Functional Performance: Tools, Rigor and Collaboration

David Sellers, Senior EngineerFacility Dynamics Engineering

21st National Conference on Building Commissioning

AIA Quality Assurance

The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

21st NCBC Conference

Presentation Description

This presentation uses a case study format to explore functional testing in an existing building commissioning process. Specifically, a functional test is developed to assess the thermal flywheel potential of a small chilled water system. The results are then used to develop control system program modifications that allow a short cycling problem to be resolved while still providing the required environmental conditions inside the facility.

21st NCBC Conference

At the end of this session, participants will be able to:

1. Understand the difference between a functional testing process in an existing building commissioning environment vs. a new construction environment

2. Understand that there can be a hierarchy to a functional testing process

3. Understand the key elements associated with developing a functional test

4. Understand how functional testing can be used as a diagnostic tool in an existing building commissioning process

5. Understand how a functional test can be used to gather useful data in an existing building commissioning process

Learning Objectives

21st NCBC Conference

The Path to Selecting Equipment and Systems

Operating Requirements

Heat Transfer Equipment Selections

Process Parameters

System Configuration

Owner’s Project

Requirements

Distribution Equipment Selections

Installation Documents

Assembled Building

Physical Configuration

Loads

Construction Project

FUNCTIONAL TESTING IN EXISTING BUILDINGS 5

The New Construction Perspective on Functional Testing

Operating Requirements

Heat Transfer Equipment Selections

Process Parameters

System Configuration

Owner’s Project

Requirements

Distribution Equipment Selections

Installation Documents

Assembled Building

Physical Configuration

Loads

Construction Project

FUNCTIONAL TESTING IN EXISTING BUILDINGS 6

Generally speaking, successful completion of  everything inside the red dotted line is required for system acceptance

Testing Hierarchy;More than Balancing Man Power

Commission Supporting 

Utility Systems

Verify Prestart Checks & Startups

Verify Control Wiring and Calibration

Verify Control Programming

Complete Equipment 

Safety Testing

Component Factory Startups

Component Startups

Sub‐assembly Factory Startups

Sub‐assembly Startups

Verify Safeties with Prime 

Mover Off‐line

Start‐up Prime Mover (Pump, 

Fan, etc.)

Test Component Controls

Test System Level Control Functionality

Test Building Level Control Functionality

Begin Normal Operations

Run Trend Analysis;  Fine Tune Systems

Seasonal and Warranty Testing

Begin Ongoing Cx

Component Level Testing

System Level Testing

Each utility system can have a testing hierarchy that is similar to this, much of which must be complete before the supporting system can be tested

7

Generally speaking, successful completion of  everything inside the red dotted line is required for system acceptance

Testing Hierarchy;More than Balancing Man Power

Commission Supporting 

Utility Systems

Verify Prestart Checks & Startups

Verify Control Wiring and Calibration

Verify Control Programming

Complete Equipment 

Safety Testing

Component Factory Startups

Component Startups

Sub‐assembly Factory Startups

Sub‐assembly Startups

Verify Safeties with Prime 

Mover Off‐line

Start‐up Prime Mover (Pump, 

Fan, etc.)

Test Component Controls

Test System Level Control Functionality

Test Building Level Control Functionality

Begin Normal Operations

Run Trend Analysis;  Fine Tune Systems

Seasonal and Warranty Testing

Begin Ongoing Cx

Component Level Testing

System Level Testing

Each utility system can have a testing hierarchy that is similar to this, much of which must be complete before the supporting system can be tested

8

Mostly Forced Response Testing

Generally speaking, successful completion of  everything inside the red dotted line is required for system acceptance

Testing Hierarchy;More than Balancing Man Power

Commission Supporting 

Utility Systems

Verify Prestart Checks & Startups

Verify Control Wiring and Calibration

Verify Control Programming

Complete Equipment 

Safety Testing

Component Factory Startups

Component Startups

Sub‐assembly Factory Startups

Sub‐assembly Startups

Verify Safeties with Prime 

Mover Off‐line

Start‐up Prime Mover (Pump, 

Fan, etc.)

