ISSUES PERTAINING TO GOVERNMENT OF CHHATTISGARH
S.No Name of the company and location
Issues in Brief Action to be Taken
1 NMDC Ltd.
NMDC Iron & Steel
Plant at Nagarnar,
Chhattisgarh
1. Request for acquisition of about 250 acres of additional land for NMDC’s proposed pellet plant and other associadated activities at Nagarnar. Request has been sent to District Collector, Bastar District in March, 2011.
Chhattisgarh State Government to expedite the matter.
2. For providing Power Supply to the Integrated Steel Plant at Nagarnar, Chhattisgarh state Power Transmission Corporation Limited (CSPTCL) has to construct:‐
a) 400 KV line from Raipur to Jagdalpur
b) 400/220 KV substation at Jagadalpur
c) 220KV line from Jagdalpur to Nagarnar.
For these FC has to be obtained by the State Govt at the earliest to ensure their completion by March,2015 for starting commissioning activities of the plant.
State Govt. to expedite the processing
3. Early clearance of Forest diversion proposals for the proposed water pipeline for the Nagarnar plant.
State Govt. to expedite the matter
Mining Lease (ML) granting for Sadartera Dolomite Block
4. ML application for Sadartera Dolomite Block. All required documents have been submitted to State’s Forest Deptt. on 10.1.2012
Request for early grant of ML for the required area.
2
2 RINL Pending PL/ML Application Two PL/ML applications are pending with the State Government
3 Monnet Ispat & Energy Ltd.
1.5 MTPA
Integrated Steel
Plant at Raigarh,
Chhattisgarh
Land acquisition for Rajgamar Dipside (South of Phulkadih Nala) Coal Block. Total mining Lease Hold Area is 625 Ha, out of which 450 Ha of area already acquired by SECL under CBA Act. Request for transfer of land by SECL pending since 21/1/2011. In this process, joint survey of the mine by the surveyors of Monnet and SECL has been completed on 15/2/2012. Detailed Land schedule is prepared and further action for surrender of Mineral Rights for overlapped land is pending with SECL.
SECL should be advised to transfer the land immediately as the mining lease can be signed only after land acquisition.
4 Jindal Steel & Power Ltd.
Expansion Project
at Raigarh Plant
Total land requirement is 1244.932 Ha. Out of which 799.101 ha land is in possession
Iorn Ore Linkage
Support is required from the State Govt. in acquiring the remaining 465.831 Ha.
Recommendations of State Govt either for mineral concession (ML/PL) for iron ore or JVwith State Govt. agency for getting linkage.
Water Allocation
Issue for allocation of balance 88.0MCM of water is pending with Water Resources Department, Govt. of Chhattisgarh since long.
Draft EIA Reports submitted to CECB to conduct public hearing in March 2012 and April, 2012 for 1 MTPA and 7 MTPA expansion projects respectively. The dates for holding public hearing are yet to be fixed.
Public hearing to be held at the earliest
5. Jayaswal Neco Industries Ltd.
Gare Palma IV/8
Application for grant of Mining Lease
Pending with State Government of Chhattisgarh since
3
Coal Block, Tamnar, Raigarh, Chhattisgarh
14.11.2011
Laindongri Iron Ore Mine, Village Barbaspur, District Kanker
Grant order for execution of Mining Lease
Pending with the State Government of Chhattisgarh for more than 18 months
Metabodli and Chhotedongar Iron Ore Mine, District Kanker and Narayanpur, Chhattisgarh
Execution of Mining Lease for both the mines
Work cannot be started due to severe law and order situation.
Green field 1 MTPA project at village Dagori, Distt. Bilaspur, Chhattisgarh
Land acquisition issues Support is required from the State Govt
6. Godawari Power & Ispat Limited, Rajnandgaon, Chhattisgarh
Land acquisition issues In principle approval received from State Government of Chhattisgarh Allotment of Government Revenue land measuring area of 9.635 hect. Allotment of private land area of 196.006 hect.
Chhattisgarh State Government to take decision
Water Allocation
Application for allotment of 17.67 mcm water
Pending with Water Resource Department, Government of Chhattisgarh.
7. Vandana Ispat Limited Village Anjora/Kopedih, Rajanadgoan, Chhattisgarh
Diversion of land/change in Land use
Pending with District Collectorate, Rajnandgoan, Govt. of Chhattisgarh
8. Shri Bajrang Power & Ispat Ltd
Dharsiwa‐Tilda Road,Raipur Chhattisgarh
Application for grant of PL for Iron Ore
Pending with State Government
4
9. Essar Steel India Ltd.
Vizag
Laying of Iron Ore slurry pipeline between Kirandul and Vizag
Matter is under considered with Chhattisgarh State Government.
