KYTC Bridge Preservation and Maintenance Program. David Steele, P.E. Branch Manager for Bridge Preservation. Bridge Inventory. 9,025 = Number of State Maintained Bridges 632 = Structurally Deficient (7%) - PowerPoint PPT Presentation

TRANSCRIPT

KYTC Bridge Preservation and Maintenance Program

David Steele, P.E.Branch Manager for Bridge

Preservation

Bridge Inventory

9,025 = Number of State Maintained Bridges

632 = Structurally Deficient (7%)

4,709 = Number of Local Maintained Bridges

District Bridge Crews

District Bridge Crews

District Bridge Crews

Bridge Preservation Conference

Central Office Staff

• Branch Manager (P.E.)• Chief Bridge Inspector• Contract Section–Repairs (3 people) Paint (1 person)• Scour and Preventive Maintenance (1 P.E.)• Load Rating Engineers (2 P.E.’s)• Ohio and Big Sandy River Bridges Manager (1 P.E)• Inventory – Pontis System Administrators (2)• Snooper Manager• Administrative Specialist