Highway/Bridge Construction Projectsin Centre County
Year 2019
Centre Region COG General ForumMarch 25, 2019
3/25/20191
State Bridge Projects
Local Bridge Projects
State Highway Projects
Municipal Projects
2019 Construction Projects in Centre County
SR 3036
Phoenix Rd.
Retaining Wall
SR 1002
Paving
I-99 Concrete
Patching
Gregg Twp.
T-419 Bridge
SR 3006, Routes 144, 150, 550,
SR 2002 Paving Projects SR 2018
Paving
Route 64
Paving
SEE
CENTRE REGION
PROJECTS SLIDE
SR 322
Potters Mills Gap
Section B06
SR 445
Bridge
SR 144
South Fork
Beech Creek Bridge
SR 144
Wallace Run
Bridge
SR 2005, 2012, 2014
Paving Projects
SR 2007
Bridges
Exit 161
WB Ramp
Worth Twp.
T-348 Bridge
Route 26
Lick Run and
SEDA-COG
JRA Bridges
33 locations
3/25/20192
1. I-99 Concrete Patching
2. Atherton St. Ramp Bridge over I-99
3. Valley Vista Dr. Turning Lanes
4. Valley Vista Dr. Shared Use Path
5. Atherton St. Drainage/Repaving
6. W. College Ave./Corl St.
Signal/Pedestrian Crossing
7. Bernel Rd. Repaving
8. E. College Ave./Elmwood St.
Signal/Pedestrian Crossing
9. E. College Ave./Clover Rd.
Intersection
10. Elmwood St. Bridge (in Lemont)
11. Atherton St./Route 45 Signal
Upgrade
2019 Construction Projects in the Centre Region
1
5
10
7
11
98
6
2
43
3/25/20193
Stakeholders
collaborating on
communications…
• PennDOT
• State College Boro
• Ferguson Twp.
• Penn State
• CATA
• CCMPO
3/25/20194
Intensive construction
project…not just a repaving
• Water lines
• Sewer lines
• Culvert replacements
• Stormwater lines
• Additional inlets
• New curbing
• Signal improvements
Pedestrian crossings in 2019…• Watch for directional signs• Cross at designated locations• May change day-to-day
3/25/20195
3/25/20196
Completed
Completed
Partial fundingon 2019 TIP
No fundingon 2019 TIP
Underconstruction
Utility work inSection 153
may begin in 2019!
Section 153
Park Avenue to Westerly Parkway
3/25/20197
Bridge Preservation Projects in the Centre Region
SR 3010 Elmwood Street
Bridge over Spring Creek
SR 3014 Atherton Street
Westbound Ramp
Bridge over I-99
Work begins April 5, 2019
Work begins Summer 2019
3/25/20198
Patton Township project
▪ Amblewood Way
▪ Oakley Drive
▪ Sandy Ridge Road
▪ Devonshire Drive
Completion mid-2019
Valley Vista Drive Turn Lanes – Patton Twp.
3/25/20199
Valley Vista Drive Shared Use Path
Ferguson and
Patton Townships
Tudek-Circleville Path
to Carnegie Drive
Completion late-2019
3/25/201910
Route 322 Potters Mills Gap
Section B06
Completion late 2020
3/25/201911
to Lamar
to Milesburg
I-80
Route 26Jacksonville Road
New traffic signalRamp queue metering
Extend WB ramp
Remove embankment
Westbound ramp safety improvements:▪ Install traffic signal▪ Ramp queue metering▪ Extend WB ramp▪ Remove embankment
Construction to be completed by AugustEst. cost = $1,047,000
I-80 Exit 161 (Bellefonte)
3/25/201912
PennDOT Online Resources
https://www.dot7.state.pa.us/OneMapor Google “PA One Map”
https://www.penndot.gov/RegionalOffices/district-2/ConstructionsProjectsAndRoadwork/Pages/default.aspx
or Google “PennDOT District 2”
3/25/201913
I-99 - Gray’s Woods Interchange to I-80 Exit 161
3/25/201914
Centre Regional Planning Agency814-231-3050
Tom Zilla - tzilla@crcog.netTrish Meek - tmeek@crcog.netGreg Kausch - gkausch@crcog.net
Centre County Planning & Community Development Office814-355-6791
Leslie Warriner - ljwarriner@centrecountypa.gov
www.ccmpo.net
CCMPO Staff Contacts
top related