Implementation of Water Safety Plan For

Rural Water Supply In Malaysia

Ministry of Health, Malaysia

July 2012

WSP Implementation Program

- Done

WSP Implementation Program

- Done

WSP Implementation Program

Malaysia Experience Piloting

Water Safety Plan’s

In Rural Communities

Steps Taken To Introduce WSPApril 2010 June 2010 Aug 2010 Sept 2010

Steps Taken To Introduce WSPOct 2010 – December 2011

Steps Taken To Introduce WSPFeb 2011 Dec 2010-June 2011 June-Dec 2011

Pilot Projects

Pilot Project On Sanitary Well (Kg Mela,

Kelantan)

Pilot Project On Sanitary Well (Kg Mela,

Kelantan)

Pilot Project On Gravity Feed System (Kg

Padang, Pahang)

Pilot Project On Gravity Feed System (Kg

Padang, Pahang)

Pilot Project On Rain Harvesting

System(Lundu, Serian, Sarawak)

Pilot Project On Rain Harvesting

System(Lundu, Serian, Sarawak)

Checklist Form Used In Implementing WSP

In Malaysia

BULAN :

TARIKH :_______/________/________

MASA :____________

40 sen/ BAYARAN BAYARAN JUMLAH TARIKH

BACAAN 1 BACAAN 2 JUMLAH unit METER (RM) TABUNG (RM) BAYARAN (RM) BAYARAN

Catitan : Bacaan1 - Bacaan 2 = Jumlah x 40sen/unit = Bayaran Meter + Bayaran Tabung = Jumlah Bayaran

PEMERIKSA METER :__________________________________ PEMERIKSA KIRA-KIRA :_____________________________________

REKOD PEMBAYARAN BIL AIR KG. MELA

NO METERBIL NAMA

Kg. Mela – Payment Record (Water Bill)

Example of Checklist Form Used In

Implementing WSP In Malaysia

Bulan : JAN / FEB /MAC /APR /MEI /JUN /JUL/AUG /SEP /OKT / NOV / DIS

Sistem Paip Agihan

a. Penyambungan paip agihan dalam Ya Tidak

keadaan sempurna.

b. Paip agihan pecah / bocor Ya Tidak

c. Meter air berfungsi dengan baik. Ya Tidak

d. Adakah terdapat penyambungan tanpa kebenaran Ya Tidak

e. Adakah perlu melakukan penyelenggaraan/pembaikian

Kerja-kerja penyelenggaraan

a. Tarikh :

b. Jenis Kerja :

c. Bilangan orang :

NAMA PEMERIKSA :_____________________________________

Catatan

SENARAI SEMAK PENYELENGGARAAN BEKALAN AIR BAGI TELAGA KG MELA, GUA MUSANG, KELANTAN

Kg. Mela – Sanitary Well Maintenance Checklist

Example of Checklist Form Used In

Implementing WSP In Malaysia

KKM/WSP/GFS/1

SENARAI SEMAK

PENYELENGGARAAN PROJEK BEKALAN AIR LUAR BANDAR BAGI GRAVITY FEED SYSTEM

(KAWASAN TADAHAN)

Bulan/Tahun: Tarikh:

Kampung: Masa:

1. Keadaan Persekitaraan Kawasan Tadahan

a. Tiada Pencemaran Ya Tidak

b. Pencemaran yang dikenal pasti di kawasan

sekitar kawasan tadahan(Jika Ada) ___________________________________

2. Keadaan Empangan(Dam)

a. Struktur empangan didalam kedaan baik Ya Tidak

b. Penapis di dalam keadaan baik Ya Tidak

c. Paip agihan Utama didlam keadaan baik

(50 meter dari kawasan tadahan) Ya Tidak

3. Kuantiti dan kualiti air

a. Kuantiti air didapati mencukupi Ya Tidak

b. Kualiti air Jernih Keruh

4. Masalah-masalah lain yang dikesan di kawasan tadahan

______________________________________________________________________________________

______________________________________________________________________________________

5.Ulasan dan cadangan penambaikan terhadap empangan(dam) oleh pemeriksa

______________________________________________________________________________________

______________________________________________________________________________________

Dilaporkan oleh

Tandatangan:

Nama Pemeriksa:

Disahkan oleh

Tandatangan:

Nama Pengesah :

Kg. Padang – GFS Maintenance Checklist (Catchment Area)

Example of Checklist Form Used In

Implementing WSP In Malaysia

KKM/WSP/GFS/2

SENARAI SEMAK

PENYELENGGARAAN PROJEK BEKALAN AIR LUAR BANDAR BAGI GRAVITY FEED SYSTEM

(PAIP AGIHAN UTAMA)

Bulan/Tahun: Tarikh:

Kampung: Masa:

1. Keadaan Paip Agihan Utama

a. Paip agihan utama didapati baik dan selamat Ya Tidak

b. Sambungan paip didapati baik Ya Tidak

c. Paip agihan utama didapati bocor/pecah Ya Tidak

(senaraikan tempat jika ada) ___________________________________

____________________________________________________________________________

d. Ada aktiviti penyambungan tanpa kebenaran Ya Tidak

(senaraikan tempat jika ada) ___________________________________

____________________________________________________________________________

e. Ada kesan gangguan binatang Ya Tidak

(senaraikan tempat jika ada) ___________________________________

____________________________________________________________________________

2. Masalah-masalah lain yang dikesan di Paip Agihan Utama

______________________________________________________________________________________

______________________________________________________________________________________

5.Ulasan dan cadangan penambaikan terhadap Paip Agihan Utama oleh pemeriksa

______________________________________________________________________________________

______________________________________________________________________________________

Dilaporkan oleh

Tandatangan:

Nama Pemeriksa:

Disahkan oleh

Tandatangan:

Nama Pengesah :

Kg. Padang – GFS Maintenance Checklist (Main Pipe)

Example of Checklist Form Used In

Implementing WSP In Malaysia

KKM/WSP/GFS/3

SENARAI SEMAK

PENYELENGGARAAN PROJEK BEKALAN AIR LUAR BANDAR BAGI GRAVITY FEED SYSTEM

(PAIP AGIHAN KE RUMAH)

Bulan/Tahun: Tarikh:

Kampung: Masa:

1. Keadaan Paip Agihan ke rumah

a. Paip agihan ke rumah didapati baik dan selamat Ya Tidak

b. Sambungan paip didapati baik Ya Tidak

c. Paip ke rumah didapati bocor/pecah Ya Tidak

(senaraikan tempat jika ada) ___________________________________

____________________________________________________________________________

d. Ada aktiviti penyambungan tanpa kebenaran Ya Tidak

(senaraikan tempat jika ada) ___________________________________

____________________________________________________________________________

e. Ada penyambungan ke rumah melebihi satu

penyambungan (bagi rumah yang tiada tangki

senaraikan tempat jika ada) ????? ___________________________________

____________________________________________________________________________

2. Masalah-masalah lain yang dikesan di Paip Agihan ke rumah

______________________________________________________________________________________

______________________________________________________________________________________

5.Ulasan dan cadangan penambaikan terhadap Paip Agihan ke rumah oleh pemeriksa

______________________________________________________________________________________

______________________________________________________________________________________

Dilaporkan oleh

Tandatangan:

Nama Pemeriksa:

Disahkan oleh

Tandatangan:

Nama Pengesah :

Kg. Padang – GFS Maintenance Checklist (Distribution Pipe)

Water Sampling RecordKg. Mela – Water Sampling

JABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTAN

Aras 5, Wisma Persekutuan, Jalan Bayam,

15590 Kota Bharu, Kelantan.

http://jknkelantan.moh.gov.my

Telefon: 09-7413300

09-7413400

09-7413406

09-7413407

Fax: 09-7441333

Pengarah Kesihatan Negeri (Talian Terus): 09-7443960

MAKLUMAT PESAMPELAN SAMPEL AIR BAKAS

(DISERTAKAN BERSAMA SEMASA PENGHANTARAN SAMPEL KE MAKMAL KESIHATAN PEROL

Tarikh Pesampelan : 31 Mei 2011 Masa Menconto h :12:40 PM Nama Bekalan/ Punca Air: TTSR Tempat Mencontoh :Kampung Mela (01) Jenis Air :Air Mentah Keputusan-keputusan Analisis Unit Nila i Bacaan --------------------------------------------------- ----------------- UJIAN FIZIKAL (DIJALANKAN PEGAWAI DI LAPANGAN) ---------------------------------------------- pH (6.5-9.0) - 6.39 TDS - Total Dissolved Solids (<1000) - 71.6 Kekeruhan (<5) NTU 0.69 Oksigen Terlarut mg/l 2.6 8 Suhu 0C 26.4 Warna (<15) TCU 5.0 Konduktiviti - - UJIAN MIKROBIOLOGI (DIJALANKAN DI MAKMAL) Keputu san --------------------------------------------------- ----------------- Total Coliform Absent / Present 2.0 MPN/100ml E.coli Absent / Present 0 MPN/100ml UJIAN KIMIA (DIJALANKAN DI MAKMAL) Unit Nilai Ba caan --------------------------------------------------- ----------------- Ammonia Nitrogen (NH3-N) (<1.5) mg/l 0.18mg/l Ammonia Nitrate (NO3-N) (<10) mg/l 0. 70mg/l Ferum (Fe)(<0.3) mg/l 1.60mg/l Mangan (Mn)(<0.1) mg/l 0.335mg/l Aluminium (Al) (<0.2) mg/l 0.025mg/l --------------------------------------------------- ----------------- …………………………………………………………….. (TANDATANGAN PENYAMPEL AIR) Cop: MOHD ZULKEFLY BIN SAID PENOLONG PEGAWAI KESIHATAN PERSEKITARAN (BAKAS) PEJABAT KESIHATAN DAERAH GUA MUSANG