10. TATA STEEL LIMITED
Chhattisgarh Steel Plant
5.5 MTPA Integrated Steel plant at Baster.
Land has been acquired by the Government of Chhattisgarh and transferred to Chhattisgarh State Industrial Development Corporation (CSIDC) for allotment to TSL on 99 years lease. TSL has requested for demarcation of the said land before taking possession of the same
Physical possession of the acquired land for the Plant to TSL pending more than two years
State Government should expedite demarcation of land after resolution of issues.
To be expedited
5
ISSUES PERTAINING TO GOVERNMENT OF JHARKHAND
S.No Name of the company and location
Issues in Brief Action to be Taken
1 SAIL
Issues in SARANDA FOREST DIVISION for which Stage – II Forestry Clearance of SAIL Mines (KIRIBURU, MEGHAHATUBURU, GUA & CHIRIA) are pending: 1. Early approval of
Integrated Wildlife Management Plan of Saranda, Singhbhum (West)
2. Submission of phased plan for future use of remaining unbroken area within all existing leases in Saranda Forest Division by Government of Jharkhand to MoEF
3. Submission of the Catchment Area Treatment (CAT) Plan of Koyna‐Karo catchment area in Saranda Forest Division by Government of Jharkhand. 4. State Government to identify inviolate area in SARANDA free from mining and depict them on map with digitized boundaries. Map should also depict mining areas under consideration.
Government of Jharkhand to expedite compliance of these Stages‐I forest clearance conditions before grant of Stage‐II forest clearances for Kiriburu, Meghahatuburu, Gua and Chiria leases of SAIL by MoEF. Non compliance of Stage‐I forest clearance conditions may close mining operations at Gua mines beyond 13.8.2014 (subject to grant of +1 WP beyond 13.8.13 by MoEF) till grant of Stage‐II forest clearance.
2. NMDC
Sasangda Iron Ore
NMDC applied for PL for Iron ore mine over an area of 1.1546 sq. km. on 21.5.07. As per the
State Government to grant the PL so that the exploration work in the area could be started.
6
Block agreement with the State Government the deposit will be developed by the JV Co. of NMDC and JSMDC (60: 40) ratio. Ministry of Mines already granted its prior approval for grant of PL in favour of JV.
NMDC applied for PL and ML for Ghatkuri Iron Ore Deposit on 18.4.2007.
Grant of the PL and ML in favour of NMDC.
NMDC has applied for 7 MLs/PLs for iron ore mines, 2 MLs/PLs for gold mines, and 5 MLs/PLs for bauxite mines in the Jharkhand State.
State Government to take further necessary action.
3. RINL Grant of 07 Nos of PLs for Iron Ore mines
Decision on PL applications are to be expedited by the State Government.
4. Tata Steel Limited.
Jamshedpur Steel Plant
Eastern Road Corridor at Jamshedpur to provide safe and smooth uninterrupted connectivity with the National Highway. Government of Jharkhand has given ‘in Principle’ approval to execute the project as a PPP with them
State Government to expedite
Renewal of ML and FC of Noamundi Iron Ore Mine
ML of Noamundi Iron Ore Mine has expired and is presently operating under “Deemed provision.
Renewal of the ML and FC for Noamundi Iron Mine by the State Government
Application for grant of Forest Clearance for Kotre Basantpur & Pachmo Coal Blocks
Pending with State Government of Jharkhand
Expansion from 5 to 10 MTPA for Brown Field Integrated Steel Plant
Proposal pending with Secretary Industries (Govt of Jharkhand)
5. Jindal Steel & Power Ltd.
a) Patratu
Transfer of Govt. Land by way of Lease Settlement is under process for 188.03 Acres.
State Govt. to provide assistance in land acquisition
7
Project, Jharkhand Acquisition of private land through Land Acquisition under process for 753.93 Acres.
Iron Ore Linkage Recommendation from Jharkhand Govt. is pending for mineral concessions for Iron and Manganses Ores.
Allocation of Iron Ore mine To develop Iron Ore Mines in Joint Venture with State Govt. Agency so as to meet Iron Ore requirement of Steel Plant.
