Integrating Renewables into the European Power System

1

Dr. Susanne NiesCorporate Affairs Manager, ENTSO-E

EU-GCC Workshop: Electricity Interconnections and Trading for Growth and Efficiency

21 May, 2017

ENTSO-E INSTRUMENTAL FOR THE CHANGE

2

300 000 km of

transmission lines

3300 TWh electricity

consumption

43 TSOs

36 countries

over 500 million

customers servedof the global

electricity

consumption

15%

Network Codes facilitate EU policies

• 260 GW of RES connected

• 25 GW in 2016

• >10 GW of EU demand

side response

• NO multi-state interruptions recent years

• Up to 300 coordinated tasks/day in a RSC

• Hundreds trained employees in RSCs

programs and offices

• 23 states and 85% of European

consumption market coupled

• 10 million data files made available

yearly for 2500 daily users of

ENTSO-E transparency platform

Security of supply

Competitiveness & Social WelfareSustainability

Network codes

THE ENERGY TRANSITION

Wind

Solar

Hydro

potential

Flow

North-south

Flow

North-East

South-West

Illustration of main RES potential across Europe towards 2030

27% RES policy goal means 45%of generation from renewables in the power transmission system

+30% energy

efficiency

-40% CO2

emissions

27%

Renewable

Energy

Sources

The EU’s 2030 goals

EU TARGETS NEED ADEQUATE INFRASTRUCTURE

Regional differences & needs

must be considered

TSOs plan adequate

infrastructure investments

(TYNDPs)

Exchange of

flexibility

Geo-

political

Loop-flows

Physical

congestions

Market

integration

TYNDP 2016 investments at

€150bn

80% of TYNDP projects are due to

accommodate RES into the system

6

BUILDING GRIDS AND CREATING VALUE (TYNDP 2016)

Consumers Society/Climate

Higher grid cost:

1,5 – 2 €/MWh

Lower wholesaleprices:

1,5 – 5 €/MWh

Emissions down by:

50 – 80%

Reduced spillage of renewable energy by:

30 – 90 TWh

Emissions

reduction

only due

to grid:

8%but…

7

Aggregated PV feed-in from selected Continental Europe TSOs, 20

March 2015

22

GW

at

9.30a

m

35 GW

at

12.00

am

14 GW

at

10.00

am

The 2015 solar eclipse as a test for the future

challenges

• Successful preparation and cooperation avoiding disturbances

• Minimum cost: 4.2 M€ for additional reserves, cost of a black-out (~450-600 M€ / hour for

Germany)

• Increasing risks: expected RES ramping of 32GW/h after the eclipse in August 2027

(14GW/h in 2015)

Situation Solutions

1 Coordinated security analysis

> TSOs coordinated their assessment of the situation

2 Coordinated planning

> Anticipation of issues> Secured reserves and emergency plans

3 Real-time coordination between TSOs

> Real-time communication between TSOs during the eclipse

> Frequency quality was maintained

8

The Flexibility challenge

A new role for our networks…

From asset……………………………………..

8

……to smart optimization of generation and load

56% wind power: End-consumers play an

increasingly important role

September 2016 in

Denmark, one week (source Energinet.dk)

Pag

e 9

Flexibility

Service

Providers Flexibility

Bids

Single

Flexibility

Platform

Coordination

functions

3 Single (national) Flexibility Platform

Activations

TSO

Bid selection

for TCM and

Balancing

(specific)

DSO

Bid Selection

for DCM

EU Common

MOL

Bid selection

for

Balancing

(standard)

Data exchanges after Balancing Energy GCT

Activations Balancing

Bids with

Restrictions

Activation

Requests

Flexibility Bids

Limitations

Activation Information

Flexibility Bids

Limitations

Activation Information

Grid impact

analysis

Grid impact

analysis

RES Integration is possible, when..

1

2

3

4

You set the right market framework

You build the grid for it

You establish active system management, with active

customers, smart meters, digitalisation

You have a ONE system approach!

THANK YOUFOR YOUR ATTENTION