Water Sampling Record

JABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTANJABATAN KESIHATAN NEGERI KELANTAN

Aras 5, Wisma Persekutuan, Jalan Bayam,

15590 Kota Bharu, Kelantan.

http://jknkelantan.moh.gov.my

Telefon: 09-7413300

09-7413400

09-7413406

09-7413407

Fax: 09-7441333

Pengarah Kesihatan Negeri (Talian Terus): 09-7443960

MAKLUMAT PESAMPELAN SAMPEL AIR BAKAS

(DISERTAKAN BERSAMA SEMASA PENGHANTARAN SAMPEL KE MAKMAL KESIHATAN PEROL

Tarikh Pesampelan : 31 Mei 2011 Masa Menconto h :01:10 PM Nama Bekalan/ Punca Air: TTSR Tempat Mencontoh :Kampung Mela (02) Jenis Air :Air Mentah Keputusan-keputusan Analisis Unit Nila i Bacaan --------------------------------------------------- ----------------- UJIAN FIZIKAL (DIJALANKAN PEGAWAI DI LAPANGAN) ---------------------------------------------- pH (6.5-9.0) - 6.42 TDS - Total Dissolved Solids (<1000) - 65.8 Kekeruhan (<5) NTU 1.67 Oksigen Terlarut mg/l 4.2 7 Suhu 0C 27.1 Warna (<15) TCU 12.0 Konduktiviti - - UJIAN MIKROBIOLOGI (DIJALANKAN DI MAKMAL) Keputu san --------------------------------------------------- ----------------- Total Coliform Absent / Present 151.5 MPN/100ml E.coli Absent / Present 16.1 MPN/100ml UJIAN KIMIA (DIJALANKAN DI MAKMAL) Unit Nilai Ba caan --------------------------------------------------- ----------------- Ammonia Nitrogen (NH3-N) (<1.5) mg/l 0.03mg/l Ammonia Nitrate (NO3-N) (<10) mg/l 0. 50mg/l Ferum (Fe)(<0.3) mg/l 0.17mg/l Mangan (Mn)(<0.1) mg/l 0.313mg/l Aluminium (Al) (<0.2) mg/l 0.016mg/l --------------------------------------------------- ----------------- …………………………………………………………….. (TANDATANGAN PENYAMPEL AIR) Cop: MOHD ZULKEFLY BIN SAID PENOLONG PEGAWAI KESIHATAN PERSEKITARAN (BAKAS) PEJABAT KESIHATAN DAERAH GUA MUSANG

Kg. Mela – Water Sampling

Water Sampling RecordKg. Padang – Water Sampling

Lesson Learned During Introduction Of

WSP Pilot Projects

� Thorough explanation and exchange of information on WSP needed,

� Full cooperation from community

� Comprehensive & suitable document made available

� Respective roles should be well defined and accepted

� Challenge in imparting understanding of the concept of health risks.

WSP Modules For Rural Water Supply

System

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

BAKAS Officers and Staffs Role and

ResponsibilityFor 2012 - Each district will start with one project

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

Villagers’ Role and Responsibility

WSP Modules For Rural Water Supply

Systems

WSP Modules For Rural Water Supply

Systems

Figure 1 : Distribution pipeline of Kg Padang, Jerantut, Pahang

WSP Modules For Rural Water Supply

Systems

WSP Modules For Rural Water Supply

Systems

Level Descriptor Rating (indicative) in numerical terms

Likely hood of occurrencecategory

A Almost Certain 5

B Likely 4

C Moderate 3

D Unlikely 2

E Rare 1

‘Severity/Impact/Consequence’ categoryA Insignificant No detectable impact

(1)

B Minor Aesthetic impact

causing

dissatisfaction (2)

C Moderate Major aesthetic impact

possibly resulting in

use of alternative

sources ( 3)

D Major Morbidity expected

from

consuming water (4)

E Catastrophic Mortality expected

from

consuming water (5)

WSP Modules For Rural Water Supply

Systems

Water sampling, checking the integrity of water supply system, sanitary survey

WSP Modules For Rural Water Supply

Systems

Auditing on records, situation in the field and water sampling

WSP Modules For Rural Water Supply

Systems

WSP Modules For Rural Water Supply

Systems

WSP Materials

WSP Materials

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Materials

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Posters

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Posters

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Posters

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Brochure - Wells

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Brochure - GFS

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Brochure – Rain Harvesting

Engineering Services Division, Ministry of Health, MalaysiaEngku Azman Tuan Mat

WSP Guideline

Thank You