Test Component Controls

Test System Level Control Functionality

Test Building Level Control Functionality

Begin Normal Operations

Run Trend Analysis;  Fine Tune Systems

Seasonal and Warranty Testing

Begin Ongoing Cx

Component Level Testing

System Level Testing

Each utility system can have a testing hierarchy that is similar to this, much of which must be complete before the supporting system can be tested

9

Mostly Forced Response Testing

Transition to Natural Response Testing

Generally speaking, successful completion of  everything inside the red dotted line is required for system acceptance

Testing Hierarchy;More than Balancing Man Power

Commission Supporting 

Utility Systems

Verify Prestart Checks & Startups

Verify Control Wiring and Calibration

Verify Control Programming

Complete Equipment 

Safety Testing

Component Factory Startups

Component Startups

Sub‐assembly Factory Startups

Sub‐assembly Startups

Verify Safeties with Prime 

Mover Off‐line

Start‐up Prime Mover (Pump, 

Fan, etc.)

Test Component Controls

Test System Level Control Functionality

Test Building Level Control Functionality

Begin Normal Operations

Run Trend Analysis;  Fine Tune Systems

Seasonal and Warranty Testing

Begin Ongoing Cx

Component Level Testing

System Level Testing

Each utility system can have a testing hierarchy that is similar to this, much of which must be complete before the supporting system can be tested

10

Mostly Forced Response Testing

Transition to Natural Response Testing

Mostly Natural Response Testing

The Existing Building Perspective on Functional Testing

Operating Requirements

Heat Transfer Equipment Selections

Process Parameters

System Configuration

Owner’s Project

Requirements

Distribution Equipment Selections

Installation Documents

Assembled Building

Physical Configuration

Loads

Construction Project

FUNCTIONAL TESTING IN EXISTING BUILDINGS 11

The Existing Building Perspective on Functional Testing

Operating Requirements

Heat Transfer Equipment Selections

Process Parameters

System Configuration

Owner’s Project

Requirements

Distribution Equipment Selections

Installation Documents

Assembled Building

Physical Configuration

Loads

Construction Project

FUNCTIONAL TESTING IN EXISTING BUILDINGS 12

New Construction versus EBCx Testing

New Construction• Trying to prove design intent

• Demonstrate all elements of the system meet requirements

• Verification and quality assurance process

EBCx• Trying to understand design

intent• Focused on certain elements

of the system • Diagnostic and troubleshooting

process

FUNCTIONAL TESTING IN EXISTING BUILDINGS 13

Le Conte Hall

• UC Berkeley Physics Department Home

• 148,000 square feet• Four floors plus basement‒ Floors 1 and 2 - Classrooms

and research‒ Floors 3 and 4 - Offices, class

rooms, informal meeting space

• Interconnected with other physics department buildings

• MBCx program participant since 2009

• MBCx Best Practices Award winner for the 2009 program cycle

FUNCTIONAL TESTING IN EXISTING BUILDINGS 14

Le Conte Hall

• UC Berkeley Physics Department Home

• 148,000 square feet• Four floors plus basement‒ Floors 1 and 2 - Classrooms

and research‒ Floors 3 and 4 - Offices, class

rooms, informal meeting space

• Interconnected with other physics department buildings

• MBCx program participant since 2009

• MBCx Best Practices Award winner for the 2009 program cycle

It Takes a Team to SucceedLeft to Right

Anthony Vitan, Eleanor Crump, Julia Gee, Chuck Frost

FUNCTIONAL TESTING IN EXISTING BUILDINGS 15

Le Conte Hall

• UC Berkeley Physics Department Home

• 148,000 square feet• Four floors plus basement‒ Floors 1 and 2 - Classrooms

and research‒ Floors 3 and 4 - Offices, class

rooms, informal meeting space

• Interconnected with other physics department buildings

• MBCx program participant since 2009

• MBCx Best Practices Award winner for the 2009 program cycle

It Takes a Team to SucceedLeft to Right

Ancestors of David Sellers, Mark Porter, Ron Simens, Gary Kawabuchi and Mark Arney test a

