This is the Post-Print version of the published material
For Citation: Özcan-Top Ö., and McCaffery F. (2017) “How Does Scrum Conform to the Regulatory Requirements Defined in MDevSPICE®?" In: Software Process Im-provement and Capability Determination. SPICE 2017. Communications in Computer and Information Science, vol 770. Springer, Cham, https://doi.org/10.1007/978-3-319-67383-7_19
How does Scrum Conform to the Regulatory Requirements Defined in MDevSPICE®?
Özden Özcan-Top1, Fergal McCaffery1,2
1Regulated Software Research Centre & Lero Dundalk Institute of Technology, Dundalk, Ireland
2STATSports Group, Dundalk, Ireland ozden.ozcantop@dkit.ie, fergal.mccaffery@dkit.ie
Abstract. Medical device software development is subject to high regulations
due to the potential risk of harming patients with unsafe medical devices. These
regulations require software development to be performed with high discipline
and evidence to be provided for auditory purposes. It’s not easy to manage both
conformance to regulations and efficiency in medical device development.
Therefore, there is a transition towards agility in safety critical systems develop-
ment, to build high quality systems, shorten time to market, improve customer
and employee satisfaction and ensure both safety and reliability. In this study, we
evaluated one of the most highly adopted agile software development methods,
Scrum from a regulatory perspective. We investigated to what extend the regula-
tory requirements defined in MDevSPICE® are met with implementation of the
Scrum method and what additional processes and practices have to be performed
to ensure safety and regulatory compliance in the healthcare domain.
Keywords. MDevSPICE®, Scrum, Regulatory Compliance, Safety Critical Do-
main, Agile Software Development.
1 Introduction
The safety critical nature of medical device software requires Medical Device (MD)
regulations are in place to ensure the safety of these devices. Manufacturers have to
comply with the requirements to market an MD within a particular region. International
standardizing bodies and regional regulatory authorities issue these requirements as
standards or guidance. In the US, the Food and Drug Administration (FDA) issues the
regulation through a series of official channels, including the Code of Federal Regula-
tion (CFR) Title 21, Chapter I, Subchapter H, Part 820 [1]. In the EU, the corresponding
regulation is outlined in the general Medical Device Directive (MDD) 93/42/EEC [2],
the Active Implantable Medical Device Directive (AIMDD) 90/385/EEC [3], and the
In-vitro Diagnostic (IVD) Medical Device Directive 98/79/EC [4] - all three of which
have been amended by 2007/47/EC [5].
Software development in medical domain is typically performed with traditional,
plan-driven approaches like Waterfall and V-Model. The V-Model is perceived to be
the best fit with regulatory requirements [6]. Some of the reasons why these methods
are still valid today, despite their rigidness and limitations, can be listed as follows: (a)
It is pretty straightforward to produce the necessary deliverables required to achieve
regulatory audits with these models. (b) Verification, validation and risk assessments
are particularly important in medical device software development and these processes
are planned and executed in parallel with a corresponding development phase of the V-
Model. (c) In these models, each phase must be completed before the next phase begins.
This approach works well when there is high confidence in the requirements defined.
Ensuring regulatory requirements continuously is only one of the challenges that
medical companies face. Some of others are managing the change during development,
being timely to market, ensuring high quality, safety and high productivity. Agile soft-
ware development methods have positive results for overcoming these challenges [7].
Therefore, there is a transition going on in medical device development companies to
achieve agility as well as safety and reliability.
In this study, we evaluated Scrum [8], to understand the level of regulatory compli-
ance when they are implemented. A mapping between these methods and the medical
device software process assessment framework, MDevSPICE® has been performed for
this purpose. The second purpose of this research is to reveal additional practices that
have to be performed to ensure compliance when there is no specific adaptation of
Scrum for the medical domain.
The rest of the paper is structured as follows: In Section 2, we provide the back-
ground for this research which includes brief descriptions of MDevSPICE® and Scrum.
We also provide a literature review of Scrum in the medical device development do-
main. In Section 3, we described the research methodology. In Section 4, we present
the mapping and discuss the additional practices that have to be considered. In Section
5, we provide conclusions for this research.
