GREAT WESTERN
1
ELECTRIFICATION
Wales
Alastair Byers – Consents Manager, Wales on behalf ofEssel Hagan – Highways & Utilities Co-ordinator
Bridge Works in Wales
Wales 2
Bridge Works in Wales
Updates: May 2014 to January 2016
Farm Road, Caldicot Station [SWM2-15-55]
Reconstruction E: 347498 N: 187597
• Proposed Start:
May 2014
• Proposed Finish:
August 2014
Wales 33
August 2014
• C3 Budget Estimates
received from BT.
C3 requested from
WPD and Wessex
Water.
Church Road [SWM2-150-15]
Reconstruction & Track Lower E: 344031 N: 187158
• Proposed start:
October 2014
Wales 44
• Proposed End:
January 2015
• C3 requested from
Welsh Water.
Maesglas Road [SWM2-160-15]
Reconstruction E: 330313 N: 185880
• Proposed start:
November 2014
• Proposed End:
Wales 55
• Proposed End:
March 2015
• C3s requested from
Wales & West, WPD
and Welsh Water.
Parsons FB [SWM2-150-28]
Reconstruction E: 343770 N: 187043
• Proposed start:
December 2014
• Proposed End:
Wales 66
• Proposed End:
March 2015
• C3 requested from
Welsh Water.
The Ramp [SWM2-150-42]
Reconstruction E: 343507 N: 186930
• Proposed start:
December 2014
• Proposed End:
Wales 77
• Proposed End:
March 2015
• C3 received from
Wales & West and
BT. Awaiting
responses from WPD
and Welsh Water.
Llandavenny Road [SWM2-152-01]
Reconstruction E: 341142 N: 187002
• Proposed start:
December 2014
• Proposed End:
Wales 88
• Proposed End:
March 2015
• C3s received from
BT. Awaiting
responses from WPD
and Welsh Water.
Somerton Road [SWM2-156-70]
Reconstruction E: 333359 N: 187740
• Proposed start:
December 2014
• Proposed End:
Wales 99
• Proposed End:
March 2015
• C3 received from BT.
Awaiting responses
from Wales & West,
WPD and Welsh
Water.
Whitewall FB [SWM2-151-00]
Reconstruction E: 342774 N: 186863
• Proposed start:
December 2014
• Proposed End:
Wales 1010
• Proposed End:
March 2015
• C3s requested from
WPD and Welsh
Water.
Mardy Road [SWM2-167-10]
Reconstruction E: 322291 N: 178820
• Proposed start:
January 2015
• Proposed End:
Wales 1111
• Proposed End:
March 2015
• C3s: Requested from
WPD, and Welsh
Water. Received
from Vodafone and
BT.
Rogiet Road [SWM2-148-68]
Reconstruction E: 346125 N: 187534
• Proposed start:
January 2015
• Proposed End:
Wales 1212
• Proposed End:
April 2015
• No services
Undy Halt FB [SWM2-150-52]
Reconstruction E: 343346 N: 186888
• Proposed start:
January 2015
• Proposed End:
Wales 1313
• Proposed End:
April 2015
• C3 requested from
WPD and Welsh
Water.
Chepstow Road [SWM2-157-71]
Reconstruction E: 331903 N: 188428
• Proposed start:
January 2015
• Proposed End:
Wales 1414
• Proposed End:
April 2015
• C3s: Requested from
Wales & West, WPD,
Welsh Water.
Received from BT.
Bridge Street [SWM2-158-62]
Reconstruction E: 330695 N: 188079
• Proposed start:
January 2015
• Proposed End:
Wales 1515
• Proposed End:
April 2015
• C3 received from BT
and Wales & West.
Awaiting responses
from, WPD and
Welsh Water.
Tunnel Terrace [SWM2-158-64]
Reconstruction E: 330695 N: 188079
• Proposed start:
February 2015
• Proposed End:
April 2015
Wales 1616
April 2015
• C3 received from BT.
Awaiting responses
from WPD and Welsh
Water. Wales & West
confirms LPs can be
protected.
Cuckoo Bridge [SWM2-160-77]
Reconstruction E: 330200 N: 184652
• Proposed start:
February 2015
• Proposed End:
Wales 1717
• Proposed End:
May 2015
• C3 received from BT.
Beresford/Moorland Road [SWM2-168-53]
Reconstruction E: 320367 N: 177317
• Proposed start:
February 2015
• Proposed End:
Wales 1818
• Proposed End:
May 2015
• C3s requested from
WPD, Welsh Water,
and Wales & West.
