Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 1
GUIDELINES ON
QUIETER CONSTRUCTION FUND
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 2
1. OBJECTIVE
1.1 The Quieter Construction Fund (QCF) is a funding scheme to support Singapore-
registered companies to adopt the use of quieter construction equipment, noise control
equipment and encourage innovative solutions to mitigate noise and hence, reduce the
impact of construction noise on sensitive premises to achieve a quieter living
environment.
1.2 ‘Equipment’ henceforth refers to individual or a group of quieter construction
equipment, noise control equipment and innovative solutions to mitigate noise at
construction or demolition sites.
2. ELIGIBILITY CRITERIA
2.1 To be eligible, the applicant must be a Singapore-registered company who is
a) Operating on existing or proposed construction site(s) also referred to as
‘Builder’; or
b) Supplying construction equipment for existing or proposed construction site(s)
also referred to as ‘Supplier’. (Refer to 3.5 for more details)
2.2 The above mentioned construction site(s) must be located less than 150 metres from
any hospital, home for the aged sick, residential building or other noise sensitive
premises.
2.3 Purchase or leasing of equipment from or to related companies is not supported.
2.4 Equipment which is required contractually by the developer (whether public or private)
is not supported under the QCF. Equipment that is in excess of the contractual
requirement can be considered. The applicant would have to declare that “the contract
for the Construction Project does not require the Applicant to procure or use quieter
construction equipment” in Part 5 of the Application Form.
3 EQUIPMENT REQUIREMENTS
3.1 The types of equipment that will be considered for support are listed in Annex A1.
(Note that the list of equipment shown in Annex A1 is not exhaustive)
3.2 The applicant has to show that the noise performance of the equipment meets
requirements listed in Annex A2. The noise performance of the equipment must be
measurable during inspection.
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 3
3.3 The supported equipment must be used at the approved construction site(s) and
according to the Terms & Conditions of the grant.
3.4 For applicants who are builders, the purchase or leasing of equipment must not be made
before submission of application.
3.5 For applicants who are suppliers, the purchase of equipment must not be made before
submission of application. Upon provisional approval from NEA, suppliers must
submit the proof of purchase to NEA within 1 month from the date of provisional
approval.
3.6 Purchase of used equipment will not be supported.
3.7 The same equipment or any of its components shall not have been granted the Quieter
Construction Fund or other cash reimbursement or incentives from the Government or
other Government agencies (e.g. BCA’s Mechanisation Credit)
4 FORM OF ASSISTANCE
4.1 The funding support is shown below:
Equipment Category Purchase / Lease Cost Funding %
Quieter Construction
Equipment (purchase)
≤$100,000 per equipment Up to 50%, capped at
$30,000 per equipment
>$100,000 and ≤$200,000
per equipment
Up to 30%, capped at
$50,000 per equipment
>$200,000 per equipment Up to 25%, capped at
$150,000 per equipment
Quieter Construction
Equipment (leasing)
≤$30,000 per equipment Up to 50%, capped at
$9,000 per equipment
>$30,000 per equipment Up to 30%, capped at
$20,000 per equipment
Purchase & Setting up
of Noise Control
Equipment
≥$5,000per Project Site Up to 50% per Project
Site
Purchase & Setting up
of Innovative Solution
≥$5,000per Project Site Up to 50% per Project
Site
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 4
4.2 All disbursements will be made on a reimbursement basis to a single account of the
applicant only.
4.3 The minimum total investment amount per application must be $5,000 or above.
4.4 For applicants who are builders operating on construction site of project cost ≤ $50
million, the total funding disbursed to the project site is capped at $150,000, or 5% of
the project contract value, whichever is lower.
4.5 For applicants who are builders operating on construction site of project cost > $50
million, the total funding disbursed to the project site is capped at $200,000.
4.6 For applicants who are suppliers, the total funding disbursed to an applicant, being a
supplier of equipment, is capped at $150,000, over 2 years.
4.7 All costs which are not relevant to the above equipment category are not supported (i.e.
cost of disassembly, maintenance, operations and internal manpower etc). GST and
COE are not supported. The costs for Professional Engineer’s services as well as site
sound measurement report for perimeter noise barrier and noise enclosure are
supported.