Coking Coal and Non Coking Coal:
Part of Amarkonda‐Murgadangal non coking coal block has been allocated on 17.01.2008 by Ministry of Coal, Govt. of India to cater the requirement of 1000 MW Captive power plant.
This is a regionally explored coal block and needs further exploration work to be done by us to prepare Geological Report and Mining Plan. Due to local law and order problems, JSPL is unable to start exploration work. The company has already applied for long term coal linkage to Ministry of Coal on 6.6.2011 for the 1320 MW CPP for the intervening period till the coal mine is developed.
6. JSW Steel Ltd Sonahatu Block Ranchi, Jharkhand
Govt. of Jharkhand have issued an order deallocating 92.50 MCM of water for its 10 MTPA Greenfield plant.
State Government to withdraw deallocation order.
Speedy transfer of Govt land (GM‐Jungle Jhari) in Gumla Distt in favour of JSW JSL for compensatory afforestation (CA) purpose for Stage‐I FC compliance for Ankua Iron Ore and Rohne Coal Mining projects.
State Govt. of Jharkhand to provide assistance for transfer of land for CA purpose.
7. Jayaswal Neco Industries Ltd. Moitra Coking Coal Block, Hazaribag, Jharkhand
Application for stage‐I Forest Clearance
Pending with the State Government of Jharkhand
8
Request for land acquisition Pending before the State Government of Jharkhand since 10.7.2005
8. Monnet Ispat and Energy Limited
Bokaro, Jharkhand
Land acquisition issue Due to unavailability of RoR, land acquisition is pending with State Government.
Allocation of land is pending with State Government.
Allocation of water Pending with State Govt.
Request for alternate iron ore mine in lieu of allocation of Ghatkuri iron ore mines which is now reserved for PSUs
State Government should provide required help.
9 BHUSHAN POWER & STEEL LTD
Jharkhand Steel & Power Project
Land acquisition Issues
Land acquisition related issues are the most diffcult being faced by the Company towards implementation of its steel project. As per TEFR, total land requirement was of 3258 acres.
Based on our original application dated 1.7.2008 to Secretary, Revenue and Land Reforms, Govt. of Jharkhand, for acquisition of land, the same was forwarded by Dy. Commissioner, East Singhbhum (Jamshedpur) to Secretary (Revenue & Land Reforms) in May, 2010. However, due to constraints being faced for procurement of land and our keenness to implement the project, the Company decided to initially proceed with implementation of 1.0/1.2 MTPA Steel Plant and 100 MW Power Plant in phase‐I over 578 acres of land. The work for Phase –II will start concurrently as soon as the land is procured.
Till date over 380 acrs of private land has already been purchased.
State Government to expedite.
9
Application for acquisition of further 196.49 acres of Private land for Phase‐I was made on 14.6.2012 with Principal Secretary, Revenue & Land Reforms, Jharkhand. Agreement for same has also been signed on 31.12.2012. However the processing of further notification under 4(1) etc is still under process.
Application for Government land 59.98 acres was made to the Principal Secretary, Revenue and Land Reforms, Jharkhand on 4.7.2011. Currently the same is lying in the office of Dy. Commissioner, East Singhbhum for further processing.
As required for acquisition of private land and Govt. land, the statutory Gram Sabhas have already been successfully conducted.
Application for Scheduled Tribe land 62.07 acres stands filed in the court of Dy.
Commissioner for awarding the land in their favour.
10. Arcelor Mittal India Limited
Jharkhand
Forest Clearance application in respect of 662.95 Ha Karampada PL area pending since 25.2.2011 and permission for test drilling.
State Govt. to grant permission for exploratory drilling and FC for land.
Applied for acquisition of 2210 acres of land in Nov’ 11 under the Jharkhand Voluntary Land Acquisition Rules 2010
Government of Jharkhand may be requested to acquire land expeditiously.
10
ISSUES PERTAINING TO GOVERNMENT OF ODISHA
S.No Name of the company and location
Issues in Brief Action to be Taken
1
SAIL
Bolani & Barsua Iron ore Mines
Anomaly in the levy of royalty on iron ore in the State of Odisha
1. After the issue of circular dated 07.09.10 of Commissioner‐cum‐Secretary, Govt. Of Odisha, Dept. of Steel and Mines, the royalty on both iron ore lump as well as on fines from Bolani & Barsua mines of SAIL are being charged at the rate of lump on the assumption that these mines are producing calibrated lump Ore (CLO‐ input for DRI route of iron making).