Received from BT.
Newport Station FB [SWM2-158-43]
Reconstruction E: 330901 N: 188348
• Proposed start:
April 2015
• Proposed End:
Wales 1919
• Proposed End:
June 2015
• C3 requested from
Welsh Water.
Maerdy Farm [SWM2-162-28]
Reconstruction E: 328625 N: 183157
• Proposed start:
April 2015
• Proposed End:
Wales 2020
• Proposed End:
July 2015
• No service on this
Bridge.
Adamsdown Place [SWM2-169-37]
Reconstruction E: 322291 N: 178820
• Proposed start:
July 2015
• Proposed End:
Wales 2121
• Proposed End:
October 2015
• C3s requested from
WPD and Welsh
Water.
Wentloog Road [SWM2-166-57]
Demolition E: 322890 N: 179107
• Proposed start:
October 2015
• Proposed End:
Wales 2222
• Proposed End:
December 2015
• C3s requested from
WPD, Welsh Water
and received from
BT.
Hawse Lane [SWM2-162-68]
Reconstruction E: 327965 N: 182684
• Proposed start:
October 2015
• Proposed End:
Wales 2323
• Proposed End:
January 2016
• No service on this
Bridge.
Green Lane / Heol Las [SWM2-164-57]
Reconstruction E: 325533 N: 180927
• Proposed start:
October 2015
• Proposed End:
Wales 2424
• Proposed End:
January 2016
• No service on this
Bridge.
Trowbridge Road [SWM2-166-27]
Reconstruction E: 323408 N: 179391
• Proposed start:
October 2015
• Proposed End:
Wales 2525
• Proposed End:
January 2016
• C3 requested from
WPD.
Summerway [SWM2-163-48]
Jacking E: 326982 N: 181976
• Proposed start:
November 2015
• Proposed End:
Wales 2626
• Proposed End:
February 2016
• No service on this
Bridge.
Pellett Street [SWM2-169-72]
Reconstruction E: 318887 N: 176068
• Proposed start:
November 2015
• Proposed End:
Wales 2727
• Proposed End:
February 2015
• C3s requested from
WPD and Welsh Water.
Wales & West service
to be protected.
Cardiff Road [SWM2-159-52]
Reconstruction E: 330233 N: 186754
• Proposed start:
December 2015
• Proposed End:
Wales 2828
• Proposed End:
March 2016
• C3 received from BT
and Wales & West.
Awaiting responses
from WPD and Welsh
Water.
Splott Road [SWM2-169-07]
Reconstruction E: 319961 N: 176786
• Proposed start:
January 2016
• Proposed End:
Wales 2929
• Proposed End:
April 2016
• C3s requested from
WPD, Welsh Water.
Received from BT
and Wales & West.
Parapet Works – provisional dates
BEFORE AFTER
Wales 30
BEFORE AFTER
• Parapet compliance works.
• Contractors to be appointed early 2014 (to be confirmed).
• Following the appointment of the Contractors we would expect a provisional programme of works and traffic
management proposals to have been developed, where we would discuss the programme and the traffic
management requirements for each of the structures with the various Local Authorities.
• Starting works in mid 2014 and completing all GWML structures within a 12-18 month period.
• Parapet compliance works will take place on 13 Welsh structures.
Occupation Bridge No.10363
Occupation Bridge No.10419
Accomodation Bridge No.10453
King Grove Lane Farm Bridge No.10477
Parapet works
Severn Tunnel Junction Footbridge No. 14861
Eastern Access Road No. 15162
Spytty Road Bridge No. 15603
Docks Access Road A4042 No. 16018
Wales 31
King Grove Lane Farm Bridge No.10477
Dodington Road-Lilliput-No.10520
Overbridge Bridge No.10632
Halfpenny FB No.10826
Dragon Road Bridge No.11015
Docks Access Road A4042 No. 16018
Penstaff Brachdy Lane No. 16742H
Marshfield Road No. 16370
Foxes Court No. 16167
CONTACT DETAILS
Alastair Byers Consents Manager, Wales
E: alastair.byers@networkrail.co.uk M: 07790 395381
Essel Hagan
Wales 32
Essel Hagan Highways & Utilities Coordinator
E: essel.hagan@networkrail.co.uk M: 07932 047870
Margaret BurgessWestern Highways Interface Advisor
E:margaret.burgess@networkrail.co.uk