new ideaFUNCTIONAL TESTING IN EXISTING BUILDINGS 16

2004 – 2007 Renovation– Seismic issues– Deferred maintenance– Reconfiguration– Restoration– MEP Update

FUNCTIONAL TESTING IN EXISTING BUILDINGS 17

HVAC Equipment40,000 cfm constant volume reheat, 100% outdoor air AHU for 1st and 2nd floor (basement location)

Exhaust fans associated with AHU 1

FUNCTIONAL TESTING IN EXISTING BUILDINGS 18

HVAC Equipment32,000 cfm constant volume reheat, economizer equipped AHU for 3rd and 4th floor

FUNCTIONAL TESTING IN EXISTING BUILDINGS 19

HVAC EquipmentSteam fired variable flow heating hot water system (basement location)

FUNCTIONAL TESTING IN EXISTING BUILDINGS 20

HVAC EquipmentAir cooled constant volume chilled water system

FUNCTIONAL TESTING IN EXISTING BUILDINGS 21

A Bit More Information on the Chilled Water System• 2 – 50 ton compressors• Compressors can unload to 25% of capacity• Compressors equipped with hot gas bypass• Relatively short piping circuit

FUNCTIONAL TESTING IN EXISTING BUILDINGS 22

Small Load + Large (Relatively) Chiller = Potential Problem

Internal Load, No Outdoor Air Cooling, 1‐5 Tons Maximum

100 Ton Chiller

Visit www.Av8rdas.wordpress.com for a larger copy of the system diagram; Link located on the right side of the home page under 03 – Materials from Classes and Presentations

FUNCTIONAL TESTING IN EXISTING BUILDINGS 23

100% Outdoor Air Load

Economizer Equipped Load

Large temperature supply temperature swings potentially a problem in terms of maintaining the desired conditions at the load

FUNCTIONAL TESTING IN EXISTING BUILDINGS 24

Five to six compressor cycles  per hour or more; a.k.a “short cycling”

FUNCTIONAL TESTING IN EXISTING BUILDINGS 25

The Problem with Short Cycling

FUNCTIONAL TESTING IN EXISTING BUILDINGS 26

Unresolved short cycling cost impacts‒ Less than optimal temperature control

• IEQ issues in hot and humid climates• Product quality issues• Ripple effects (other control processes become

unstable‒ Premature compressor or motor failure

• Unscheduled outage• Unscheduled cost - $20,000 - $40,000 each for

the 50 ton compressors on this project

The Problem with Short Cycling

FUNCTIONAL TESTING IN EXISTING BUILDINGS 27

The Research Load is Not the Only Small Load

100% Outdoor Air Load

Economizer Equipped Load

100 Ton Chiller

FUNCTIONAL TESTING IN EXISTING BUILDINGS 28

Non-integrated vs. Integrated

• Cooling coil load • Q = 4.5 x cfm x ∆h• Q = 4.5 x 30,000 x (25.4 –

22.8)• Q = 351,0000 Btu/hr• Q = 29.3 tons

• Cooling coil load • Q = 4.5 x cfm x ∆h• Q = 4.5 x 30,000 x (22.8 –

22.6)• Q = 27,0000 Btu/hr• Q = 2.3 tons

FUNCTIONAL TESTING IN EXISTING BUILDINGS 29

Non-integrated vs. Integrated

• Space Conditions• Space temperature = 72°F• Space RH = 50%• Space enthalpy = 26.4 Btu/lb