2 Background
2.1 MDevSPICE®
MDevSPICE® is a medical device software process assessment framework developed
with the purpose of integrating the regulatory requirements from the relevant medical
device software standards and guiding medical device software developers to produce
medical software that will be safe and reliable. It has been built upon 19 medical soft-
ware development and software engineering standards, some of which can be seen on
Fig 1.
The MDevSPICE® process assessment model is a two-dimensional model of the
process quality characteristic of process capability. In one dimension, the process di-
mension, the processes are defined. In the other dimension, the capability dimension, a
set of process attributes are grouped into capability levels. Processes in this process
assessment model are described in terms of their Purpose, Process Outcomes, Base
Practices and Work Products. Although the set of Process Outcomes is necessary and
sufficient to achieve the Purpose of the process, the Base Practices together with Work
Products provide a possible way to achieve the Process Outcomes. The list of processes
in MDevSPICE® process assessment model is given in
Fig. 2.
Fig. 1. Some of the Standards and Guidelines within MDevSPICE®
Safety classifications reflect the degree of harm that can result from medical device
usage. Every medical device has to be assigned a safety class. Different international
safety classification systems are in use throughout the world. There are three medical
device safety classifications under US and EU regulations. Based on IEC 62304:2006,
Class A devices are not intended to support or sustain human life, and may not lead to
unreasonable risk of illness or injury. Class B medical devices may cause damage or
harm to humans. Class C devices are usually those that support or sustain human life,
and present a potential risk on illness or injury. Hand-held surgical instruments are
Class A devices. An example of a Class B medical device is a powered wheelchair. An
example of a Class C device is an implantable pacemaker.
The software safety classification of a medical device will determine the amount of
IEC 62304 requirements that have to be fulfilled, with class A requiring much less
IEC 62304:2006, Medical device software – Software
life cycle processes
Medical Standards
IEC 80002-3:2014, process reference model
for Medical device software processes
ISO 14971:2009, Medical devices — Application of
risk management to medical devices
ISO 13485:2003, Medical devices — Quality
management systems — Requirements for
regulatory purposes
IEC 80002-1:2009, Guidance on the
application of ISO 14971 to medical device software
Process Assessment Standards
ISO/IEC 33002:2014, Information technology — Process assessment —
Requirements for performing process
assessment
ISO/IEC 15504-5:2012, Information technology – Process assessment –An
exemplar process assessment model
ISO/IEC 15504-2:2003, Information technology – Process assessment – Part 2: Performing an
assessment
ISO/IEC 12207:2008, Systems and Software
Engineering – Software life cycle processes
Software Life Cycle
practices to be put in place than for Class C. Additionally, the higher the safety classi-
fication the greater the amount of overhead associated with defining, implementing and
providing objective evidence that the defined processes have actually been imple-
mented. In this context, for each process, MDevSPICE® defines what outcomes have
to be achieved and which base practices need to be performed for these safety classes.
Fig. 2. MDevSPICE® Processes
2.2 Scrum
Scrum was developed by Schwaber and Sutherland with the purpose of providing a
management framework for software development [8, 9]. Scrum does not provide any
specific technical practices for implementation.
The fundamental idea behind Scrum is to apply process control theory to software
development to achieve flexibility, adaptability and productivity [7]. It relies on a set
of values, principles and practices which can be adopted based on specific conditions.
Scrum gives value on providing frequent feedback, embracing and leveraging variabil-
ity, being adaptive, balancing upfront and just-in-time work, continuous learning,
Medical Device System Life Cycle ProcessesPRO.1 Project PlanningPRO.2 Project Assessment and ControlPRO.4 Risk ManagementENG.1 Stakeholder Requirements DefinitionENG.2 System Requirements AnalysisENG.3 System Architectural DesignENG.5 System IntegrationENG.6 System Qualification TestingENG.7 Software InstallationENG.8 Software Acceptance Support
Medical Device Software Life Cycle ProcessesENG.4 Software Development PlanningDEV.1 Software Requirements AnalysisDEV.2 Software Architectural DesignDEV.3 Software Detailed DesignDEV.4 Software Unit Implementation and VerificationDEV.5 Software Integration and Integration TestingDEV.6 Software System TestingSRM.1 Software Risk Management
Support ProcessesPRO.5 Configuration Management
SUP.4 Software ReleaseSUP.8 Software Problem Resolution
SUP.9 Software Change Request ManagementENG.10 Software Maintenance
value-centric delivery and employing sufficient ceremony [10]. It offers effective solu-
tions by providing specific roles, artifacts, activities and rules.
