integrating renewable energy to the grid

Post on 12-May-2015

1.471 Views

Category:

Technology

1 Downloads

Preview:

Click to see full reader

DESCRIPTION

Joe Corbett, Mainstream's Head of Technology presented to the Institution of Engineering and Technology on 27 February in London. The presentation seeks to examine the rationale and technical challenges to the Energy Bridge proposition. The presentation also focuses on the technology advances relating to the Supernode concept.

TRANSCRIPT

The Energy Bridge Ireland – UK Rationale and Technical challenges

- Joe Corbett, Head of Technology- London, 27 February 2014

2

Chile (onshore wind & solar)

Pipeline:1,200MW

South Africa (onshore wind & solar)

Pipeline: 4,854MW

USA (onshore)Pipeline: 1,265MW

Germany (offshore wind)Horizont: 1,200MW

Scotland (offshore wind)Neart na Gaoithe: 450MW

UK (offshore wind)Hornsea: 6,000MW

Canada (onshore wind & solar)

Pipeline:995MW

Ireland (onshore wind)Pipeline: 1200 MW

In Construction/In Operation In Development

Ireland (onshore wind)Knockaneden – 9 MWCarrickeeney – 8 MW

Old Man wind farm - 46MW

Jeffreys Bay wind farm – 138MWDe Aar solar park – 50MW

Droogfontein solar park – 50MW

Negrete wind farm – 33MW

Coal26%

Nu-clear25%

Gas24%

Hy-dro15%

Wind3%

Oil3%

Biomass2%

Waste1%

Solar PVGeothermal

•Energy Security

•Sustainability

•Economic Development

•GHG Reduction

Source: IEA

Drivers for Change – Europe’s Electricity Fuel Mix (2008)

Debate?

S. & Cent. America1%

Azerbaijan1% Kazakhstan

2%

Russian Federation

33%

Turk-menistan

2%Uzbek-istan2%

Africa15%

Middle East8%

Western Europe

35%

•Remove Coal•Nuclear Debate•Increase Renewables•Secure Supplies•Invest in Transmission

Constraints•Regulation•Public Opposition

•Onshore Wind•Overhead Lines

Europe Gas Sources 2010Source: BP

• Ireland 2020 targets• 4GW

• Gate 3 = 3.9GW• Only require 55%• Future of PSO Contribution for wind beyond gate 3?

• Currently 13.5GW in queue BEYOND Gate 3

•Not possible to absorb domestically•Curtailment / Constraint

• Interconnector Exports?

Beyond Gate 3 (2025) – The Queue

Ireland & UK 2020 Targets Synergy

Ireland● Electricity from Renewables by 2020 – 40%

● Equates to 4 GW installed by 2020● 2 GW already installed● 0.25 GW p.a. required to reach target● 16 GW waiting in Grid Queue!

● Only requires 12.5% of current grid queue to reach2020 target

● Irish Wind potential = 345 TWh p.a.● Equates to 19 x market size● Significant opportunity to Export

UK● Electricity from Renewables by 2020 – 30%

● Equates to 35 GW installed by 2020● Currently 8.5 GW installed● 3.3 GW p.a. required to reach target● 22 GW in Grid Queue

● UK installed 0.7 GW in 2011

● LCPD – coal decommissioning

Political Stimulus

● Concept of export first raised at British Irish council 2011

● Declarations of intent made by both ministers June 2012 to enact legislation

● UK Energy Bill Dec 2012● Provides for projects outside UK REZ to

qualify for CfD’s

● Bi-lateral MoU now signed● IGA Q1 2014

Mainstream Energy Bridge – 5,000MW Direct Export

Projects of Common Interest and SuperNode

Energy Bridge Context

Technology and Innovation

12

Cables Today

● AC Application● SCFF - 500kV / 1,200 MW● XLPE - 500kV / 1,000 MW

● DC Application● Mass-Impregnated (MI)

● 500kV / 1,600 MW Installed● 600kV / 2,200 MW Awarded

● Extruded (XLPE)● 200kV / 400 MW Installed● 320kV / 900 MW Awarded

● SCFF● AC/DC● Short Lengths

13

Grid Design

Friends of the Supergrid Technical Working Group

DC Breakers

•Resonance

•Power Electronics•Full Bridge Conversion

•Ballistic Breaker

•Superconductor

•Hybrid

•Plasma

Ballistic Breaker™

Roger Faulkner :Ballistic Breaker Corporation

Long Distance Transmission

•HVDC•Overhead Lines

•Permitting/Consent

•Cables (>100 Years Old)•MI = 800kV •XLPE = 500kV•No. Joints•Drilling / Tunnelling

•GIL•Elpipes•Research

Roger Faulkner: LONG DISTANCE UNDERGROUND HVDC TRANSMISSION VIA ELPIPES (ICHVE 2010)

Baker Hughes

Technology Development (Friends of the Supergrid – Technical Working Group)

● Increased power ratings for VSC (1,000 MW at 320 kV DC)

● Demonstrators for DC side fault clearing (e.g. DC Circuit Breakers)

● DC 320 kV cables with extruded insulation in operation at different onshore and offshore projects (500 MW per cable)

● DC cables with extruded insulation >320 kV developed

● MI-PPL 600kV (1.1GW per cable) developed and higher voltages in development

● MI >500 kV cable developed

● AC GIL in operation

● Standardization work for HVDC grids in CIGRÈ, CENELEC started

Today – 2015 (Supergrid Preparation Phase)

2015 – 2020 (Supergrid Phase 1)

After 2020 (Supergrid Phase 2)

● DC cables with extruded insulation >320 kV in operation

● MI-PPL 600kV cable in operation

● MI >500kV in operation

● Development of new extruded insulation compounds for HVDC cables

● System for fast selective fault detection in HVDC networks

● DC side selective fault clearing and system reconfiguration

● Hierarchical control architecture for integrated AC and DC Grid in Europe

● Demonstrators for DC/DC Converter

● Further Development of MI and MI-PPL Cables

● HVDC cables with new extruded insulation compounds in operation

● Superconducting cables

● DC GIL

● DC/DC converter

Control and InformationCo

mm

unica

tions

/SCA

DA SuperNode Control

AC Control & Protection

Smart Meter

Source: Sustainable Energy Horizon Panel report

Mainstream Initiatives

Friends of the Supergrid

SuperNode• Low Voltage Model• Medium Power Pilot (H2020)• TEN-E-Funding• SuperNode Concept Design and Scale

Model

PowerTube

International Bodies Working Groups

Inventing the Future

Insanity: doing the same thing over and over again and expecting different results.— Albert Einstein—

There are those who look at things the way they are, and ask why... I dream of things that never were, and ask why not?— Robert Kennedy —

Source: Microsoft

We are on a once-off transition to sustainability

Joe CorbettHead of Technology

joe.corbett@mainstreamrp.comwww.mainstreamrp.com

Thank You

top related