• Space Load (average cooling coil leaving conditions)

• Q = 4.5 x cfm x ∆h• Q = 4.5 x 30,000 x (26.4–

22.7)• Q = 499,500 Btu/hr• Q = 41.6 tons

FUNCTIONAL TESTING IN EXISTING BUILDINGS 30

Non-integrated vs. Integrated

LOADS

Space Coil – Non-Integrated Coil – IntegratedEconomizer Economizer

41.6 tons 29.3 tons 2.3 tons

FUNCTIONAL TESTING IN EXISTING BUILDINGS 31

Dealing with Short Cycling

• Infinite Capacity Modulation‒ No refrigeration compressor

can modulate over an infinite range on its own• Technology dependent

(reciprocating vs. centrifugal vs. scroll vs. screw vs. absorption)

• System dependent‒ Size of the piping

network‒ Relative sizes of the

prime movers

• False load‒ Serve a recirculating

constant volume reheat load

‒ Hot gas bypass

FUNCTIONAL TESTING IN EXISTING BUILDINGS 32

Dealing with Short Cycling

• Infinite Capacity Modulation‒ No refrigeration compressor

can modulate over an infinite range on its own• Technology dependent

(reciprocating vs. centrifugal vs. scroll vs. screw vs. absorption)

• System dependent‒ Size of the piping

network‒ Relative sizes of the

prime movers

• False load‒ Serve a recirculating

constant volume reheat load

‒ Hot gas bypass

FUNCTIONAL TESTING IN EXISTING BUILDINGS 33

Dealing with Short Cycling

• Infinite Capacity Modulation‒ No refrigeration compressor

can modulate over an infinite range on its own• Technology dependent

(reciprocating vs. centrifugal vs. scroll vs. screw vs. absorption)

• System dependent‒ Size of the piping

network‒ Relative sizes of the

prime movers

• False load‒ Serve a recirculating

constant volume reheat load

‒ Hot gas bypass• Lengthen the compressor run

cycles and off cycles‒ Anti-recycle timer‒ Thermal flywheels

FUNCTIONAL TESTING IN EXISTING BUILDINGS 34

Dealing with Short Cycling

• Infinite Capacity Modulation‒ No refrigeration compressor

can modulate over an infinite range on its own• Technology dependent

(reciprocating vs. centrifugal vs. scroll vs. screw vs. absorption)

• System dependent‒ Size of the piping

network‒ Relative sizes of the

prime movers

• False load‒ Serve a recirculating

constant volume reheat load

‒ Hot gas bypass• Lengthen the compressor run

cycles and off cycles‒ Anti-recycle timer‒ Thermal flywheels

FUNCTIONAL TESTING IN EXISTING BUILDINGS 35

Here’s a Question

How much of a thermal flywheel does the existing piping system represent?

FUNCTIONAL TESTING IN EXISTING BUILDINGS 36

Who Knows the Answer?

… the Building KnowsFUNCTIONAL TESTING IN EXISTING BUILDINGS 37

How Do We Ask The Building About It?

• We perform a functional test• Functional test components

‒ Statement of purpose‒ Instructions for using the

test form‒ Equipment requirements‒ Acceptance criteria‒ Precautions‒ Documentation‒ Procedure‒ Return to Normal and

Follow-upVisit www.Av8rdas.wordpress.com for a copy of the test; Link located on the right side of the home page under 03 – Materials from Classes and Presentations

FUNCTIONAL TESTING IN EXISTING BUILDINGS 38

Start With A Statement of Purpose

General Guidelines• Target the effort• Goal of the test• Underlying assumptions• Desired outcome‒ Tie to acceptance criteria

