miso wisconsin relationship public service commission randel pilo, assistant administrator august 7,...
Post on 18-Jan-2016
214 Views
Preview:
TRANSCRIPT
MISO Wisconsin Relationship
Public Service CommissionRandel Pilo, Assistant Administrator
August 7, 2008
Potential Benefits from an ISO
Production Cost Savings for Ratepayers By Dispatching Generation Over Larger Footprint. {~3-4% Savings}
Increased Use of Transmission System in Terms of Flow without Decreasing Reliability
Less Reliance on Physical Curtailments on Congested Transmission Lines.
Prevent Utilities that Own Generation and Transmission From Exercising Vertical Market Power, Whereby Grid Access is Denied or Overpriced to Other Utilities.
Better Price Signals for Construction of New Generation or Transmission.
Consolidation of Functional Areas like Contingency Reserves and Regulation to Create Savings
Coordinated Inter-regional Transmission Planning & Analysis
Potential Downsides to RTOs
Set Up Costs for Control Centers, Computers, and Operation. Central Dispatch needs Effective Market Monitoring to Make Sure
No Strategic Pricing or Capacity Withholding Occurs. Market Design Must Be Correct Loss of Economies of Scope. Utilities Who Were Efficiently
Operating Their Combined Transmission and Generation Assets May Experience Increased Costs Due to Disaggregation.
Settlements Process for Transactions Can Be Complex and Subject to Dispute.
Seams Can Exist Creating Operational and Cost Disparities Federal and State Jurisdiction Legal Issues Abound.
Present Issue Areas
$420 million Arrowhead-Weston Line was Excluded from Regional Cost Sharing; PSCW is Challenging this in Federal Court.
Transmission Planning—MISO, Xcel, ATC, and PSCW roles– Several Ongoing Transmission Studies with Results Due in 2009.
Transmission Cost Allocation—RECB1 and RECB2. – Presently, regional cost sharing is set at 20% of project cost.
Resource Adequacy—MISO has proposed an administrative fee approach in conjunction with a voluntary excess capacity auction.
Prevention of Non-competitive Pricing by Market Generators. Targeted Load Shedding in Real Time . Should US DOE and FERC have Siting Autority over Projects in
Wisconsin? – Congestion Conference in Chicago mid September 2008.
MISO Membership
PSCW continues to monitor. 2007 Stakeholder study suggested staying in
MISO because there would have been a $51 million exit fee, and the other options did not look much more appealing.
Need to constantly assess due to membership changes, ongoing construction of new lines in MISO footprint, and cost sharing implications.
Make sure MISO continues to bring value.
PSCW Watchdog Functions
PSCW participates with Regional State Committee, Organization of MISO states containing 14 states, or OMS.
PSCW interacts directly with RTO Board, Management, and MISO Staff. Dedicated Commissioner with 6 technical staff as backup.
PSCW Intervenes in Appropriate FERC Dockets
Costs Examined in Rate Proceedings
Appendix
Congestion Fixes In Progress—ATC. 2007 Energy Prices in Key MISO Zones. Market Monitor Synopsis on MISO pricing. Potential Transmission Improvements in Upper
Midwest under study in MTEP.
2007 ATC Top Ten Congested Elements& Approved PSCW Projects Addressing Congestion
KeyBLACK –
Congested element rank and nameRED –
Projects that address congestion
#7,#8 & #9 Stiles – Pulliam#6 Highway V - PrebleMorgan – Werner West (2009)
#3 Hintz – Werner#4 Ellington – Hintz#8 N Appleton – Werner WestWeston Unit 4 (2008)Gardner Park – Hwy 22 (2009)
#2 Arpin – Eau ClaireArrowhead – Weston (2008)
#1 Paddock TransformerPaddock-Rockdale (2010)
#5 Pleasant Valley – Arthur RoadSaukville – St Lawrence (2008)
LMP Differentials Into ATCAnnual - 2007
*
ATC$54
NI $48IL $47
MN $56
MISO $51
Minnesota Hubhigher than ATC
Illinois Hubs lower than ATC
Executive Summary:
The Midwest ISO energy markets performed competitively in 2007.Although certain suppliers in the Midwest ISO have local market power, therewas very little evidence of attempts to exercise market power in 2007.Hence, mitigation measures were employed infrequently to address economicwithholding that would have increased energy prices or uplift costs.
The most frequent mitigation occurred in MinnesotaNew Narrow Constrained Area (“NCA”) defined in January 2007.
Higher fuel prices, played a primary role in the 13 percent increase in average energyprices in 2007 and other rising costs, including:
A 26 percent increase in uplift costs associated with revenue sufficiency guarantee payments (“RSG”) that was due to higher fuel prices and increased
commitment of peaking resources to manage congestion.
A 28 percent increase in congestion costs that was due to the increased redispatch costs caused by higher fuel prices and other factors discussed in the report.
Wisconsin Projects Under Study Only
top related