US 62 Project Update
The project will realign and reconfigure the intersections of US 62,
Middlebranch Ave., Harrisburg Rd. and 30th St. and includes the construction of
a roundabout at Harrisburg Rd. and 30th St. to reduce traffic delay, improve
operational efficiency and improve safety in the project vicinity.
� The project is currently in the final design phase and right-of-way (affected
private properties) evaluation and acquisition will be completed in 2017.
� Utility relocation activities will begin in late Summer 2017.
� Roadway Construction is expected to begin in Spring 2018 and be completed
in 2020.
For additional information, contact Dayna Mallas, P.E. (ODOT Project manager)
by email to Dayna.Mallas@dot.ohio.gov or by telephone at 330-786-4931.
www.Transportation.Ohio.Gov/Dist4