Market Coordination Team Update

Retail Market SubcommitteeJuly 11, 2007

Susan Munson Retail Market Liaison/MODPO

• What did it contain?

POLR Rule (PUCT Project 31416) Mass Transition transactional solution Terms and Conditions (PUCT Project 29637) Miscellaneous Change Controls

18 change controls 35 transactions modified 77 CRs, 6 TDSPs, and ERCOT

Texas SET 3.0 in a Nutshell

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO

• Implementation Guides posted on Texas SET Guides page of ERCOT.com under Current Texas SET Implementation Guideshttp://www.ercot.com/mktrules/guides/txset/index.html

• SEF Files posted in File Cabinet of Retail Testing websitehttp://etod.ercot.com/

• CBCI Initial Load file to be sent by CRs

Texas SET 3.0 Odds & Ends

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO

Initial Production Load file

Between July 16, 2007 and July 31, 2007, all CRs should submit to ERCOT, via NAESB, an initial production load Customer Billing Contact Information File (CBCI file)

For more information, review the Retail Market Guide

o Section 7.11.6 Customer Billing Contact Information Fileo Appendix F6 for file layouts

ERCOT will provide a confidential report to the PUCT by August 15, 2007 which will include the Name and DUNS Number of CRs who submitted the initial load CBCI file to ERCOT and the same information for those CRs that did not submit reports. 

For questions – contact your ERCOT Retail Account Manager

Customer Billing Contact Information File

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO

• Meeting Dates and Locations 2007

July 13 – AEP, Corpus Christi August 28 (Lessons Learned) – ERCOT Met Center

(Note: all meetings are held in conjunction with TX SET meetings)

Future Meetings/Market Communications

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO

ERCOT Contacts

ERCOT Project Manager ERCOT SR. Business AnalystHope Parrish Jennifer Frederick

hparrish@ercot.com jfrederick@ercot.com

512-248-6522 (w) 512-248-6733 (w)

512-771-9582 (c) 512-413-0815 (c)

ERCOT Market LiaisonSusan Munson

smunson@ercot.com

512-248-3881 (w)

512-826-0564 (c)

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO

Questions?

Project: PR40038_01 Current Phase: Execution

2007 PPL Source: Market/PUCT Priority: 0-Carryover Rank: 1 Budget: $1-$3 MM Program Area: RO