“Works in Progress to the “Works in Progress to the Football World Cup Football World Cup –– Brazil 2014”Brazil 2014”
AIRPORT INFRASTRUCTURE FIFA WORLD CUP 2014
August 2011
Eng. Márcio Eduardo Rodrigues KuntzINFRAERO
Airports Pavement Seminar & VI FAA Airport Pavement Workshop, I Short Course of Airfield
Pavements Maintenance
Airports – FIFA WORLD CUP 2014
• Belo Horizonte (Confins) - MG
1. Tancredo Neves International Airport– Confins
2. Belo Horizonte, Pampulha Airport – Carlos Drummond de Andrade
• Brasília - DF
3. Brasília International Airport – Presidente Juscelino Kubitschek
• Cuiabá - MT
4. Marechal Rondon International Airport - Cuiabá
• Curitiba - PR
5. Afonso Pena International Airport - Curitiba
• Fortaleza - CE
6. Pinto Martins International Airport - Fortaleza
• Manaus - AM
7. Eduardo Gomes International Airport – Manaus
• Natal - RN
8. São Gonçalo do Amarante International Airport – Natal
CuiabáCuiabáBrasília
Recife
Natal
Confins
Santos DumontGaleão
Porto Alegre
Manaus
Curitiba
Salvador
Guarulhos
Fortaleza
Congonhas
PampulhaCampinas
• Porto Alegre - RS
9. Salgado Filho International Airport – Porto Alegre
• Recife - PE
10. Recife – Guararapes International Airport – Gilberto Freire
• Rio de Janeiro - RJ
11. Rio de Janeiro,Galeão International Airport – Antonio Carlos Jobim – Rio de Janeiro
12. Santos Dumont Airport – Rio de Janeiro
• Salvador - BA
13. Salvador International Airport – Deputado Luis Eduardo Magalhães
• São Paulo, Guarulhos e Campinas - SP
14. Congonhas Airport - São Paulo
15. São Paulo,Guarulhos International Airport – Gov. André Franco Montoro
16. Viracopos,Campinas International Airport - Campinas
Airports - FIFA WORLD CUP 2014
Host Citys FIFA WORLD CUP
Investiments ‐ 2010 to 2014
Ord City Airport
Value (R$ million) 2010 (mi) 2014 (mi)
Ca Dem Ca Dem
1 São Paulo Guarulhos 1.229,36 24,9 26,8 52,7 38,9
Congonhas ‐ 12,0 13,7 15,0 15,0
Campinas 804,1 6,8 5,4 24,0 9,5
2 Rio de Janeiro Galeão 697,30 17,4 12,3 44,0 18,7
Santos Dumont ‐ 8,5 3,6 8,5 5,4
3 Belo Horizonte Confins 505,65 10,2 7,2 16,5 13,0
Pampulha ‐ 1,5 0,6 1,5 0,9
4 Brasília Brasília 563,24 14,0 14,3 26,5 21,30
5 Porto Alegre Porto Alegre 711,35 11,2 6,6 15,2 8,8
6 Curitiba Curitiba 242,36 7,8 5,7 14,6 7,6
7 Recife Recife 24,60 16,7 5,9 16,7 7,8
8 Salvador Salvador 47,61 12,9 7,6 12,9 10,2
9 Fortaleza Fortaleza 347,78 6,2 5,0 8,6 7,0
10 Manaus Manaus 393,51 6,4 2,6 13,5 3,8
11 Cuiabá Cuiabá 91,33 1,9 2,1 5,7 3,1
12 Natal São Gonçalo do Amarante 506,32 ‐ ‐ 5,9 2,9
Totais 5,658,19 158,40 119,40 275,90 171,0
Legend: Ca – Capacity of Airport Terminal
Dem ‐ Demand of passengers (boarding, landing and connection).
