7/29/2019 Medford presentation on police and fire station funding options
1/29
FUNDING OPTIONS FOR FACILITIES(Police and Fire)
Medford City Council Study SessionSeptember 12, 2013
Add photo Add photo
-
7/29/2019 Medford presentation on police and fire station funding options
2/29
PROJECT HISTORY - Police FacilityEstablished NEED
Currently occupying 15,000 sq feet of space.
Built in 1967 (was supposed to be temporary location atthat time).
Space Needs Study by MacKenziepresented to City Council on March 14, 2013Study Session.
Current location does not meet seismicrequirement for Essential Facility and PublicSafety should not be housed in this City Hallbuilding.
2
-
7/29/2019 Medford presentation on police and fire station funding options
3/29
PROJECT HISTORY - Police FacilityEstablished NEED
Co-mingled public areas and multi-use facility
creates substantial risk to the safety of all currentCity Hall users, including the public.
Public and secure space is mixed, as is securespace with civilian employees, making it a hugesafety risk in current location. Secured space isinadequate.
Lack of operation space for report writing,interview rooms, locker rooms and storage, lack
of secured police parking.3
-
7/29/2019 Medford presentation on police and fire station funding options
4/29
POLICE NEED
Determined to be a facility of 42,423 ft with aparking structure of 223 stalls.
City-owned property on 10th St at Ivy St.
Cost of recommended facility is $21.6 Million.(including parking garageand cost of debt)
4
-
7/29/2019 Medford presentation on police and fire station funding options
5/29
POLICE NEED
Considerations already made: Construction on City-owned property - no cost for land
Surface parking lots and pedestrian improvements to be
paid out of budgeted funds (-$700,000)
Proposed facility allows for20-25 year growth; after thatsubstations/precincts
5
-
7/29/2019 Medford presentation on police and fire station funding options
6/29
August 2012 Facilities Master Plan provided by
MacKenzie and previously presented to CityCouncil.
Initial estimate for rehabilitation of Fire
Stations 2 through 6 as well as training andlogistics = $16.6 M.
PROJECT HISTORY - Fire FacilitiesEstablished NEED
6
-
7/29/2019 Medford presentation on police and fire station funding options
7/29
Project Costs:
Fire Station #2 $3.9 Million Fire Station #3 $4.4 Million
Fire Station #4 $2.7 Million
Fire Station #5 $2.0 Million
Fire Station #6 $0.5 Million
Training $2.4 Million
Logistics $0.7 Million
Cost of Issuing Debt $0.2 Million
Total $16.8 Million
PROJECT HISTORY - Fire FacilitiesEstablished NEED
7
-
7/29/2019 Medford presentation on police and fire station funding options
8/29
Fire Station #2 $3.1 Million
Fire Station #3 $4.4 Million Fire Station #4 $2.7 Million
Fire Station #5 $2.0 Million
Fire Station #6 $0.5 Million
Training $2.4 Million
Logistics $0.7 Million
Cost of Issuing Debt $0.2 Million
Total $10.4 Million
$6.4 Million Reduction
PROJECT HISTORY - Fire FacilitiesProjects Removed/Reduced:
8
-
7/29/2019 Medford presentation on police and fire station funding options
9/29
FUNDING OPTIONS
Police $ 21.6 Million
Fire $ 10.4 Million
$ 32.0 Million Total bond needed
What are the funding options availableand what are the estimated costs?
What are the revenue options to meet thatcost?
9
-
7/29/2019 Medford presentation on police and fire station funding options
10/29
SOME CONSIDERATIONS: First discuss the BOLI issue and the potential for
cost savings.
Comparison was BOLI wage rate vs AGC Union rate.
Non-Union rates are not included.10
-
7/29/2019 Medford presentation on police and fire station funding options
11/29
Not as much potential for savings as anticipated
in a non-BOLI job. The estimate is in the 3% to5% range. This type of construction is generally atunion scale, so the savings are minimal.
These types of facilities would be BOLI wage jobsunder the definition of ORS 279C.840 in standardgovernment financing (Bond Options #1 and #2).
In order to avoid BOLI, the City would have to useother funding options (NNN/Lease, Debt/Equity)that are not recommended.