Our Statement of Purpose• Assess the thermal flywheel

represented by the existing piping system‒ Determine the minimum and

maximum chilled water temperatures that can be tolerated

‒ Quantify the thermal flywheel in terms of ton-hours

FUNCTIONAL TESTING IN EXISTING BUILDINGS 39

Test Form Instructions

General Guidelines• How should results be

documented?‒ Pass‒ Fail‒ Intermediate information‒ Comments

• Date and time stamps• Initials

Be clear; words have different meanings to different people

FUNCTIONAL TESTING IN EXISTING BUILDINGS 40

Test Form Instructions

General Guidelines• How should results be

documented?‒ Pass‒ Fail‒ Intermediate information‒ Comments

• Date and time stamps• Initials

Our Instructions• Review the procedure prior to

testing• Document the results in the

CACEA commissioning tool• Review decisions to deviate

from the plan with the team and note changes

• If the test is suspended prior to completion, run through the return to normal procedure

FUNCTIONAL TESTING IN EXISTING BUILDINGS 41

Required Equipment

General Guidelines• Standard tool set• Special tools‒ Unusual measurement

requirement‒ Critical accuracy requirement‒ Expediency

FUNCTIONAL TESTING IN EXISTING BUILDINGS 42

Required Equipment

General Guidelines• Standard tool set• Special tools‒ Unusual measurement

requirement‒ Critical accuracy requirement‒ Expediency

Our Equipment• Standard tool set

FUNCTIONAL TESTING IN EXISTING BUILDINGS 43

Acceptance Criteria

General Guidelines• Tied directly to the test’s stated

goals‒ Measured parameters‒ Documented conditions

• Clear and unambiguous terms• Special documentation

requirements‒ Picture‒ Witness signature‒ Control system report‒ Trend data

“Wait! Wait! Cancel that … I guess it says ‘helf.’”

FUNCTIONAL TESTING IN EXISTING BUILDINGS 44

Acceptance Criteria

General Guidelines• Tied directly to the test’s stated

goals‒ Measured parameters‒ Documented conditions

• Clear and unambiguous terms• Special documentation

requirements‒ Picture‒ Witness signature‒ Control system report‒ Trend data

Our Acceptance Criteria• Information only test; There

are no acceptance criteria‒ Acceptance criteria are less

common for EBCx testing‒ A similar test in a new

construction process may have acceptance criteria

FUNCTIONAL TESTING IN EXISTING BUILDINGS 45

Precautions

General Guidelines• Safety concerns

‒ Protection‒ Comfort level

• Risk management‒ Operational risks

• Cost vs. benefit• Likelihood of the problem

‒ Equipment damage‒ Temporary over-rides

HERMAN

“Arnold, will you please stand away from that on/off switch”

FUNCTIONAL TESTING IN EXISTING BUILDINGS 46

Precautions

General Guidelines• Safety concerns

‒ Protection‒ Comfort level

• Risk management‒ Operational risks

• Cost vs. benefit• Likelihood of the problem

‒ Equipment damage‒ Temporary over-rides

Our Precautions• Be careful working around

rotating machinery• Remember that there are other

things connected to the system, directly and indirectly when manipulating system parameters

• Exercise caution when driving chilled water temperatures to lower than normal ranges

FUNCTIONAL TESTING IN EXISTING BUILDINGS 47

Documentation

General Guidelines• What do you need to support

the test?‒ Submittals‒ Performance data‒ System diagrams‒ Calibration data‒ Factory start-up data

• What do you need to capture before starting?‒ Nameplate data‒ As found conditions

Our Documentation• Supporting information

‒ Located on the project web portal

‒ System diagram‒ Mechanical drawings‒ Control sequences ‒ Control shop drawings ‒ O&M information and