A Scrum Team consists of a Product Owner, a Scrum Master and the Development
Team roles. Scrum Teams are self-organizing and cross-functional so that they could
accomplish their work by themselves, rather than being directed by others outside the
team and without depending on others not part of the team [9]. There are special events
in Scrum which have been developed to create regularity and to minimize the need for
meetings and are time-boxed.
2.3 Scrum Implementation in Safety Critical Domain
In the literature, we see many examples of Scrum implementation in the safety critical
domain [11-16] . We briefly discuss some of these studies below:
Wolff [11] presents implementation of a formal specification language and Scrum
with combination in an aircraft project. Executable specifications were used in order to
validate system functionality, to understand the requirements and design of the system
more precisely. In addition to conventional software implementation tasks within a
sprint, formal specification investigation tasks were also defined.
Regulated Scrum [12] is an example of an adapted approach which has been imple-
mented and validated in a highly regulated organization. Scrum was enhanced to ensure
regulatory compliance in the medical domain. Some of the enhancements of the ap-
proach are having quality assurance people who ensure regulatory compliance at the
end of each sprint (called continuous compliance), using templates to guide the devel-
opment process, implementing coding standards and performing peer code review, es-
tablishing end-to-end traceability from the requirements elicitation stage to the code
base with the help of tool support (called living traceability), risk management and con-
tinuous integration.
Another implementation of Scrum in a European space industry company with Test
Driven Development, Continuous Integration and Pair Programming was discussed in
[13]. Siemens Healthcare integrates Scrum into their software development process and
additionally implements “feature orientation” practice to resolve the challenge of man-
aging the flow of requirements coming from several product lines [14].
This literature review shows that Scrum was not used in the safety critical domain
with their original versions, but, tailored for this domain and also combined with sup-
plementary practices to ensure safety and regulatory compliance.
3 Research Approach
The purpose of this research is to reveal to what extend the regulatory requirements
defined in MDevSPICE® are met when implementing Scrum. We defined the following
research questions in relation to this purpose:
RQ1: How well the regulatory requirements of a safety Class B type medical device
are met by through implementation of Scrum? RQ2: Which processes of MDevSPICE®
are covered by implementing Scrum? RQ3: Which base practices of MDevSPICE® are
covered by an implementation of Scrum? RQ4: What additional practices regarding
those processes specified need to be performed in order to fully achieve a process at
Level 1: Performed Process?
Research steps.
1. Listing Scrum practices at a fine granularity level.
2. Mapping MDevSPICE® base practices with Scrum Practices.
3. Identifying which processes were affected from the mapping.
4. Identifying the coverage ratio and deciding which MDevSPICE® base practices
need to be included for those processes to satisfy a fully-achieved level.
Abrahamsson et al. [7], compared different agile software development methods to
show which phases of software development were supported by these methods. Based
on the comparison, Scrum covers project management, requirements specification, in-
tegration test and system test phases
However, instead of selecting these processes mentioned above first, and then check-
ing the coverage within MDevSPICE®, we preferred to do the mapping in the other way
around. We first listed the Scrum practices and then mapped them to MDevSPICE®
base practices. With this approach we were able to identify which processes of
MDevSPICE® were covered with a basic Scrum implementation.
Limitation of the Research.
Scrum could be taken as a prescriptive method with the descriptions of how the Scrum
events will be performed and artifacts will be developed. However, Scrum is not de-
fined at the practice description level provided by MDevSPICE®. Mapping of the
method was limited to the given information in the following resource: The Scrum
GuideTM by Ken Schwaber and Jeff Sutherland [17].
4 The Mappings and Discussions
Scrum and practices were mapped against MDevSPICE® (IEC 62304) Class B require-
ments. As the level of detail for the Scrum practices was limited, we needed to make
some assumptions during the mapping. We assumed that process artifacts such as pro-
ject plans or project monitoring reports would be developed during a Scrum implemen-
tation, as evidence required for the audits needed to be collected. Although it is very
likely that some base practices would be performed during software development using
Scrum, we couldn’t rate a 100% coverage for them, as they might not be performed at
the level of the detail required in MDevSPICE®. The coverage ratio is calculated based
on the formula of: “the number of achieved base practices in a process / all base prac-
tices in a process”.