Airports Investiments- FIFA WORLD CUP2014Overview
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 505,65 million
Operational Data 2010 2014
Airport Terminal (m²): 60.305 67.675
Airport Terminal Capacity (pax,year): 10,28 million 16,5 millionAirport Passenger Demands,Year: 7,26 million 13,0 million
Airport Apron(m²): 114.240 306.640
City: Belo Horizonte Airport: Int. Tancredo Neves - Confins
1 AIRPORT TERMINAL RENOVATION AND ROAD SYSTEM
ADEQUACYScheduled Start: September,2011Scheduled Conclusion: December,2013Total Planned Investment: R$ 236,65 million
2 RUNWAY AND APRON RENOVATION AND EXPANSION
Scheduled Start: September,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 169,00 million
City: Belo Horizonte Airport: Int. Tancredo Neves - Confins
3 NEW REMOT AIRPORT TERMINAL, PARK, AIRPORT CARGO
TERMINAL EXPANSION AND ROAD SYSTEM ADEQUACYScheduled Start: March,2012Scheduled Conclusion: March,2013Total Planned Investment: R$ 100,00 million
City:BrasíliaAirport: Int. Pres. Juscelino Kubitschek
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 563,24 million
Operational Data 2010 2014Airport Terminal (m²): 81.200 175.000Airport Terminal Capacity (pax,year): 12,00 million 26,50 millionAirport Passenger Demands,Year: 14,34 million 21,34 million
Airport Apron(m²): 181.000 403.000
City:BrasíliaAirport: Int. Pres. Juscelino Kubitschek
1 AIRPORT TERMINAL EXPANSION - TEMPORARY
Scheduled Start: August,2011Scheduled Conclusion: November,2011Total Planned Investment: R$ 4,63 million
2 AIRPORT TERMINAL RENOVATION
Start: April2011Scheduled Conclusion: January,2012Total Planned Investment: R$ 4,9 million
3 AIRPORT TERMINAL RENOVATION, APRON
EXPANSION, ROAD SISTEM AND NEW BUI/LDINGSCOMPLEMENTARYScheduled Start: February,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 4,9 million
4 2º AIRPORT VIADUCT
Scheduled Start: January,2012Scheduled Conclusion: October,2012Total Planned Investment: R$ 116,24 million
City: CuiabáAirport: Int. Marechal Rondon
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 91,33 million
Operational Data 2010 2014Airport Terminal (m²): 5.460 13.200Airport Terminal Capacity (pax,year): 1,98 million 5,7 millionAirport Passenger Demands,Year: 2,1 million 3,1 million
Airport Apron(m²): 38.800 38.800
Airport Park (m²): 9.450 13.785Aiport Park Capacity (un): 405 517
1.533
City: CuiabáAirport: Int. Marechal Rondon
1 AIRPORT TERMINAL RENOVATION AND EXPANSION,
ROAD SYSTEM ADEQUACY END NEW PARKScheduled Start: April,2012Scheduled Conclusion: July,2013Total Planned Investment: R$ 88,43million
ESTACIONAMENTOVEÍCULOS
2 AIRPORT TERMINAL EXPANSION - TEMPORARY
Start: June,2011Scheduled Conclusion: November,2011Total Planned Investment: R$ 2,90 million
City: CuritibaAirport: Int. Afonso Pena
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 242,36 million
Operational Data 2010 2014Airport Terminal (m²): 45.000 62.445Airport Terminal Capacity (pax,year): 7,8 million 14,6 millionAirport Passenger Demands,Year: 5,7 million 7,6 million
Airport Apron(m²): 84.062 143.941
City: CuritibaAirport: Int. Afonso Pena
1 RUNWAY AND TAXIWAY SISTEM EXPANSION
Start: July,2011Scheduled Conclusion: April,2013Total Planned Investment: R$ 1,69 million
2 AIRPORT TERMINAL AND ROAD SISTEM
EXPANSIONScheduled Start: April,2012Scheduled Conclusion: October,2013Total Planned Investment: R$ 41,30 million
3 AIRPORT CARGO TERMINAL EXPANSION
Start: December,2010Scheduled Conclusion: March,2013Total Planned Investment: R$ 17,78 million
4 THIRD RUNWAY PROJECT
Scheduled Start: January,2013Scheduled Conclusion: December,2013Total Planned Investment: R$ 14,28 million
