GREAT LAKES AND OHIO RIVER DIVISIONCONSTRUCTION ROUNDTABLE

LTC Sonny AvichalCommander, Nashville District5 - 6 December 2019

2

AGENDA

• ASSIGNED MISSON/ PROGRAM (NAVIGATION/HYDROPOWER)

• DISTRICTS WITH MISSION• PROJECTED WORK

3

RIVER NAVIGATION

• LRD operates over 2,500 miles of navigable waterways • Workload includes maintenance, repair, rehabilitation and

replacement of lock and dam facilities • Heavy civil construction in a marine environment• Maintenance of shipping traffic during construction

4

DISTRICTS WITH INLAND RIVER NAVIGATION MISSION

DISTRICT CDR DDE POC Name POC #

Huntington COL Evers Mike Keathley Eileen Hodges 304-399-5632

Louisville COL Gant Linda Murphy Tim Fudge 502-315-6731

Nashville LTC Avichal Patricia Coffey Diane Parks 615-736-7273

Pittsburgh COL Short Lenna Hawkins

Kathy Griffin 412-395-7234

5

Lock Chamber - $240MAwarded: Sep 2017Earliest Comp: Jun 2023

Current

Future

Approach Walls & DecommissioningAward scheduled: Sep ’21$100M - $250M: IFB

Site RestorationAward scheduled: Sep ’23$5M - $10M: IFB

CHICKAMAUGA LOCK REPLACEMENTFUTURE CONTRACTS

6

Lock & Associated Facilities $1,006MTVA Transmission Towers 13MP & L Railroad 97MHwy 62 and other roadways 100M

Total $1,216M

$485M Exp thru Sep 2019 = 40% complete

Downstream Lock Monoliths $250M to $500MIFB Award – July 2021

Approach Walls $25M to $100MIFB Award – Sept. 2022

KENTUCKY LOCK ADDITIONFUTURE CONTRACTS

Site Development$1M to $5MIFB Award – Sept. 2022

7

OLMSTED LOCK AND DAMFUTURE CONTRACTS

Future Contract (all IFB) Ready to Advertise Scope Range

Demolition L&D 53 Phase II 1-Jun-20

Demolition of remaining dam components near the KY bank (Bear Traps and Fixed Weir) and reamining sections of the 600' lock chamber on the IL bank.

$10 –25M

Landside Demo L&D 52 and 53 1-Feb-20

Demolition of remaining landside structures at these two locations. < $2M

County Road Resurfacing 1-Feb-20 Resurface county road from project site to IL Highway 37 < $1MResident Office Conversion 1-Jun-20 Convert Resident Office to storage warehouse. < $1MRefurbish Bulkheads 1-Feb-20 Refurbish Maintenance Bulkheads located at Smithland < $1M

D/S Highwater Electrical 1-Feb-20Install electrical service in downstream harbour area for use during highwater events < $1M

U/S Harbor Access 1-Feb-20Construct tower and ramp access from shore to harbor area < $3M

Abutment Blanks 1-Feb-20Construct two wicket blanks to be used in place of the first and last wickets adjecent to the abutments < $1M

Final Site Restoration 1-Jun-20 Complete restoration of the construction site < $3M

8

REGIONAL NAVIGATION FY20, FY21 & FY22 FORECAST

Monongahela Lock and Dam 3Remove Structure and Install

Mod. Spur Dikes>$10M

Monongahela Pool 2 ClearingTBD

$1M-$5M

Kentucky LockConduit Repair$250K-$500K

Downstream Lock Monoliths

>$10MSite Development

$1M-$5MApproach Walls

>$10MWilson Lock

Electrical Rehab Upper Boom Wall and Light Poles

$250K-$500K

Pike Island Lock and DamRiver Wall Mon. 33/34 Repair

$500K-$1M

Chickamauga LockApproach Walls and Decomm.

>$10MSite Restoration

FY23$5M-$10M

Olmsted Lock and DamDemo L&D53 Phase II

>$10MDemo L&D52 landside

<$2MResurface roadway

<$1MConvert R.O. to

warehouse<$1M

Refurb. Maint. Bulkheads<$1M

D/S Harbor Elec.<$1M

Tower & Ramp Access<$3M

Wicket Blanks<$1M

Site Restoration<$3M

Dashields Lock and DamInstall Waterway Booms

$1M-$5MWaterway Dam Signage

$1M-$5M

Ft Loudoun LockHVAC for OPS Bldg.

