjusted point count
Use several question sets about the team and the environment Create a fudge factor
Multiply the unadjusted count by the fudge factor Yields the adjusted point count Translate into person hours LOE (level of effort)
estimate Karner* proposes 20 person hours /UCP * Gustav Karner 1993 M.Sc. thesis
04/13/23 28
A Use Case Based Method
Begin with actors Determine if simple average or complex
04/13/23 29
A Use Case Based Method
Weight Use Cases Based on the number of transactions
(scenarios) in the use case Can use Analysis classes instead, if they have
been identified
04/13/23 30
Determine the unadjusted use case points (UUCP) Weighted Actors + Weighted Use Cases =
UUCP
10 + 50 = 60
04/13/23 31
04/13/23 32
Determine the total Technical Complexity Factor (TCF)
(0.01 * Tfactor) + 0.6 = TCF or(0.01 * 42) = 0.6 = 1.02tcf
Then calculate the size of the software (Use Case) project by multiplying UUCP by TCF
UUCP * TCF = SzUC60 * 1.02 = 61.2
04/13/23 33
Calculate the Experience Factor for the team
04/13/23 34
Calculate the Experience Facto
Add all the factors to get the total EF = 12
Calculate the Experience Factor (EF) by multiplying EF by -0.03 and adding 1.4 (-0.03 *EFactor) + 1.4 = EF (-0.03 * 12) = 1.4 = 1.04
04/13/23 35
Finally Calculate the Use Case Points (UCP) and Effort1. Calculate total points (UCP)
SzUC * EF = UCP 61.2 * 1.04 = 63.648 Or
UUCP * TCF * EF = UCP 60 * 1.02 * 1.04 = 63.648
2. Calculate Man Hours1. count the number of factor E1-E6 that are below 3 and the number of E7-E8 that
are above 3; if total is<= 2, use ER = 20; if total is 3 or 4 use ER = 28; if total is 5 or more consider restructuring the teamER * UCP = total ManHours20 * 63.648 = 1,272.9628* 63.648 = 1782.44
04/13/23 36
Risk and Reports Adjust for Risk
Use a historically derived risk coefficient Multiply Man hours by 1+ coefficient Assume for demo .05 (1.0 + .05) * 1,782.144 = 1.871.25 (adjusted man hours)
Adjust for reports List all reports if possible. Assign simple, average, complex ratings Based on historical data assign man hours by level Compute total additional hours and add to total
1871.25 + 940 = 2,811.25 total man hours
04/13/23 37
Estimate Cost and Duration Very Early in Project
1. Use the function point method to estimate lines
of code
2. Use Boehm’s formulas to estimate labor
required
3. Use the labor estimate and Boehm’s formula to
estimate duration
04/13/23 38
Sample Scope Tracking
Access data base discussion