CONSIDERATIONS(cont):
11
-
7/29/2019 Medford presentation on police and fire station funding options
12/29
FUNDING OPTIONS We reviewed/examined other funding
options: Bond Option #1 (General Obligation Bond)
Bond Option #2 (Full Faith and Credit Obligation Bond)
Lease Triple Net Option
Debt/Equity Option
63/20 Option
12
-
7/29/2019 Medford presentation on police and fire station funding options
13/29
13
-
7/29/2019 Medford presentation on police and fire station funding options
14/29
14
FUNDING for PUBLIC SAFETY FACILITIES
Canby Urban Renewal 08/2011 08/2012
Gresham Urban Renewal 03/2013 12/2013 Keizer Urban Renewal 03/2008 early 2009
Klamath Falls Bond Measure 05/2009 07/2010
McMinnville Bond Measure 03/2007 06/2008
Monmouth Bond Measure Passed in 05/2013
Roseburg Urban Renewal 04/2008 11/2009
Sandy Urban Renewal 08/2009 09/2011
Springfield Bond Measure 02/2008 02/2009 Troutdale Bond Measure 10/2011 09/2012
West Linn Bond Measure started 09/2013
Woodburn Bond Measure 09/2005 10/2006
FUNDING CONSTRUCTION PERIOD
-
7/29/2019 Medford presentation on police and fire station funding options
15/29
FUNDING OPTIONSWe and our consultants agree that a Full Faith
and Credit Bond (Bond Option #2) is therecommended funding option:
City of Medford has bonding capacity Does not require a referendum approval
We have an identified revenue source to meetthe interest/principal payment
More timely to implement
15
-
7/29/2019 Medford presentation on police and fire station funding options
16/29
BOND OPTION #2 (example)
$32.0 million 30 years at 4.75%
Full Faith and Credit Obligation Bond Option #2
16
-
7/29/2019 Medford presentation on police and fire station funding options
17/29
17
Bond Option #2
Project Costs for Both Police and Fire:Police Facility
Building,Garage & Parking lot 21,900,000
Land - City owned -
Parking lot - "pay as you go" (700,000)
Cost of Issuing Debt 400,000
Amount needed 21,600,000
Fire Facilities
New Fire Station & All Renovations 16,600,000Land for the new fire station - City owned -
Some Renovations - "pay as you go" or eliminated (6,400,000)
Cost of Issuing Debt 200,000
Amount needed 10,400,000
Total Amount to be Borrowed 32,000,000$
Annual Payment 2,000,000$30 year debt - interest rate of 4.75%
-
7/29/2019 Medford presentation on police and fire station funding options
18/29
FUNDING ALTERNATIVES WITH
BOND OPTION #2
$32.0 Million Bond =
Total annual payment of $2 Million(based on 4.75% on 30 year bond)
Alternative 1 = Some combination of: % of Public Safety Facility Surcharge $
% of City of Medford Tax increase $ % pay as you go budgeted funds for a portion
18
This would require a referendum by voters if tax rate increased
-
7/29/2019 Medford presentation on police and fire station funding options
19/29
(cont)
Alternative 2 = $0.35 per $1000 increase in
City of Medford tax rate.
$53 per year for an assessed $150,000* homegenerates $2 Million per year.(deductible/tax advantage)
* Average assessed value for Medford residence
* This would require referendum approval if tax rate increased
19
FUNDING ALTERNATIVES WITH
BOND OPTION #2
-
7/29/2019 Medford presentation on police and fire station funding options
20/29
(cont)
Alternative 3 = Public Safety Facility Surcharge(recommended option)
$2.00 per month per residential/business unit willgenerate an estimated $0.9M per year.
When the Street Fee surcharge is removed, increase
the Public Safety Facility Surcharge to $4.82. Thiswill generate an estimated $2.5M per year.
20
FUNDING ALTERNATIVES WITH
BOND OPTION #2
-
7/29/2019 Medford presentation on police and fire station funding options
21/29
In approximately 60 months, the Transportation
Projects surcharge will end.
For SFR (single family residence), that will result in$2.82 decrease in the Street Fee.
Public Safety Facility Fee Surcharge could beginat $2.00 and increase to $4.82 at the time the
Street Fee portion expires in approximately 2018.