4.1 Scrum Mapping
Scrum Method was described in terms of its roles, events and artifacts. Below, we pro-
vide the mapping for the roles and events. The artifacts which are basically product
backlog and sprint backlog were not included in the mapping separately, as they were
part of the events. Even though MDevSPICE® does not emphasize any specific roles,
we mapped the activities that needs to be performed by the Scrum roles to the base
practices of MDevSPICE®, shown in Table 1. In Table 2, the mapping between the
Scrum events and the MDevSPICE® Processes and Base Practices are provided (RQ2-
RQ3). The bold written text in the 3rd column of Table 1 and Table 2 show the mapped
processes. The other text in the same column refer to the mapped base practices (BPs).
Table 1. Mapping of Scrum Roles‘ Activities and MDevSPICE® Processes & Base Practices
Scrum
Roles
Specific Activities of the Roles MDevSPICE® Processes & Base
Practices
Product
Owner
“¾ deciding which features and func-
tionality to build and the order in
which to build them
¾ communicating to all other partici-
pants a clear vision of what the Scrum
team is trying to achieve
¾ being responsible for the overall
success of the solution being devel-
oped or maintained”
PRO.1 Project Planning
PRO.1.BP1: Define the scope of work
PRO.1.BP3: Evaluate feasibility of the
project.
PRO.1.BP6: Define needs for experience,
knowledge and skills.
PRO.1.BP7: Identify and monitor project
interfaces
PRO.1.BP9: Allocate resources and re-
sponsibilities.
PRO.1.BP11: Implement the project plan.
ENG.1 Stakeholder Requirements Defi-
nition
ENG.1.BP1: Identify stakeholders.
Scrum
Master
“¾ helping everyone involved under-
stand and embrace the Scrum values,
principles, and practices.
¾ helping the organization through
the challenging change management
process that can occur during a Scrum
adoption
¾ protecting the team from outside in-
terference and takes a leadership role
in removing impediments that inhibit
team productivity”
PRO.1 Project Planning
PRO.1.BP2: Define life cycle model for
the project.
Dev-
Team “¾ a diverse, cross-functional collec-
tion of these types of people who are
responsible for designing, building,
and testing the desired product”
PRO.1 Project Planning
PRO.1.BP4: Define and maintain esti-
mates for project attributes
PRO.1.BP5: Define project activities and
tasks.
PRO.1.BP8: Define project schedule.
PRO.1.BP10: Establish project plan.
PRO.1.BP11: Implement the project plan.
Table 2. Mapping of Scrum Events and MDevSPICE® Processes & Base Practices
Scrum
Events
Descriptions of the Events MDevSPICE® Processes and Base Prac-
tices
Sprint
Planning
“The work to be performed in
the Sprint is planned at the Sprint
Planning. This plan is created by
the collaborative work of the en-
tire Scrum Team.”
PRO.1 Project Planning
PRO.1.BP4: Define and maintain estimates
for project attributes
PRO.1.BP5: Define project activities and
tasks.
PRO.1.BP7: Identify and monitor project
interfaces.
Daily
Scrum
“A 15-minute time-boxed event
for the Development Team to
synchronize activities and create
a plan for the next 24 hours.”
PRO2. Project Assessment and Control
PRO.2.BP3: Report progress of the project.
PRO.2.BP4: Perform project review.
Sprint
Review
“A meeting held at the end of the
Sprint to inspect the Increment
and adapt the Product Backlog.
The timeline, budget, potential
capabilities, and marketplace for
the next anticipated release of the
product are reviewed”
PRO2. Project Assessment and Control
PRO.2.BP1: Monitor project attributes
PRO.2.BP2: Monitor project interfaces
PRO.2.BP3: Report progress of the project.
PRO.2.BP4: Perform project review.
PRO.2.BP5: Act to correct deviations.
Sprint Ret-
rospective
“A meeting to inspect how the
last Sprint went with regards to
people, relationships, process,
and tool”
PRO2. Project Assessment and Control
PRO.2.BP6: Collect project experiences
Product
Backlog
Grooming
“Product Backlog (PB) is an or-
dered list of everything that
might be needed in the product
and is the single source of re-
quirements for any changes to be
made to the product.” “PB lists
ENG.1 Stakeholder Requirements Defini-
tion
ENG.1.BP2: Obtain requirements.