equipment submittal data• Capture before starting

‒ Current set points‒ Lab operating criteria

FUNCTIONAL TESTING IN EXISTING BUILDINGS 48

Prerequisites

General Guidelines• Conditions necessary to test

‒ Weather‒ Operating mode

• System readiness• People required for testing

‒ Owner‒ Contractor/Technicians‒ Code official‒ Factory representative

• Some items may tie back to precautions

Our Prerequisites• Low load condition required• Research and other building

functions can tolerate loss of chilled water

• Verify staff buy-in/available:‒ Lab‒ Building/campus

management‒ Physical plant

FUNCTIONAL TESTING IN EXISTING BUILDINGS 49

Preparation

General Guidelines• Team members in position

‒ Rehearsal• Monitoring equipment

‒ In position‒ Activated‒ Calibrated

• Coordinated with building functions

• As found conditions documented

FUNCTIONAL TESTING IN EXISTING BUILDINGS 50

Preparation

General Guidelines• Team members in position

‒ Rehearsal• Monitoring equipment

‒ In position‒ Activated‒ Calibrated

• Coordinated with building functions

• As found conditions documented

Our Preparation• Verify system flow rate has

been documented via pump test

• Verify logging is working for critical parameters

FUNCTIONAL TESTING IN EXISTING BUILDINGS 51

The Procedure

General Guidelines• Thinking it through ahead of

time is important• Be clear

20.

l

Perform a shut off test to verify the pump

Proceed as follows:and documenting the pump differential pressures.size by briefly closing the discharge valve and

Requirement DataInclude units Initials, Date

and Time

Completed

20.

Pump discharge pressureReturn discharge valve to original position.

Pump suction pressure

Document discharge valve positionStart the second pump to prevent a chiller safety shut down due to loss of flow.

document:Briefly close the discharge valve and

Perform a shut off test to verify the pump

Proceed as follows:and documenting the pump differential pressures.size by briefly closing the discharge valve and

Requirement DataInclude units Initials, Date

and Time

Completed

20.

l

Perform a shut off test to verify the pump

Proceed as follows:and documenting the pump differential pressures.size by briefly closing the discharge valve and

Requirement DataInclude units Initials, Date

and Time

Completed

FUNCTIONAL TESTING IN EXISTING BUILDINGS 52

The Procedure

General Guidelines• Thinking it through ahead of

time is important• Be clear• Include cross-references

‒ Multiple indications of results‒ Take more data than you

need

Our Procedure• Run the supply water

temperature as far down as possible with out nuisance safety trips

• Monitor the zone temperatures‒ When researchers indicate

they are concerned:• Document the cycle time• Document the chilled

water temperature• Run the chilled water

temperature back down and document the run cycle time

Visit www.Av8rdas.wordpress.com for a copy of the test; Link located on the right side of the home page under 03 – Materials from Classes and Presentations

FUNCTIONAL TESTING IN EXISTING BUILDINGS 53

Return To Normal and Follow up

General Guidelines• Don’t take off for home as soon as

you’ve finished the test!‒ Release manual over-rides‒ Return set points to normal‒ Wait to make sure things are

working properly!

FUNCTIONAL TESTING IN EXISTING BUILDINGS 54

Return To Normal and Follow up

General Guidelines• Don’t take off for home as soon as

you’ve finished the test!‒ Release manual over-rides‒ Return set points to normal‒ Wait to make sure things are

working properly!• Did all go as planned?

‒ Does the data make sense?‒ Is it telling you something that

requires immediate action?‒ Are your documentation needs

covered?• Issue preliminary reports

FUNCTIONAL TESTING IN EXISTING BUILDINGS 55

Return To Normal and Follow up

General Guidelines• Don’t take off for home as soon as

you’ve finished the test!‒ Release manual over-rides‒ Return set points to normal‒ Wait to make sure things are

working properly!• Did all go as planned?