5 QUALIFYING PERIOD
5.1 The Qualifying Period refers to the period separately defined for builders and suppliers
below whereby the following conditions listed below have been carried out in order for
support to be granted.
5.2 The Qualifying Period for builders refers to the period not more than 6 months starting
from the date of application to such time when all of the following must have been
carried out, in order for support to be granted:
i. Completed the purchase or lease of approved equipment; and
ii. Implemented the equipment at the approved construction site; and
iii. Informed and facilitated NEA officer for site inspection; and
iv. Conducted a sound measurement of the equipment at the approved construction
site.
5.3 The Qualifying Period for suppliers refers to the period not more than 6 months
starting from the date of purchase of equipment to such time when all of the following
must have been carried out, in order for support to be granted:
i. Imported the equipment into Singapore
ii. Informed and facilitated NEA officer for equipment inspection; and
iii. Conducted a sound measurement of the equipment; and
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 5
iv. Leased the equipment to a construction site located less than 150m from any
hospital, home for the aged sick, residential building or other noise sensitive
premises
Refer to Annex C for requirements on site sound measurement report
5.4 Support will not be granted if the proposed equipment is
i. Purchased/leased, before the date of application; or
ii. Delivered and received in Singapore by the applicant before the date of
application; or
iii. Purchased / leased after the Qualifying Period.
5.5 The date on vendor's invoice is deemed to be the date of purchase of the proposed
equipment / machinery.
6 POSSESSION PERIOD
6.1 During the Possession Period, the applicant shall not:
i. use the equipment for unintended purposes or at non pre-approved sites;
ii. lease or lend the equipment to a party (unless for applicants who are
suppliers);
iii. sell the equipment;
iv. allow the equipment to lose its intended function or be damaged beyond
repair;
v. scrap/dispose the equipment; or
vi. allow or be a party in bringing the equipment out of Singapore.
6.2 It is the applicant’s responsibility to take care of the equipment, and shall be solely
responsible for any losses. Lost / Stolen of equipment shall not entitle the applicant to
claim under the scheme.
6.3 Every application will be evaluated individually for noise reduction impact. The same
equipment may be approved for one application but rejected for another application.
6.4 The Terms & Conditions attached to the Letter of Offer apply.
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 6
7 CLAIM
7.1 The applicant should submit for claims using the prescribed claim form. The applicant
should submit one consolidated claim application for cash purchase of equipment.
7.2 For approved funding of $50,000 or higher per project site for purchase, and approved
funding of $10,000 or higher per project site for leasing only, external audit
certification on qualifying expenses of the equipment must be submitted.
7.3 All claims must be submitted within the stipulated Claim Period.
8 HOW TO APPLY
8.1 Applicants are encouraged to contact the Fund Secretariat to determine the eligibility of
their proposed equipment before submitting an application.
8.2 Applications are to be made on the prescribed application form, with all necessary
supporting documentation duly attached. The application and supporting documentation
may be submitted in soft copies. The soft copies should be emailed to
nea_qcf@nea.gov.sg, and entitled in the format “QCF Application – [Company Name]”
All information submitted will be held in the strictest confidence.
For more information, you may refer to the FAQs or contact us via the following email
or phone number.
Email: nea_qcf@nea.gov.sg
Tel: 6731 9834
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 7
ANNEX A1 – LIST OF SUPPORTED EQUIPMENT (List not exhaustive)
Category Equipment Name Photographs for Reference
Quieter Construction
Equipment
*(see notes for
specific equipment)
Jack-in piling
‘Silent’ sheet piling
Concrete crusher machine
Electrical rebar bender & cutter
Electrical concrete vibrator /
poker
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 8
Battery powered floodlights
(without use of generators)
Noise Control
Equipment
Perimeter noise barrier
Noise curtain containing sound
absorbing material
Plant noise enclosure
Machine noise enclosure
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 9
Rotary head enclosure
Acoustic silencer or muffler
Vibration absorption, isolation or
damping device
Innovative Solution Crack inducer
Modified Auger bucket
Insulated Kelly Bar
Active Noise Control device
*Notes for specific equipment:
1) For leasing of piling machines
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 10
Only the leasing cost of the machine would be claimable. The cost of the piling materials is not
claimable. The applicant should provide an itemized quotation stating the breakdown of the total cost
of the piling contract.
