N.C. 12 Rodanthe Bridge
STIP Project No. B-2500BProject Update | June 3, 2021
2
Please NoteMICROPHONES ARE MUTED
If you are calling in(872) 240-3212 Access Code: 651-543-237
please mute your phone during the presentation
If you wish to submit a comment or question, during the meeting:1. Use the chat box
Or2. Call: 984-205-6615 enter code: 8679 leave message
**your message will be transcribed, and presenters will receive it during the meeting**
– Introduction of NCDOT staff in attendance
– Review of past update meeting questions and responses
– Project update
– Questions and comments
Questions or comments?Use Chat Box or Call – 984-205-6615 enter code: 8679
NCDOT Staff
4
Sterling Baker, PEDivision Engineer
NCDOT Highway Division 1
Pablo Hernandez, PEResident Engineer
NCDOT Highway Division 1
Byron KyleDesign Build Project Engineer
NCDOT Design Build Unit
Diane WilsonSr. Public Involvement Officer
NCDOT Public Involvement, Community Studies and Visualization Unit
Review ofthe March 4, 2021update meeting
5
Responses to questions submitted at the December 3meeting were presented
Pablo Hernandez presented an update on the project status
__________________________________
Responses to the questions submitted on March 4 follow
6
What will happen to the ‘s-turns’ road?_________________________________
Current plans show this area cross hatched which means the roadway will be removed
The plans also show the turnaround that we will install at the north end of the Mirlo Beach subdivision
7
What are plans to ease traffic on N.C. 12 during the high visitor season?_________________________________
Construction activities during high visitor season will be restricted – no daytime lane closures between June 15 and September 15 –
After September 15, there are no lane closures Friday afternoon to Sunday night
Impact should be minimal
8
Are lane closures anticipated in the spring as earthwork / paving resume?
_________________________________
With paving ongoing at north end, no affect to travel on N.C. 12
New roadway contractor is working on plans for south end where there could be more involvement with N.C. 12 traffic but because of
the newness of the contractor (to the project), we are giving them time for getting a plan together
9
Will there be a fishing area on the bridge?_________________________________
There are no plans for fishing access on this structure
_____________________________________________
How many miles of N.C. 12 does the bridge abate?_________________________________
About 2.8 miles will be bypassed
10
What is the average clearance under the bridge at the highest point?
_________________________________
Approximately 17’ – 4” from Water line to bottom of bridge
Bridge will not be high rise or ‘humpback’ like Currituck Sound or Oregon Inlet bridges
11
When will the roundabout at the southern end be started and completed?
_________________________________
Constructing the roundabout now/early was considered.
However, maintaining traffic on N.C.12 in existing alignment from the Liberty Gas Station to the S-curves during construction due to bridge not being completed would cause issues with traffic backups during
the high-volume timeframe
12
13
Is there a bike lane on the bridge?_________________________________
No dedicated bike lanes on the bridge
8’ wide shoulders like on Oregon Inlet Bridge – on both sides
All paved areas associated with project will have 4-8’ paved shoulders like the remainder of N.C.12 down to Hatteras
What are you doing to prevent ocean over wash into Milo Beach after the road is removed?
Are you installing some protection going east to west to protect what has become a traditional wash out area?
_________________________________
At the end of the Mirlo Beach subdivision, along a portion of remnant N.C. 12, sandbags in the dune south of the refuge boundary will remain
Sandbags will be installed and a new dune running east west will be built at the end of the N.C. 12 remnant
One of the challenges along N.C.12 is over wash from many different points. The Department will do our best to maintain drivable access
on the remnant14
June 3, 2021 Update
Questions or comments?Use Chat Box or Call – 984-205-6615 enter code: 8679
June 3, 2021
16
Construction on the bridge is approximately 75% complete
____________________________
Expenditures as of May 25, 2021$ 133,257,611
(includes design, permitting & claims settlement)
Adjusted Contract Value $155,024,024
June 3, 2021
17
90 of 108 Bents have been installed ( 297 of 352 piles )
___________________________
288 of 388 Concrete Girders set__________________________
80 of 107 Deck Spans cast
June 3, 2021
18
Pile driving on the northern portion of the project still has its challenges. (north & south end separated by ~ 2,600ft)
Current technique to help ease the pile installation, (augering the soil inside the cylinder pile),
has shown positive results with pile installation
At this time anticipate pile driving could be complete in early September 2021
June 3, 2021
19
At this time, the two work trestles are not planned to meet
The north work trestle will be first to be removed while the southern work trestle continues toward the north to
complete the bridge
The trestle components, gantries & cranes will be dismantled and trucked off the bridge
June 3, 2021
20
Phase 1 of CHEC’s transmission line relocation at the north end of the bridge is underway
The riser poles and other adjustments have been madeUnderground bore should begin later in June.
At the south end of the bridge CHEC has completed phase 1 for relocating the transmission lines (U/G bore & riser poles)
June 3, 2021
21
Resuming roadway work at the south end of the project has not been determined yet
The early morning concrete placements will likely resume in mid-June
Bridge completion is currently projected for late 2021 or early 2022
Contact Information
22
Pablo HernandezNCDOT Resident Engineer’s Office – Manteo
252-473-3637
NC12-Rodanthe@publicinput.com
Questions or comments?Use Chat Box or Call – 984-205-6615 enter code: 8679
23
Next UpdateSeptember 2, 2021
6:00 p.m.
Location to be Announced
Questions or comments?Use Chat Box or Call – 984-205-6615 enter code: 8679