loop 360 program · –loop 360 is ranked on texas’ 2018 most congested roadways list...

Post on 17-Sep-2020

0 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Updated September 2019Updated September 2019

Loop 360 Program

Updated September 2019

About Loop 360

Major north/south transportation corridor Runs 14 miles from US 183 to US 290/SH 71 Serves residents and commuters Known for natural beauty, Hill Country features,

Pennybacker Bridge

2

Updated September 2019

Problem

Severe traffic congestion– Mobility and safety concerns– Loop 360 is ranked on Texas’ 2018 Most Congested

Roadways list– Currently takes approximately 70% longer to travel during

peak periods than during free-flow conditions– Traffic will worsen as population grows – population is

expected to double by 2040

3

Updated September 2019

Problem

4

Updated September 2019

Challenges

Improvements along Loop 360 face several challenges, including a sensitive environment, cliffs which sometimes experience rockslides, and natural hills and valleys.

5

Updated September 2019

Challenges – Environment

6

Updated September 2019

Challenges – Rockslides

7

Updated September 2019

Challenges – Hills and Dales

8

Updated September 2019

About the Loop 360 Program

Program purpose: Upgrade multiple intersections to improve mobility and safety along the corridor– Eliminate at-grade crossings – Install over/underpasses at major intersections– Reconfigure RM 2222 and RM 2244 to diverging

diamond intersections– Separate local and through traffic at intersections– Increase safe access to/from adjoining neighborhoods– Add accommodations for bicyclists and pedestrians

9

Updated September 2019

Loop 360 Program

Projects:– Lakewood Drive/

Spicewood Springs Road– Courtyard Drive/

RM 2222– Westlake Drive/

Cedar Street– RM 2244– Westbank Drive/

Lost Creek Boulevard– Walsh Tarlton Lane

10

Updated September 2019

Project Process

11

Multi-step process with ongoing stakeholder engagement

Updated September 2019

Lakewood Drive/Spicewood Springs Road

12

Project Overview:

– Remove the traffic signals from the Loop 360 mainlanes at Spicewood Springs Road (E)/Bluffstone Drive, Spicewood Springs Road (W), and Lakewood Drive

– Construct overpasses at Spicewood Springs Road (E)/Bluffstone Drive and Lakewood Drive with non-signalized U-turns in both directions

– Add a shared-use path and sidewalks within the project limits

Due to their proximity and similar environmental considerations, TxDOT has combined the environmental process for the Lakewood Drive and the Spicewood Springs Road projects

Environmental stages complete: early 2021

Updated September 2019

Lakewood Drive/Spicewood Springs Road

13

Updated September 2019

Courtyard Drive/RM 2222

14

Project Overview:– Remove traffic signal from the Loop 360 mainlanes at

Courtyard Drive and construct an underpass – Reconfigure RM 2222 at Loop 360 to a diverging

diamond intersection– Add a shared-use path and sidewalks within the

project limits Environmental, preliminary and final engineering

complete: mid 2023

Updated September 2019

Courtyard Drive/RM 2222 – Looking North toward RM 2222

15

Updated September 2019

Diverging Diamond Intersections – RM 2222 and RM 2244

16

Reduce crash points Move more cars Facilitate left turns without left-turn signal Enhance visibility

Updated September 2019

Westlake Drive/Cedar Street

17

Project Overview:– Remove traffic signal from the Loop 360 mainlanes at

Westlake Drive and Cedar Street– Construct an underpass at both intersections, including non-

signalized U-turns in both directions at Westlake Drive– Add a shared-use path and sidewalks within the

project limits Environmental, preliminary and final engineering

complete: early 2022

Updated September 2019

Westlake Drive/Cedar Street

18

Updated September 2019

Forthcoming: Westbank Drive/Lost Creek Boulevard, RM 2244

19

RM 2244:

– This project is the last scheduled project in the program and has not yet moved forward into the environmental stage. It is likely that RM 2244 at Loop 360 will be reconfigured to a diverging diamond intersection

– Environmental, preliminary and final engineering complete: mid 2026

Westbank Drive/Lost Creek Boulevard:

– This project is still in developmental stages. It is likely that the traffic signals will be removed at both intersections and either overpasses or underpasses will be installed

– Environmental, preliminary and final engineering complete: early 2026

Updated September 2019

Westbank Drive/Lost Creek Boulevard, RM 2244

20

Updated September 2019

Walsh Tarlton Lane

21

Project Overview:– Remove traffic signals from the Loop 360 mainlanes at

Walsh Tarlton Lane– Construct an overpass at Walsh Tarlton Lane with non-

signalized U-turns in both directions– Add a shared-use path and sidewalks within the

project limits Environmental, preliminary and final engineering

complete: early 2025

Updated September 2019

Walsh Tarlton Lane

22

Updated September 2019

Program Schedule

23

Updated September 2019

But much of Loop 360 will continue to look like this

24

Updated September 2019

Context Sensitive Solutions (CSS)

25

A collaborative approach to developing roadways that fit within their surroundings

Considers not only physical aspects or standard specifications of a roadway, but also community resources

Community Feedback

– November 2018: TxDOT conducted a survey to receive feedback from the community

– March 2019: TxDOT shared the results of that survey and collected further public input

– June 2019 and August 2019: TxDOT collected and incorporated additional feedback on the refined options

More details about the CSS process can be found at Loop360Project.com

Updated September 2019

Context Sensitive Solutions (CSS)

26

These are the types of features developed using a CSS approach

Updated September 2019

How Can I Stay Informed?

27

For the most up-to-date information,visit the program website

www.Loop360Project.com

Questions or Comments?Email the project team

info@Loop360Project.com

top related