$100K-$250K

9

RIVER NAVIGATION FORECASTLocation Requirement Year FAR Range

Kentucky Lock, Grand Rivers, KY Conduit Repair 2020 $250K - $500K

Wilson Lock, Florence, AL Electrical Rehab Upper Boom Wall & Light poles from main lock crossover tunnel 2020 $250K to $500K

Ft Loudoun Lock, Lenoir City, TN HVAC Installation for Operation Bldg. 2020 $100K to $250K

Kentucky Lock, Grand Rivers, KYDownstream Lock Monoliths 2020 >$10MSite Development 2022 $1M-$5MApproach Walls 2022 >$10M

Chickamauga Lock, Chattanooga, TN Approach Walls and Decommissioning 2021 >10MSite Restoration 2023 $5M-$10M

Olmsted Lock & Dam, KY & IL

Demolition of remaining L&D 53 Phase II components 2020 >$10MDemolition of remaining L&D 52 landside structures 2020 <$2MResurface county road from project site to IL HWY 37 2020 <$1MConvert Resident Office to warehouse 2020 <$1MRefurbish maintenance bulkheads at Smithland 2020 <$1MInstall electrical service in downstream harbor for highwater use 2020 <$1MConstruct tower and ramp access from shore to harbor area 2020 <$3MConstruct two wicket blanks 2020 <$1MComplete restoration of the construction site 2020 <$3M

Monongahela Lock and Dam 3 Remove structure to streambed elevation; install modified spur dikes 2021 >$10MMonongahela Pool 2 Clearing Removal of vegetation flooded by pool raise; may be Small Business TBD $1M-$5M

Dashields Lock & Dam, Coraopolis, PA Install waterway booms 2020 $1M-$5MWaterway dam signage 2020 $1M-$5M

Pike Island River Wall, Wheeling WV Repair monoliths 33/34 crack 2020 $500K-$1M

10

HYDROPOWER

• USACE is the largest renewable energy producer in the nation at 25% of hydropower

• LRD operates 10 hydroelectric generation plants• Workload includes repair, replacement and modernization

of aging equipment• Electrical / Mechanical manufacture and construction• Units have not been fully disassembled since installation

11

DISTRICTS WITH HYDROPOWER MISSION

DISTRICT CDR DDE POC Name POC #

Detroit LTC Turner Scott Thieme Marie Strum 313-226-6444

Nashville LTC Avichal Patricia Coffey

Diane Parks 615-736-7273

12

CENTER HILL DAM AND POWER PLANT

• Average equipment age – 60 years• Declining availability, reliability, efficiency• Need for rehab and modernization• Replace turbine runners, rewind generators

• Improved efficiency and reliability• Improved water quality• Increased capacity

13

Barkley Intake and Spillway Crane

Replace Between $5M and

$10M

Old Hickory Main Power Transformer Supply

Between $1-5M

Old Hickory Turbine Generator Rehab

Between $25M - $100M

Barkley Turbine Generator Rehab

Between $25M -$100M

Barkley Main Power Transformer Install

Between $1M and $5M

Wolf Creek Main Power Transformer

SupplyBetween $1M-$5M

Wolf Creek Main Power Transformer

InstallBetween $1-5M

Cheatham Medium Voltage Cables Replacement

Between $1M-$5M

Center Hill Medium Voltage Cables Replacement

Between $1M- $5M

Cordell Hull Excitation Replacement/Excitation

Single Award Task Order Contract

Between $1M - $5M

Old Hickory Main Power Transformer

InstallBetween $1-5M

REGIONAL HYDROPOWER FY20, FY21 & FY22 FORECAST

Sault Ste. Marie Refurbish

Overhead Bridge Crane

Old Hickory Excitation Replacement/Excitation SATOC Task OrderBetween $1M - $5M

Sault Ste. Marie Replace Rails for Overhead Bridge

Crane

Sault Ste. Marie Replaced Potable

Water System

Sault Ste. Marie Replace Medium Voltage Circuit

Breaker

14

REGIONAL HYDROPOWER FORECASTLocation Requirement Year FAR Range

Barkley Dam, Grand Rivers, KY

Turbine and Generator Rehab: 4 Kaplan Runners (Uprate), Rewind 3 Generators 2020 $25M-$100MMain Power Transformer Install 2020 $1M-$5M165-ton Intake Gantry Crane Replacement 2020 $5M-$10MPowerplant HVAC Replacement 2020 $1M-$5M

Cheatham Dam, Ashland City, TN Medium Voltage Cables 2022 $1M-$5M

Center Hill Dam, Lancaster, TN Medium Voltage Cables 2022 $1M-$5M

Cordell Hull Dam, Carthage, TN Excitation System Replacement - 3 Units, Supply and Install, Rotating to Static 2019 $1M-$5M

Old Hickory Dam, Old Hickory, TN

Excitation Replacement - 4 Units, Supply and Install, Rotating to Static 2020 $1M-$5MMain Power Transformer Supply 2@13.2/69 kV, 100 MVA Three-Phase Xfrmrs 2019 $1M-$5MMain Power Transformer Install - Includes relocation from existing yard 2021 $1M-$5MTurbine and Generator Rehab - 4 Kaplan Runners, 3 Generator Rewinds 2022 $25M-$100M

Wolf Creek Dam, Somerset, KY

Main Power Transformer Supply 2021 $1M-$5MMain Power Transformer Install 2022 $1M-$5M

Center Hill Dam, Lancaster, TN Powerplant HVAC Replacement 2019 $1M-$5M

J Percy Priest Dam Hydropower Plant, Nashville, TN

Replace Breakers and Motor Control Centers 2020 $250K - $500K

St. Marys Falls Canal Hydroelectric Plant (Sault Ste. Marie, MI)

Replace rails for an overhead bridge crane 2020 $250K-$500KRepair / refurbish an overhead bridge crane 2021 TBDReplace potable water system 2021 TBDReplace Medium Voltage Circuit Breaker 2022 TBD