2) For purchasing/leasing of excavators with noise reduced engines
Application must be accompanied with localized noise barriers. The localised barriers must be of
sufficient dimension to mitigate noise generated during the operation of the excavator. The cost of the
localised noise barriers is also claimable.
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 11
ANNEX A2 – PERFORMANCE REQUIREMENTS
Equipment Category Performance Requirements
Quieter Construction
Equipment
At least 5 dB(A) quieter than 2 other equipment
meant for the same work commonly used in
Singapore.
Noise Barrier & Enclosure Comprises acoustic absorbing material
Designed and installed to ensure effectiveness of
noise reduction
Tested and reported according to the following
standards or equivalent international standards:
a) ISO 10140-2 : 2010 Acoustics -- Laboratory
measurement of sound insulation of
building elements -- Part 2: Measurement of
airborne sound insulation; and
b) ISO 717-2 : 2013 Acoustics -- Rating of
sound insulation in buildings and of
building elements -- Part 1: Airborne sound
insulation.
or
a) ASTM E90 Standard Test Method for
Laboratory Measurement of Airborne
Sound Transmission Loss of Building
Partitions and Elements; and
b) ASTM E413 Classification for Rating
Sound Insulation.
For noise panels:
a) Achieve a Sound Transmission Class of 20
b) Perimeter noise barrier: Achieve a
minimum noise reduction of 10 dB(A) for
specific construction work as compared to
without the noise barrier, measured at the
same receiver point within the acoustic
shadow of the noise barrier. The perimeter
noise barrier, if used as site hoarding,
should meet and surpass BCA’s
requirements for protective hoarding in
terms of minimum height.
c) Noise enclosure: Achieve a minimum noise
reduction of 15 dB(A) for specific
construction work, as compared to without
the noise enclosure, measured at the same
distance from the noise source.
For noise curtains:
a) Achieve a Sound Transmission Class of 15
b) Noise curtains: Achieve a minimum noise
reduction of 5 dB(A) for specific
construction work, as compared to without
the noise curtain, measured at the same
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 12
distance from the noise source. The noise
curtains should ONLY BE USED to
mitigate noise as a localized barrier or at the
façade of a superstructure and NOT as a
substitute for the parameter noise barrier on
the site hoarding.
Innovative Solution Able to achieve a minimum noise reduction of 5
dB(A) for a specific construction work where the
Innovative Solution is implemented
ANNEX B – LIST OF NON-SUPPORTED EQUIPMENT
Equipment which normally does not cause construction noise or not meant to mitigate
construction noise will not be supported. Items such as the following will not be supported:
Noise meters
Security system
Environmental monitoring equipment
Computer hardware and software
Public relation programmes
Consultancy studies
Equipment that are quieter due to smaller dimensions or power
Guidelines on Quieter Construction Fund
Updated Jan 2017 Page 13
ANNEX C – REQUIREMENTS FOR SITE SOUND MEASUREMENT REPORT
Applications that are offered the grant will be required to conduct site sound
measurement to prove that the implemented equipment meets performance requirements in
Annex A2. Only equipment that meets the performance requirements will be supported. The
site sound measurement must be carried out during the Qualifying Period.
1) Quieter construction equipment
The applicant must facilitate NEA officers for an equipment inspection during the
Qualifying Period.
2) Noise control equipment – Perimeter noise barrier, noise enclosures and noise curtains
The site sound measurement report must be prepared by an independent company and
with reference to ISO 10847 Acoustics – In-Situ Determination of Insertion Loss of Outdoor
Noise Barriers of All Types, or other equivalent international standards, subject to NEA’s
approval. The site sound measurement must be conducted in the presence of NEA officers.
The applicant must submit the report before or during the submission of Claim form.
3) Innovative solutions
The applicant must facilitate NEA officers for an equipment inspection during the
Qualifying Period. For specific innovative solutions such as active noise control system, a
site sound measurement report must be prepared by an independent company with reference
to a relevant ISO or other equivalent international standard, subject to NEA’s approval. The
site sound measurement must be conducted in the presence of NEA officers. The applicant
must submit the report before or during the submission of Claim form.