City: FortalezaAirport: Int. Pinto Martins
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 347,78 million
Operational Data 2010 2014Airport Terminal (m²): 38.500 61.964Airport Terminal Capacity (pax,year): 6,22 million 8,7 millionAirport Passenger Demands,Year: 5,07 million 6,5 million
Airport Apron(m²): 38.000 76.000
City: FortalezaAirport: Int. Pinto Martins
PÁTIO of AERONAVES
1 AIRPORT TERMINAL RENOVATION AND EXPANSION
AND ROAD SYSTEM ADEQUACYScheduled Start: January,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 347,78 million
City: ManausAirport: Int. Eduardo Gomes
FIFA WORLD CUP 2014Investiments 2011-2014
R$ 393,51 million
Operational Data 2010 2014Airport Terminal (m²): 43.000 80.000Airport Terminal Capacity (pax,year): 6,4 million 13,5 millionAirport Passenger Demands,Year: 2,6 million 3,8 million
Airport Apron(m²): 45.000 45.000
City: ManausAirport: Int. Eduardo Gomes
PÁTIO of AERONAVES
PISTA of POUSO,ofCOLAGEM
1 AIRPORT TERMINAL RENOVATION AND
EXPANSION AND ROAD SYSTEM ADEQUACYScheduled Start: November,2011Scheduled Conclusion: December,2013Total Planned Investment: R$ 393,51 million
City: NatalAirport: São Gonçalo do Amarante
FIFA WORLD CUP 2014Investiments 2010-2014
R$ 506,32 million
Operational Data 2010 2014Airport Terminal (m²): - 5,9 millionAirport Terminal Capacity (pax,year): - 2,9 million
Airport Apron(m²): 200.400 200.400
City: NatalAirport: São Gonçalo do Amarante
1 NEW TAXIWAY AND APRON
Start: May,2011Scheduled Conclusion: November,2013Total Planned Investment: R$ 98,32 million
2 AIRPORT TERMINAL CONSTRUCTION
Scheduled Start: August,2011Scheduled Conclusion: -Total Planned Investment: R$ 408,00 million
City: Porto AlegreAirport: Int. Salgado Filho
FIFA WORLD CUP2014Investiments 2010-2014
R$ 711,35 million
Operational Data 2010 2014Airport Terminal (m²): 37.600 104.304Airport Terminal Capacity (pax,year): 11,24 million 15,24 millionAirport Passenger Demands,Year: 6,6 million 8,8 million
Airport Apron(m²): 92.567 130.587
Airport Park (vehicles) (m²): 54.837 130.000Airport Park Capacity (vehicles) (un): 2.031 4.653Airport Park Demands (vehicles) (un): 2.667 4.000
City: Porto AlegreAirport: Int. Salgado Filho
1 AIPORT TERMINAL AND APRON RENOVATION
AND EXPANSIONScheduled Start: September,2011Scheduled Conclusion: December,2013Total Planned Investment: R$ 345,80 million
2 RUNWAY AND TAXIWAY EXPANSION
Scheduled Start: February,2012Scheduled Conclusion: November,2013Total Planned Investment: R$ 223,20 million
3 NEW AIRPORT CARGO TERMINAL
Start: November,2010Scheduled Conclusion: October,2012Total Planned Investment: R$ 137,15 million
4 AIRPORT TERMINAL EXPANSION
Start: May,2011Scheduled Conclusion: November,2011Total Planned Investment: R$ 5,20 million
City:RecifeAirport: Int. Gilberto Freire
FIFA WORLD CUP 2014Investiments 2010-2014
R$ 24,60 million
Operational Data 2010 2014Airport Terminal (m²): 52.000 52.000Airport Terminal Capacity (pax,year): 8,0 million 8,0 millionAirport Passenger Demands,Year: 4,7 million 7,3 million
Airport Apron(m²): 132.000 132.000
City:RecifeAirport: Int. Gilberto Freire
1 NEW AIRPORT CONTROL TOWER
Scheduled Start: February,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 18,47 million
2 NEW CONECTOR
FinishedTotal Planned Investment: R$ 6,13 million
City: Rio de JaneiroAirport: Int. Antônio Carlos Jobim
FIFA WORLD CUP 2014Investiments 2010-2014
R$ 697,30 million
Operational Data 2010 2014Airport Terminal (m²): 150.000 150.000Airport Terminal Capacity (pax,year): 17,4 million 44,03 millionAirport Passenger Demands,Year: 12,3 million 18,7 million