ENG.1.BP3: Define constraints.
ENG.1.BP4: Define user interaction. ENG.1.BP5: Identify critical requirements.
all features, functions, require-
ments, enhancements, and fixes
that constitute the changes to be
made to the product in future re-
leases. Product Backlog items
have the attributes of a descrip-
tion, order, estimate and value.”
“PB Grooming is the act of add-
ing detail, estimates, and order to
items in the Product Backlog.
This is an ongoing process in
which the Product Owner and the
Dev-Team perform”
ENG.1.BP6: Evaluate requirements
ENG.1.BP7: Agree on requirements.
ENG.2 System Requirements Analysis
ENG.2.BP1: Establish system requirements.
ENG.2.BP3: Optimize project solution.
ENG.2.BP4: Analyze system requirements.
ENG.2.BP5: Evaluate and update system
requirements.
ENG.2.BP7: Communicate system require-
ments.
DEV.1 Software Requirements Analysis
DEV.1.BP1: Define and document all soft-
ware requirements.
DEV.1.BP2: Prioritize requirements.
DEV.1.BP6: Evaluate and update require-
ments
DEV.1.BP7: Baseline and communicate
software requirements.
According to the mapping shown in Table 1 and Table 2, Scrum is related to 5 processes
of MDevSPICE® when it is implemented fully (RQ2). Within the mapping process, we
also evaluated and calculated the coverage ratio of the MDevSPICE® base practices for
Scrum. Table 3, shows the coverage ratio for each mapped process. The coverage eval-
uation performed by one of the authors for base practices from a Scrum perspective,
was subjective, but peer reviewed by the other author. Therefore, depending on the
implementation details and perception of the methods, different coverage ratios than
we provided could be obtained. However, the purpose of giving this ratio is to provide
readers and practitioners with an indication of how much value is achieved with basic
Scrum implementation and how much needs to be done more from a regulatory per-
spective.
Table 3. Coverage of Mapped MDevSPICE® Processes from Scrum Perspective
Mapped MDevSPICE® Processes Coverage Ratios
1. PRO.1 Project Planning 100%
2. PRO.2 Project Assessment and Control 90%
3. ENG.1 Stakeholder Requirements Definition 55%
4. ENG.2 System Requirements Analysis 71%
5. DEV.1 Software Requirements Analysis 33%
Below, we discuss why processes #3, #4, and #5 in Table 3 did not have a full cov-
erage ratio and what additional practices need to be performed for compliance to med-
ical requirements (RQ4).
#3 ENG.1 Stakeholder Requirements Definition Process: (Coverage Ratio: 5 BPs
/ 9 BPs). The following base practices of ENG.1 are assumed to be achieved by the
product owner and the development team in product backlog grooming sessions:
ENG.1.BP1: Identify stakeholders, ENG.1.BP2: Obtain requirements, ENG.1.BP3:
Define constraints, ENG.1.BP6: Evaluate requirements, ENG.1.BP7: Agree on re-
quirements. However, the other base practices of this process need special attention
which are not addressed in Scrum.
For an IEC 62304 Class B type medical software, user interaction has to be defined
and evidence has to be provided. Based on the ENG.1.BP4: Define user interaction
base practice the following information has to be defined for a medical device:
– Intended medical indication, e.g. conditions(s) or disease(s) to be screened, moni-
tored, treated, diagnosed, or prevented; – Intended patient population, e.g. age, weight,
health, condition; – Intended part of the body or type of tissue applied to or interacted
with; – Intended user profile; – Intended conditions of use, e.g. environment including
hygienic requirements, frequency of use, location and mobility; and –Operating prin-
ciple.
In a product backlog grooming session, we may assume that all stakeholder require-
ments are specified. However, as part of the ENG.1.BP5: Identify critical requirements
practice of MDevSPICE®; it has to be ensured that health, safety, security, environment
and other stakeholder requirements and functions that relate to critical qualities and
shall address possible adverse effects of use of the system on human health and safety
are identified as well.