2. Further, from Sep’2012 onwards, under Orissa Minerals Rules, 2007, for being exempted from stacking and sampling of iron ore, royalty on both iron ore lump and fines from Bolani & Barsua mines of SAIL is being charged at the royalty applicable to highest grade of iron ore lump. On these accounts an additional burden of about Rs.248 crore has impacted the bottom lines of SAIL till May’13.
1. To review the system of charging of royalty for fines at the rate of lump at Bolani and Barsua mines during August’2009 till August’2012 on the pretext of CLO being produced.
2. To review the system of charging of royalty for fines at the highest rate of royalty applicable for lumps under the provisions of exemption from stacking and sampling for Bolani and Barsua mines since September’2012 onwards.
SAIL, Thakurani Block‐A, 277.683 Ha
Grant of Prospecting License(PL) for Thakurani Block A(277.683 ha)
Govt of India in consultation with
Pending with State Governmwent
11
Govt. of Orissa had reserved 277.683 Ha in Block –A for 50 years for SAIL for undertaking exploration vide Gazette notification dated 4.2.04. Against this Notification, SAIL had applied for Grant of PL for Thakurani Block – A (277.683 ha) in Apr’04. Since then the application is pending with State Government. Utkal B‐1 coal block allocated to the Company can meet coal requirement of the project for only 2 MTPA capacity DRI plant only. Execution of Mining Lease Deed is pending for close to 1 year 8 months
Govt. of Odisha to expedite execution of ML and allotment of additional coal blocks
Allocation of captive iron ore mine for the integrated steel plant or JV with OMC
Pending with State Government.
Lying of balance stretch of 3.4 Km water pipeline for Angul plant delayed due to local resistance
State Government to assist in laying of pipeline
Revalidation of water usage approval which expired in August,2011
State Govt. to revalidate
Requirement of additional land (520 Ac) for water reservoir
Proposal to be cleared by State.
2 Jindal Steel & Power Ltd.
Angul Project, Odisha
Construction of new road from Banarpal to Angul town by‐pass road from north of Angul town for congestion free movement of coal from mines
Pending with State Government.
12
3. Bhushan Steel Ltd
Grant of Mining Lease for Iron Ore Mines
Commissioned 3 MTPA Integrated Steel Plant. The Plant capacity will increase to 5.6 MTPA by end of this month, i.e. March, 2013
A steel plant of such a large capacity cannot be operated without allocation of Captive Iron Ore Mines.
Grant of Iron Ore Mining lease to cater to requirement of Iron Ore for 5.6 MTPA integrated Steel plant.
Till such times mines are allocated and become operational, OMC (an Odisha Government State Undertaking) should be directed to accord a dedicated linkage of required quantity of iron ore to BSL at reasonable price from their mines.
Truck Unions and Transporters are literally blackmailing the consumers in the state of Odisha. Per ton transportation rate in Barbil is highest in the world. A guideline for freight charges in this regard was issued by the Odisha Government but it’s not being followed.
The guideline should be enforced by the state govt. strictly.
4 Bhushan Power & Steel Ltd. Odisha
Execution of Jamkhani Coal Block
Pending with Department of Steel and Mines, Government of Odisha.
Matter may be expedited.
Execution of Mining Lease of Bijahan Coal Block
Pending with Department of Steel and Mines, Government of Odisha
5 RINL Application for ML 5 ML applications are pending with the State Government for allotment of iron ore mines. To be expedited.
6 Monnet Ispat
Angul, Odisha
Captive iron ore mine State Government should provide required help
7 Posco‐India Private Ltd.
12 MTPA Integrated Steel
Prospecting Licence (PL) In 2006, the
Govt. of Odisha recommended POSCO’s
PL application dated July, 2005 to the
Central Govt for the grant of PL in
The MoM should take the
decision at the earliest so
that POSCO can start the
prospecting mining
13
Plant
Jagatsinghpur,
Odisha
Sundergarh. After hearing all pending
applicants as per the order of the
Revisional Tribunal, the Govt. of Odisha
again recommended POSCO’s PL
application in 2009. The
recommendation was, however,
quashed by the Odisha High Court in
2010. Finally, on 10th May 2013, the
Hon’ble Supreme Court set aside the
Odisha High Court’s order and remitted
the matter to the Central Govt to take a
decision on an early date and
communicate the same to the Govt. of
Odisha.
activities
Essar Steel Limited
Paradip Odisha
Allocation of Captive mines Pending with State Government
Grant of Priority C status for movement of Iron Ore Fines from Dhamra to ISP at Hazira.