Airport Apron(m²): 666.400 666.400
City: Rio de JaneiroAirport: Int. Antônio Carlos Jobim
1 AIRPORT TERMINAL 1 RENOVATION
Scheduled Start: January, 2012Scheduled Conclusion: July ,2013Total Planned Investment: R$ 254,10 million
2 AIRPORT TERMINAL 2 RENOVATION
Start: November, 2008Scheduled Conclusion: October,2013Total Planned Investment: R$ 316,53 million
3 RUNWAY AND APRON SISTEM
RENOVATIONScheduled Start: September,2011Scheduled Conclusion: October,2013Total Planned Investment: R$ 103,43 million
4 AIRPORT CARGO TERMINAL RENOVATION
Start: September,2009Scheduled Conclusion: December,2011Total Planned Investment: R$ 23,24 million
City: SalvadorAirport: Int. Luís Eduardo Magalhães
FIFA WORLD CUP 2014Investiments 2010-2014
R$ 47,61million
Operational Data 2010 2014Airport Terminal (m²): 69.750 69.750Airport Terminal Capacity (pax,year): 12,96 million 12,96 millionAirport Passenger Demands,Year: 7,69 million 10,28 million
Airport Apron(m²): 79.645 91.395
City: SalvadorAirport: Int. Luís Eduardo Magalhães
PISTA of POUSO,ofCOLAGEM
1 AIRPORT TERMINAL RENOVATION AND
ADEQUACY AND APRON EXPANSIONScheduled Start: March,2012Scheduled Conclusion: July ,2013Total Planned Investment: R$ 32,17 million
2 NEW AIRPORT CONTROL TOWER
Scheduled Start: January,2012Scheduled Conclusion: November,2013Total Planned Investment: R$ 15,44 million
City: GuarulhosAirport: Int. Gov. André Franco Montoro
FIFA WORLD CUP2014Investiments 2010-2014
R$ 1,229 Billion
Operational Data 2010 2014Airport Terminal (m²): 175.000 290.000Airport Terminal Capacity (pax,year): 24,97 million 52,74 millionAirport Passenger Demands,Year: 26,8 million 38,91 million
Airport Apron(m²): 650.747,73 768.547,73
City: GuarulhosAirport: Int. Gov. André Franco Montoro
1 THIRD AIRPORT TERMINAL PROJECT
Start: May,2011Scheduled Conclusion: November,2012Total Planned Investment: R$ 752,91 million
2 RUNWAY AND APRON SISTEM
EXPANSIONStart: May,2010Scheduled Conclusion: October,2013 TotalPlanned Investment: R$ 307,05 million
3 NEW TAXIWAY
Scheduled Start: January,2012Scheduled Conclusion: March,2013Total Planned Investment: R$ 57,34 million
4 AIRPORT TERMINAL NEW EXPANSION -
TEMPORARYStart: July,2011Scheduled Conclusion: January,2012Total Planned Investment: R$ 86 million
5 AIRPORT TERMINAL NEW EXPANSION -
TEMPORARYScheduled Start: April,2012Scheduled Conclusion: December,2012Total Planned Investment: R$ 23,20million
City: CampinasAirport: Int. Viracopos
FIFA WORLD CUP2014Investiments 2009-2013
R$ 804,10 million
Operational Data 2009 2014Airport Terminal (m²): 25.215 25.215Airport Terminal Capacity (pax,year): 6,8 million 17,26 millionAirport Passenger Demands,Year: 5,4 million 9,53 million
City: CampinasAirport: Int. Viracopos
1 AIRPORT TERMINAL NEW EXPANSION -
TEMPORARYStart: October,2010Scheduled Conclusion: August,2011Total Planned Investment: R$ 7,0 million
2 AIRPORT TERMINAL ADEQUACY
Scheduled Start: July,2012Scheduled Conclusion: October,2013Total Planned Investment: R$ 48,06 million
3 NEW AIRPORT TERMINAL AND APRON
Scheduled Start: June,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 664,61 million
4 SECOND RUNWAY
Start: June,2011Scheduled Conclusion: May,2012Total Planned Investment: R$ 5,0 million
5 TAXIWAYS WITH FILLETS FOR A380 ADAPTATION , AIRPORT
CARGO TERMINAL EXPANSION, NEW APRON AND RUNWAYRESURFACINGScheduled Start: February,2012Scheduled Conclusion: December,2013Total Planned Investment: R$ 79,43 million
Thank You!
Eng. Márcio Eduardo Rodrigues Kuntz
INFRAERO
Superintendence of Works
marcio_kuntz@infraero.gov.br
(55 61) 3312-2568