In medical device software development, every change on the product, whether it is
on the artifacts or the code has to be made in a controlled way. This is one of the major
contradictions between agile and the regulated worlds. For a change to be controlled, a
version control system should be in place and baselines established. This is referred to
in ENG.1.BP8: Establish stakeholder requirements baseline base practice. However,
a product backlog is a dynamic list which is continuously changing and no baselines
are taken over it.
The other major requirement in medical device software development is to build
traceability links between artifacts as this plays a significant role in defect management
and change management. This is referred to in ENG.1.BP9: Manage stakeholder re-
quirements changes. The purpose is to “Maintain stakeholder requirements traceability
to the sources of stakeholder need”. However, there is no specific emphasis on the de-
velopment of a traceability schema in Scrum method.
#4 ENG.2 System Requirements Analysis Process: (Coverage Ratio: 5 BPs / 7
BPs). We may assume that base practices: ENG.2.BP1: Establish system requirements,
ENG.2.BP3: Optimize project solution, ENG.2.BP4: Analyze system requirements,
ENG.2.BP5: Evaluate and update system requirements, ENG.2.BP7: Communicate
system requirements are performed in product backlog grooming sessions, as there are
mechanisms to achieve them. However, the following two base practices need to be
handled separately.
As part of ENG.2.BP2: Assign a safety class to the medical device based on the
regional regulations process, at the system requirements analysis phase, a safety class
has to be assigned to the product as the specific regulations apply based on the safety
class in order to prevent potential harm to human life. As mentioned also in base prac-
tice ENG.1.BP9, bilateral traceability between the stakeholder requirements and the
system requirements needs to be established as part of ENG.2.BP6: Ensure consistency
base practice.
#5 DEV.1 Software Requirements Analysis Process: (Coverage Ratio: 3 BPs / 9
BPs) We assumed that base practice, DEV.1.BP1: Define and document all software
requirements is partially achieved, as there are specific issues that needs to be addressed
for this BP. Based on FDA rules, software requirements have to be documented in a
software requirements specification document and this document should contain details
of the software functions.
It is important to determine the interfaces between the software requirements and
other elements of the operating environment such as third party software. This is achie-
ved as part of base practice, DEV.1.BP3: Determine the impact the requirements have
on the operating environment. At this stage, it is expected that the acceptance criteria
for the software tests are defined from software requirements (DEV.1.BP4: Develop
acceptance criteria for software testing based on the software requirements.) Scrum
does not have such a rule.
As mentioned above, consistency of system requirements to software requirements
has to be ensured. This is achieved through establishing and maintaining bilateral trace-
ability between system requirements and the software requirements (DEV.1.BP5: Ver-
ify all software requirements.)
The 7th base practice of DEV.1 requires establishing a baseline of software require-
ments and also providing communication of the software requirements. Due to use of
communication channels in Scrum, we feel that the second part of this base practice
can be achieved. However, the baseline of software requirements should also be added.
In medical device software development, special attention is given to risk analysis
and mitigation. With base practices, DEV.1.BP.9: Re-evaluate and maintain medical
device risk analysis and DEV.1.BP8: Establish and maintain risk control measures in
software requirements, it is ensured that risks regarding the software requirements are
identified and risk control measures are defined. Risk management should be a part of
daily or weekly Scrum review meetings.
Although we have mapped the Stakeholder, System and Software Requirements
Analysis processes with the product backlog grooming practice in Scrum, it is neces-
sary to ensure that distinction between these requirement types are clear, the traceability
links are established, and the changes made to them is managed.
In MDevSPICE®, there another process, ENG.4 Software Development Planning
includes very specific practices for regulatory requirements compliance. Some of these
base practices include assigning the software safety class of the software system, having
a software integration test plan, a verification plan, a software risk management plan
and configuration management plan. Although Scrum proposes effective ways to man-
age projects, these plans are not part of a basic Scrum method. Therefore, we assumed
that ENG.4 Software Development Planning is not covered with Scrum, even though it
is a “planning” process.
5 Conclusions
In this study, we evaluated if a Scrum implementation could meet the regulatory re-
quirements defined in MDevSPICE®, the software process assessment framework for
medical device software development. Scrum was selected due to its high recognition
and adoption in software development world. The research approach included the map-
ping of Scrum practices to MDevSPICE® processes and base practices. With this ap-
proach, we were able to define MDevSPICE® processes and base practices that could
be achieved in a basic Scrum implementation, more importantly the additional base
practices that have to be performed for ensuring safety and regulatory compliance.