State Government should provide required help
8
Essar Steel Limited
Vizag
Laying of Iron Ore slurry pipeline between Kirandul and Vizag
Matter is under consideration with Odisha State Government.
9
OMDC Renewal of mining leases of:‐
Kolha‐Roida Iron Ore & Mn.
Mines (254.942 Ha.).
Thakurani Iron Ore & Mn.
Mines (778.762 Ha.).
Dalki Mn. Manganese Mines
(266.77 Ha.).
Bhadrasahi Iron Ore & Mn.
Mines (998.70 Ha.).
Belkundi Iron Ore & Mn. Mines
(1276.798 Ha.)
Bagiaburu Iron Ore Mines
(21.52 Ha.).
Govt. of Odisha to expedite the matter
14
ii) Permission to operate Kolha‐
Roida Iron Ore & Mn. Mines
which has got all Statutory
Clearances since 23.07.2012.
iii) Permission for dispatch / Sale
of Mined out ores in various
stock areas of all the above
mining leases.
10 VISA STEEL LIMITED
District Jajpur, Kalinganagar (Odisha)
Allotment of 306 Ac of land for solid waste disposal
State Government to expedite.
Supply of adequate quantity of Iron Ore and Chrome Ore at reasonable price under long term agreement from OMC.
State Government to help .
Visa Steel signed MoU with Odisha Govt. in 2003. Allotment of captive iron ore mine pending since 2005
State Government to expedite allocation of captive iron ore mine.
Price fixing mechanism for proposed e‐auction of iron ore and casting one for chrone ore by OMC needs to be modified for viability of the user industry.
State Government to take favourable decision
Allotment of additional 675 acres of adjoining land for expansion of steel capacity to 2.5 MTPA at Kalinganagar.
State Government to speed up the process
15
ISSUES PERTAINING TO GOVERNMENT OF MAHARASHTRA
S.No Name of the
company and
location
Issues in Brief Action to be Taken
1. SAIL (CFP) Chandrapur, Maharashtra
Issue of Prospecting License(PL) of Manganese ore for Chandrapur Ferro Alloy Plant (CFP) in four areas namely Tekadi, Hiwra, Paonar Khairi and Gonditola
The areas for Prospecting License (PL) may be allocated to SAIL on priority for the viability of the CFP/SAIL.
2 JSW Ispat Steel
Ltd., Dolvi, Tal‐Pen,
Dist. Raigad,
Maharashtra
a) Land Acquisition of internal land area of 4.16.30 Hect required for expansion of the plant.
Government should help in land acquisition where minority land holders where land is embedded are holding back
b) Issuance of LoI for
Iron Ore Mine in
Gadchiroli District for
which prior approval
under Section 5(1) of
MMDR Act 1957
already granted
Government should expedite the matter
16
ISSUES PERTAINING TO GOVERNMENT OF WEST BENGAL
S.No Name of the
company and
location
Issues in Brief Action to be Taken
1. JSW Steel Ltd Salboni, West Bengal
Reservation of Ghatkuri Mines, Jharkhand for the Steel plants coming up in the State of West Bengal. In the year 2006, Govt of Jharkhand has reserve the area for the PSU u/s 17 A (2) of MMDR ACT, 1957.
To be expedited.
2. Jai Balaji Industries Limited.
Brown Field Mangalpur, P.O Bakhtarnagar, Distt. Burdwan, West Bengal
Grant of NOC for expansion Pending with State Government.
Greenfield Project at Raghunathpur, Distt Purulia, WB
Land Deed is not executed
Grant of NOC
Execution of Agreement for water requirement
Early execution of Land Deed from Government of West Bengal Pending with State Government. Early execution of Agreement Pending with State Government
17
ISSUES PERTAINING TO GOVERNMENT OF KARNATAKA
S.No Name of the
company and
location
Issues in Brief Action to be Taken
1 NMDC Ltd.
Granting of ML in the
Ramandurg iron ore mine
to NMDC primarily to
ensure feeding of iron ore
on sustained basis, to the
steel plant proposed to be
set up by NMDC at Bellary
in pursuance of MoU
singed between Govt. of
Karnataka and NMDC
To be expedited
2. RINL Application for captive iron
ore mine
One ML application is pending for
consideration
3. Arcelor Mittal India Ltd. Bellary, Karnataka
Application for captive iron
ore mining pending with
the State Govt.
