Glenmore LandfillProposed Fill PlanOpen House - February 21, 2017
Fill Plan Peak Design N
Quail Ridge
Fill Plan Peak DesignFill Plan Peak DesignN
UBCO
Fill Plan Comparisons2008 Comprehensive Site
Development Plan2017 Peak
Glenmore Road
Quail Ridge Quail Ridge
Glenmore Road
New Peak Design Benefits
Increased landfill volume and life expectancy Max. capacity expectancy shifts from 2075 t0 2100
Minimizes user fee increases If we needed to move to alternate disposal method (i.e.
shipping waste out of region) fees would increase substantially
Economic Additional billion dollars worth of airspace
Would not affect smell or noise levels
New Peak Design Benefits (cont.)
No major costs associated with shift to new fill plan Would only require minor changes to infrastructure
Visual impact would be minimized as landfill grows Progressive closure: side slopes would be revegetated as the
landfill grows in order to reduce aesthetic impacts. Blends into natural terrain of surrounding Tutt Mountain and
Bredin Hill
More flexibility City Council would have the option to adjust and slow
landfill growth at any time. The 20 meter elevation increase does not have to be fully
realized, but gives City Council’s of the future the option.
Leachate Lift StationAeration Treatment
Air Pollution Control System
Pumped to the Sanitary Sewer System
Leachate Lift Station
Emergency Backup Leachate Discharge Force main to Quail Ridge
Leachate Lift Station
Leachate Management
Landfill Gas CaptureIn Association with FortisBC Gas
2017
FlareBiogas Processing Plant
Moisture Separation & Blowers
Glenmore LandfillOpen House2017
Recently Completed Projects
Administrative Building
Completed in 2014 with innovative & sustainable features
New Lift Station
Pumps offsite away from Quail Ridge and includes
Leachate Pollution Control System
Landscaping
Additional trees planted on John Hindle Drive to provide
visual screening & environmental enhancement
Unattended Scale Terminals
For High Frequency Haulers
Reduces wait times for all customers
Wheel Wash (MobyDick)
Removes mud from vehicles preventing it from
leaving the site
Glenmore LandfillOpen House2017
2017 Enhancement Projects
Electronic Sign
Improved communication
& information to all haulers
New Website
Improvements on information
and instructions
Camera to show if there is a lineup
Leachate Recirculation (Phase 1)
Recirculation of leachate within the landfill will increase
the decomposition of the waste and increase production of
landfill gas
Landscaping
Future plantings to occur on John Hindle & Glenmore Road
Glenmore LandfillOpen House2017
Proposed Changes for Receiving Areas
Non Organics
Org
anic
s
Reduction in distance to drop off area
Improved drop off area
Traffic volume reduction by separating drop off areas
Improve efficiencies process and maintenance
Long term project(2018-2025)