We also identified the coverage ratio of MDevSPICE® processes from a Scrum per-
spective. Even though the coverage ratios are calculated from a subjective point of
view, they provide important information to readers and practitioners about which
MDevSPICE® processes are covered to what extent.
The significance of this study is that it presents a coverage analysis at the
MDevSPICE® base practice level which is very detailed and has never been performed
before. The coverage ratios showed the level of the gap between methods. The study
has also revealed conflicting practices such as “controlled change management over
continuous and dynamic change”. In addition, the discussions made around the addi-
tional practices that need to be performed, complete the missing pieces to ensure safety
and be successful over a regulatory audit in the medical device domain. The results of
this study also provide guidance us for the development of an agile integrated medical
device software development framework.
As future work, we will extend the mapping by adding XP, other agile methods
which propose a whole software development life cycle coverage such as Dynamic
Systems Development Method and scaling agile frameworks such as Disciplined Agile
Delivery and SAFE.
Acknowledgement. This research is supported by Science Foundation Ireland under
a co-funding initiative by the Irish Government and European Regional Development
Fund through Lero - the Irish Software Research Centre (http://www.lero.ie) grant
13/RC/2094. This research is also partially supported by the EU Ambient Assisted Liv-
ing project – Maestro.
References
[1] FDA. (15.05). Chapter I - Food and drug administration, department of health
and human services subchapter H - Medical devices, Part 820 - Quality system
regulation. Available:
http://www.accessdata.fda.gov/scripts/cdrh/cfdocs/cfcfr/CFRSearch.cfm?CF
RPart=820
[2] Directive 93/42/EEC of the European Parliament and of the Council
concerning medical devices, 1993.
[3] Council directive 90/385/EEC on active implantable medical devices
(AIMDD), 1990.
[4] Directive 98/79/EC of the european parliament and of the council of 27
october 1998 on in vitro diagnostic medical devices, 1998.
[5] Directive 2007/47/EC of the European Parliament and of the Council
concerning medical devices, 2007.
[6] M. Mc Hugh, O. Cawley, F. McCaffcry, I. Richardson, and X. Wang, "An
agile v-model for medical device software development to overcome the
challenges with plan-driven software development lifecycles," in Software
Engineering in Health Care (SEHC), 2013 5th International Workshop on,
2013, pp. 12-19: IEEE.
[7] P. Abrahamsson, O. Salo, J. Ronkainen, and J. Warsta, "Agile software
development methods: Review and analysis," ed: VTT Finland, 2002.
[8] K. Schwaber, "Scrum development process," in Business Object Design and
Implementation: Springer, 1997, pp. 117-134.
[9] K. Schwaber and J. Sutherland, Software in 30 days: how agile managers beat
the odds, delight their customers, and leave competitors in the dust. John
Wiley & Sons, 2012.
[10] K. S. Rubin, Essential Scrum: A Practical Guide to the Most Popular Agile
Process. Addison-Wesley Professional, 2012.
[11] S. Wolff, "Scrum goes formal: Agile methods for safety-critical systems," in
Proceedings of the First International Workshop on Formal Methods in
Software Engineering: Rigorous and Agile Approaches, 2012, pp. 23-29:
IEEE Press.
[12] B. Fitzgerald, K.-J. Stol, R. O'Sullivan, and D. O'Brien, "Scaling agile
methods to regulated environments: An industry case study," in Software
Engineering (ICSE), 2013 35th International Conference on, 2013, pp. 863-
872: IEEE.
[13] E. Ahmad, B. Raza, R. Feldt, and T. Nordebäck, "ECSS standard compliant
agile software development: an industrial case study," in Proceedings of the
2010 National Software Engineering Conference, 2010, p. 6: ACM.
[14] M. Kircher and P. Hofman, "Combining systematic reuse with Agile
development: experience report," in Proceedings of the 16th International
Software Product Line Conference-Volume 1, 2012, pp. 215-219: ACM.
[15] R. Faber, "Architects as service providers," IEEE software, vol. 27, no. 2,
2010.
[16] J. W. Spence, "There has to be a better way![software development]," in Agile
Conference, 2005. Proceedings, 2005, pp. 272-278: IEEE.