‒ Does the data make sense?‒ Is it telling you something that

requires immediate action?‒ Are your documentation needs

covered?• Issue preliminary reports

Our Return to Normal• Release any manual over rides

and return set points to normal settings

• Retrieve and save trend data• Document the results on the web

portal• Notify contractors and UCB of any

issues that were discovered

FUNCTIONAL TESTING IN EXISTING BUILDINGS 56

Our Results

Trend data shows colder temperature than local indication during the “charge” cycle

Lab and building functions can handle an upper limit of 59°F for the flywheel

A 2 hour flywheel representing about 13 ton‐hours is 

possible

It will take one compressor about 10 minutes to recharge the flywheel

FUNCTIONAL TESTING IN EXISTING BUILDINGS 57

Automating Our Results

FUNCTIONAL TESTING IN EXISTING BUILDINGS 58

Opportunity 1 - Captured

FUNCTIONAL TESTING IN EXISTING BUILDINGS 59

Opportunity 2 - Identified

Whole building meter data indicates that the compressors tend to run at full load any time they run

FUNCTIONAL TESTING IN EXISTING BUILDINGS 60

Logger Data Confirms Suspicions

FUNCTIONAL TESTING IN EXISTING BUILDINGS 61

Unnecessary Hot Gas = Unrealized Savings

Good News• Flywheel cycle captures

26,900 kWh/$2,690 of savings via the MBCx project‒ Testing performed as part of

the general MBCx effort‒ Programming modified “on

the fly”• Additional savings potential

justifies a factory service call‒ Perform routine checks and

maintenance‒ Optimize set points‒ Optimize controls

Bad News• 11,404 kWh/$1,140 of savings

“left on the table

Visit www.Av8rdas.wordpress.com for the complete story

FUNCTIONAL TESTING IN EXISTING BUILDINGS 62

The Bottom Line A Warm, Low Occupancy DayAbout 10 minutes on and 

90 minutes off with only the lab load

1‐1/2 to 2 cycles per hour with the lab and lightly loaded AHU

Compressor capacity limited during the charge cycle

FUNCTIONAL TESTING IN EXISTING BUILDINGS 63

The Bottom Line A Warm, Low Occupancy Day

FUNCTIONAL TESTING IN EXISTING BUILDINGS 64

The Bottom Line A Warm, NormalOccupancy Day

System exits the flywheel cycle when conditions warrant normal operation

Unloading system “captures” the load and runs the compressor steady‐state against it

FUNCTIONAL TESTING IN EXISTING BUILDINGS 65

The Bottom Line A Warm, NormalOccupancy Day

Second compressor comes on line to supplement the lead compressor and also matches capacity to requirements

Lag compressor takes over as lead and continues to match the load with out short cycling

FUNCTIONAL TESTING IN EXISTING BUILDINGS 66

The Bottom Line A Warm, NormalOccupancy Day

Temperature swings are moderated compared to the pattern prior to the service call

FUNCTIONAL TESTING IN EXISTING BUILDINGS 67

How Can the Functional Testing Guide Help?

FUNCTIONAL TESTING IN EXISTING BUILDINGS 68

THANK YOUDavid Sellers, Senior Engineer Facility Dynamics Engineering NW Satellite OfficeDSellers@Facility Dynamics.comOffice: (503) 286-1494Cell: (503) 320-2630www.FacilityDynamics.comTechnical blog on WordPress at Av8rdas.Wordpress.com