State Govt. to expedite processing.
18
ISSUES PERTAINING TO GOVERNMENT OF ANDHRA PRADESH
S.No Name of the
company and
location
Issues in Brief Action to be Taken
1. RINL Water : RINL made Tripartite agreement with Govt. Of Andhra Pradesh and Visakha Industrial Water Supply Company (VIWSCO) to meet its raw water requirement. The agreement envisages increase in water quantity to meet expansion requirement by making a supplementary agreement. RINL is pursuing for supplementary agreement for enhancing water quantity up to 45mgd to meet the requirement for 7.3 mtpa
State Government of Andhra Pradesh to provide required help
Power : 1. Eastern Power Distribution Company of A.P (APEPDCL) had enforced Restriction & Control (R&C) measures, even for drawl of power within the Contracted Maximum Demand, with effect from September’12 onwards. RINL had also taken up the matter of exemption of R&C measures with the Hon’ble Chief Minister of AP and other officials for kind consideration. A writ petition is also filed at Hon’ble AP High court seeking relief from imposition of R&C
Since, RINL is a continuous manufacturing Plant with captive power generation and highly thermal sensitive units, help required from State Govt. of Andhra Pradesh to
- exempt RINL from R&C measures for safe operation of the plant,
- waiver of penal charges imposed on RINL towards R & C measures & surcharges, which include penal charges on account of momentary surges in power import due to disturbances in captive power generation
- regularize RINL’s request for enhancement of Contracted Maximum Demand, from 135 MVA to 235 MVA, to ensure commissioning of expansion units.
19
measures. APEPDCL has levied 118.78 crores towards penal charges on account of R & C measures for the period Sept’12 to May’13 and cumulative surcharge of 5.75 crores for delay in non-payment of the penal charges. 2. RINL had filed an application in Oct.’07 for enhancement of contract demand to 400MVA in phased manner for meeting 6.3 MTPA expansion requirements from existing 135 MVA at 3.0 MTPA stage. APTRANSCO agreed to take up the power requirement in 4 phases at a cost of 86.33 crores. RINL paid 63.02 crores for phase 1, 2 & 3. The phase 1 works have been completed by APTRANSCO and clearances have been given by APTRANSCO and APEPDCL to enhance the Contract Maximum Demand by 100 MVA from 135 MVA to 235 MVA).
Revenue loss to the tune of 3.15 crores towards energy export during Jan & Feb.’07
During the power crisis during Jan & Feb’ 2007, RINL maximised its captive generation by changing the fuel mix to export power to grid based on the written request from CMD / APEPDCL.
In spite of agreed price @ 3.24 per unit towards the export for the period, the
Support from State Govt. of Andhra Pradesh is needed for the Payment of 3.15 Crores to RINL from APTRANSCO / APPCC towards energy export during Jan & Feb.’07.
20
APTRANSCO / APPCC initially paid @ 3.24 per unit, later adjusted to the @ 1.75 per unit, resulting in loss of revenue amounting to 3.15 crores.
Expressway alignment
Visakhapatnam–Kakinada Petroleum, Chemicals and Petro-Chemicals Investment Region Special Development Authority (VK-PCPIR SDA) proposed Expressway alignment (75 M corridor) connecting Kakinada Port to Gangavaram Port, along Visakhapatnam coast or across RINL land premises. Considering future expansion, captive port, desalination plant, safety and security aspects, RINL-VSP informed that above alignments are not feasible and suggested to take up alignment along western boundary of VSP.
GoAP to consider the alignment as suggested by VSP.
Allocation of Land RINL requested GoAP to allocate about 800 acres of land nearer to VSP to facilitate re-location of green belt so that existing green belt land adjacent to Plant premises may be used for establishing expansion units.
GoAP to expedite allocation of land.
Double lane road VSP’s Hyderabad stockyard is located at
Support from GoAP for widening of single lane road to a double lane
21
Patancheru and connected by single lane road from National Highway, which is to be widened to a double lane road.
road.
Govt of Andhra Pradesh has issued a Memo stating that RINL’s application for ML/PL in two areas in Warangal and Karimnagar districts would be processed.
To be expedited
2 M/S Kamineni
Steel & Power
India Pvt. Ltd.
Non‐allocation of Water to their Steel Plant
To be expedited
3. Essar Steel Limited
Vizag
Laying of Iron Ore slurry pipeline between Kirandul and Vizag
Matter is under considered with Odisha State Government.