August 6, 2019

Program Update

Terminal 5 Modernization

1

Item No.: 6ADate of Meeting August 6, 2019

2

List of recent events

Terminal 5 – Progress

• June 22nd Open House• Shared important project information• Answered questions from community

• July 10th Construction Kick-off• Well-attended• Speakers shared importance of project• Broad media coverage

• Orion Marine Contractors • Fully mobilized• Clearing & grubbing and asphalt demo near primary substation• Above water dock demolition

3

Event Photo

Terminal 5 – Construction Kick-Off

4

5

2019 2020 2021 2022 2023

TRANSITION CONSTRUCTION PHASE 2

PRE-CONSTRUCTION

Begin North Berth Operations

PROJECT COMPLETION

Terminal 5 – Schedule and Phasing

In-water work windows

Schedule and phasing over next 4 years6

CONSTRUCTION PHASE 1

DESIGN/PERMIT PHASED CONSTRUCTION

Uplands Improvement Project

Berth Modernization Project