SUPPLEMENTAL INFORMATIONIntegrated vs. Non-Integrated Economizer Operation

Non-Integrated is Different from Integrated

T

58°F Set Point

FUNCTIONAL TESTING IN EXISTING BUILDINGS 71

T

Non-Integrated

58°F Set Point

57°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 72

T

Non-Integrated

58°F Set Point

58°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 73

T

Non-Integrated

58°F Set Point

59°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 74

BAROMETRIC PRESSURE: 29.921 in. HGATMOSPHERIC PRESSURE: 14.696 psia

ALTITUDE: SEA LEVEL

0 5 10 15 20 25

30

35

40

45

50

50

55

55

ENTHALPY - BTU PER POUND OF DRY AIR

0

5

10

15

20

25

30

35

40

45

ENTHALP

Y - BTU P

ER POUND O

F DRY A

IR

SATURATION TE

MPERATURE - °

F

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

-5 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

105

110

115

120

DR

Y B

ULB

TE

MP

ER

ATU

RE

- °F

.001

.002

.003

.004

.005

.006

.007

.008

.009

.010

.011

.012

.013

.014

.015

.016

.017

.018

.019

.020

.021

.022

.023

.024

.025

15%

25%

2%

4%

6%

8% RELATIVE HUMIDITY

10

20

30

40

50

6070

8090

-50

05

510

10

15

15

20

20

25

25

30

30

35

35

40

40

45

45

50

50

55

55

60

60

65

65

70

70

75

75

80

8085

HU

MID

ITY

RA

TIO

- P

OU

ND

S M

OIS

TUR

E P

ER

PO

UN

D D

RY

AIR

0

1.0 1.0

-

2.04.08.0-8.0-4.0-2.0-1.0-0.5

-0.4-0.3-0.2-0.1

0.10.20.3

0.40.5

0.6

0.8

-2000-1000

0

500

1000

1500

2000

3000

5000

-

SENSIBLE HEAT QsTOTAL HEAT Qt

ENTHALPYHUMIDITY RATIO

hW

Space

Outdoor Air Mixed Air at MOA

Cooling Coil Discharge

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

BAROMETRIC PRESSURE: 29.921 in. HGATMOSPHERIC PRESSURE: 14.696 psia

ALTITUDE: SEA LEVEL

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

Visit www.Av8rdas.wordpress.com for a Resource List with links to free coil modeling software; Link from the right side of the opening page under 01 –Commissioning Resources

FUNCTIONAL TESTING IN EXISTING BUILDINGS 75

T

Integrated

58°F Set Point

57°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 76

T

Integrated

58°F Set Point

58°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 77

T

Integrated

58°F Set Point

59°F

FUNCTIONAL TESTING IN EXISTING BUILDINGS 78

BAROMETRIC PRESSURE: 29.921 in. HGATMOSPHERIC PRESSURE: 14.696 psia

ALTITUDE: SEA LEVEL

0 5 10 15 20 25

30

35

40

45

50

50

55

55

ENTHALPY - BTU PER POUND OF DRY AIR

0

5

10

15

20

25

30

35

40

45

ENTHALP

Y - BTU P

ER POUND O

F DRY A

IR

SATURATION TE

MPERATURE - °

F

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

-5 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

105

110

115

120

DR

Y B

ULB

TE

MP

ER

ATU

RE

- °F

.001

.002

.003

.004

.005

.006

.007

.008

.009

.010

.011

.012

.013

.014

.015

.016

.017

.018

.019

.020

.021

.022

.023

.024

.025

15%

25%

2%

4%

6%

8% RELATIVE HUMIDITY

10

20

30

40

50

6070

8090

-50

05

510

10

15

15

20

20

25

25

30

30

35

35

40

40

45

45

50

50

55

55

60

60

65

65

70

70

75

75

80

8085

HU

MID

ITY

RA

TIO

- P

OU

ND

S M

OIS

TUR

E P

ER

PO

UN

D D

RY

AIR

0

1.0 1.0

-

2.04.08.0-8.0-4.0-2.0-1.0-0.5

-0.4-0.3-0.2-0.1

0.10.20.3

0.40.5

0.6

0.8

-2000-1000

0

500

1000

1500

2000

3000

5000

-

SENSIBLE HEAT QsTOTAL HEAT Qt

ENTHALPYHUMIDITY RATIO

hW

Space

Outdoor Air

Cooling Coil Discharge

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

BAROMETRIC PRESSURE: 29.921 in. HGATMOSPHERIC PRESSURE: 14.696 psia

ALTITUDE: SEA LEVEL

Chart by: AKTON PSYCHROMETRICS, www.aktonassoc.com

FUNCTIONAL TESTING IN EXISTING BUILDINGS 79