lcls-ii project overview

Post on 12-Jan-2016

29 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

DESCRIPTION

LCLS-II Project Overview. David Schultz LCLS-II Deputy Project Director March 19, 2012. Outline. Project priorities and status Key features Project o verview & layout Project schedule and path forward. LCLS-II Project Priorities. Build a highly productive scientific user facility - PowerPoint PPT Presentation

TRANSCRIPT

LCLS-II Project Overview

David SchultzLCLS-II Deputy Project Director

March 19, 2012

Outline

Slide 2

• Project priorities and status• Key features• Project overview & layout• Project schedule and path forward

LCLS-II New Instruments Workshops, March 19-22, 2012

LCLS-II Project Priorities

• Build a highly productive scientific user facility Maximize technical capabilities for the longer-

range future• Simultaneous SXR and HXR operation• Experiment hall capacity• Undulator hall length

• Control the Project Cost/Schedule DOE Guidance is $405M Total Project Cost Formal Project completion (CD-4) in 2019

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 3

• Conceptual Design (CD-1) approval 10/14/11• Long-lead procurements approval 3/14/12

• Injector system and support facility• Fully funded for FY12• DOE Preliminary Design (CD-2) Review as early as

August, 2012• Establish Project baseline schedule and budget

LCLS-II Project Status

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 4

• Second 120 Hz injector and 1km LINAC section LCLS-1 and LCLS-II operate independently

• Two New Undulator sources with variable gap In a new undulator tunnel Electrons to two undulators in parallel, 60 Hz each Soft (250 - 2,000 eV) Hard (2,000 - 13,000 eV)

New underground experiment hall, two floors

Key Features of LCLS-II

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 5

Slide 6

DOE CD-3a Review of the LCLS-II Project, Dec 6-7, 2011

Linac Coherent Light Source IIInjector @1-km point

Sectors 10-20 ofLinac (1 km)

CD-0 10 April 2010, CD-1 14 October 2011CD-0 10 April 2010, CD-1 14 October 2011

X-ray Transport Optics/Diagnostics

New Underground Experiment Hall

Bypass LCLS Linacin PEP Xport Line

New Beam Transport Hall

SXR, HXR Undulators

Electron Systems Schematic Layout

LCLS-II New Instruments Workshops, March 19-22, 2012

0

• Electron Systems largely copied from LCLS-1• Gun, BC’s, diagnostics, e- dumps

Slide 7

LCLS-II New Construction Layout

LCLS-II New Instruments Workshops, March 19-22, 2012

LCLS-1

Experimental Hall 2Undulator Hall 2Beam Transport Hall 2

Slide 8

LCLS-II Undulator Hall

Space for SXR Seeding and Tapering

• Undulator tunnel is 286 meters in length Space for baseline 114 m HXR and 66 m SXR undulators Room allocated for seeding and tapering extensions

LCLS-II New Instruments Workshops, March 19-22, 2012

Space for HXR Seeding and Tapering

Baseline SXR

Baseline HXR

e- Beam Dump

Front End

Slide 9

Undulator Magnets

• LCLS-II Undulators are based on undulators designed at LBNL for the ALS.

Servo Motor

Strongbacks

CompensatingSprings

Linear Encoder

Linear Slide

MagneticStructure

LCLS-II New Instruments Workshops, March 19-22, 2012

Undulator Hall Cross Section

• Undulator tunnel is similar in cross section to the LCLS tunnel.

Slide 10

Experimental Hall 2 Layout

• Space for 4 experimental stations in an 80m long cavern.• Full size second floor for HVAC, racks, control rooms

LCLS-II New Instruments Workshops, March 19-22, 2012

Front End Systems Area for Soft X-rays Area for Hard X-rays

80m

14m

Slide 11

LCLS-II Project Schedule

Slide 12LCLS-II New Instruments Workshops, March 19-22, 2012

First Light

Install Instruments

EH2 complete

2012 plans

• Start Injector facilities construction in July• Start Injector technical system fabrication• Complete Construction designs by the end of the

year.• Develop the Project baseline schedule and

budget for presentation to DOE in August.

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 13

Summary

• LCLS-II will add capacity and capability to the LCLS scientific program, and will provide space for expansion.

• To minimize cost and risk, electron systems rely heavily on LCLS-1 designs.

• LCLS-II will dovetail with the LUSI-II project. First light in 2018.

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 14

End of Presentation

top related