SURCHARGE STRUCTURE OPTIONS:
21
-
7/29/2019 Medford presentation on police and fire station funding options
22/29
Sewer
Street
Storm
Water
Public
Safety
Parks
Pub Safety
Surcharge
22
$15.85 $15.85 $15.85 $15.85 $15.85 $15.85
$8.45 $8.45 $8.45 $8.45 $8.45$5.63
$7.71 $7.71 $7.71 $7.71 $7.71$7.71
$12.15 $12.15 $12.15 $12.15 $12.15$12.15
$2.60 $2.60 $2.60 $2.60 $2.60$2.60
$2.95 $2.95 $2.95 $2.95 $2.95$2.95
$2.00 $2.00 $2.00 $2.00$4.82
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
Current
Fees
Initial
Fees
2015 2016 2017 2018
Total: $49.71 $51.71 $51.71 $51.71 $51.71 $51.71
Current & Proposed Monthly Utility Charges - SFR
-
7/29/2019 Medford presentation on police and fire station funding options
23/29
UTILITY FEE RATES COMPARISON
23
Medford has a very low utility fee rate which includes the street fees.
With the $2.00 per month increase, we are still at the same ranking
for utility fees.
$51.71
-
7/29/2019 Medford presentation on police and fire station funding options
24/29
Sewer
Street
Storm
Water
Public
Safety
Pub Safety
Surcharge
24
15.85 15.85 15.85 15.85 15.85 15.85 15.85
8.45 8.45 8.45 8.45 8.45 8.455.63
7.71 7.71 7.71 7.71 7.71 7.717.71
12.15 12.15 12.15 12.15 12.15 12.1512.15
2.60 2.60 2.60 2.60 2.60 2.602.60
2.95 3.63 3.63 3.63 3.63 3.633.63
2.00 2.00 2.00 2.00 2.004.82
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
Total: $49.71 $52.39 $52.39 $52.39 $52.39 $52.39 $52.39
Current & Possible Monthly Utility Charges - SFR
Parks
Current Fees 2013 2014 2015 2016 2017 2018
This includes a proposed Public Safety Facilities Surcharge ($2.00) and possible Park fee increase ($0.68)
-
7/29/2019 Medford presentation on police and fire station funding options
25/29
Storm $1.23 in 2014 $0.63 in 2015
Street $0.80 in 2014 $0.46 in 2015
Sewer $1.60 in 2014 $0.81 in 2015
25
POSSIBLE STREET, STORMAND SEWER INCREASES :
-
7/29/2019 Medford presentation on police and fire station funding options
26/29
15.85 15.85 17.4518.26 18.26 18.26 18.26
8.45 8.459.25 9.71 9.71 9.71 6.89
7.71 7.71
8.949.57 9.57 9.57
9.57
12.15 12.15
12.1512.15 12.15 12.15
12.15
2.60 2.60
2.602.60 2.60 2.60
2.602.95 3.63
3.633.63 3.63 3.63
3.632.002.00
2.00 2.00 2.004.82
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
Sewer
Street
Water
Parks
Pub Safety
Surcharge
26
Total: $49.71 $52.39 $56.02 $57.92 $57.92 $57.92 $57.92
Current & Additional Possible Monthly Utility Charges - SFR
Current Fees 2013 2014 2015 2016 2017 2018
Possible increases:(included in graph)
Parks $0.68 in 2013Storm $1.23 in 2014 and $0.63 in 2015Street $0.80 in 2014 and $0.46 in 2015
Sewer $1.60 in 2014 and $0.81 in 2015
Public
Safety
Storm
-
7/29/2019 Medford presentation on police and fire station funding options
27/29
27
PUBLIC SAFETY FACILITIESCOMPARABLE CITIES BOND DEBT
Snapshot June 30, 2012
Bend Gresham Springfield Medford
General Obligation Bonds $0 $0 $25.8M $ 3.1M
Full Faith & Credit Bonds $64.4M $74.1M $0 $49.7M
(minus URA) ($23.6M) ($20.9M)
Renewal Bonds $15.0M $8.3M $30.8M $25.9M
(minus URA) ($ 5.0M)
Total Bond Debt
minus URA$79.4M $58.8M $56.6M $52.8M
-
7/29/2019 Medford presentation on police and fire station funding options
28/29
Move forward with the proposed Public Safety
Facility Surcharge plan.
Come back to Council in the next 60 days with afinalized plan to implement the code change.
Council direction.
RECOMMENDATIONS: