John R. Kasich, Jerry Wray,
Ohio Governor ODOT Director
FRA-71-9.62/9.71Project Matchmaker Event
Brian Hupp, P.E., District Construction Engineer
April 18, 2017
To provide easy movement of
people and goods from place
to place, we will:__________________________________
Take care of what we have;_________________________________
Make our system work better;_________________________________
Improve safety;_________________________________
Enhance capacity.
ODOT’S M ISSION
3
• Eight Counties
• 4,921 miles of roads
• 1,557 Bridges
• 16 Garages/Outposts
• Operating Budget
approx. $52 million
• CAPITAL PROGRAM
• 83 Construction Projects
• 390 Million Dollars
District 6
John R. Kasich, Jerry Wray,
Ohio Governor ODOT Director
Steve Fellenger, P.E. ,Project Manager
Jeff Holbrook, P.E. ,Construction Area Engineer
Andrew Opsitnik, P.E. ,Construction Project Engineer
FRA-71-9.62/9.71 Project Matchmaker
6
Project Overview
• Purpose: Major Rehabilitation of Pavement. Additional Lane Along I-71 in Both Directions from Stringtown Rd. to 70/71/315 Interchange.
ESTIMATED COST$113 Million
FRA-71-9.62/9.71 Project Matchmaker
7
Project Overview
• Perform full depth pavement replacement
• Construction of additional lane in the median, in both directions
• Rehabilitate and widen Three (3) pair of mainline structures and Replace Three (3) other structures
• One (1) new Structure
• Construct two (2) noise barriers
• Floodwall work near Greenlawn Interchange
• Upgrade all highway safety features including guardrail, drainage, lighting, and signs.
WORK INCLUDES:
FRA-71-9.62/9.71 Project Matchmaker
8
Schedule
• Sale Date:06/29/17
• Award Date: 07/10/17
• Construction Start: 08/14/17
• Construction End: 06/30/20
FRA-71-9.62/9.71 Project Matchmaker
9
Construction Work Types
Construction Work TypesCode Description Code Description
1 Clearing and Grubbing 29 Structure Repairs
4 Roadway Excavation & Embankment Construction 34 Earth Retaining Structures
7 Soil Stabilization 35 Drainage (culverts, misc)
8 Temporary Soil Erosion & Sediment Control 36 Guardrail/Attenuators
9 Aggregate Bases 37 Fence
10 Flexible Paving 38 Misc Concrete
12 Rigid Paving 39 Maintenance of Traffic
13 Pavement Planing, Milling, Scarification 40 Waterproofing
15 Sawing 41 Raised Pavement Markers
16 Flexible Replacement 42 Signing
19 Structure Removal 43 Highway Lighting
20 Level 1 Bridge 44 Traffic Signals - Standard
21 Level 2 Bridge 45 Pavement Markings
23 Reinforcing Steel 46 Landscaping
24 Structural Steel Erection 51 Micro Tunneling
25 Stud Welding 53 Piling
26 Structural Steel Painting 55 & 56 Fiber Optic Cable Installation, Splicing, Termination and Testing
27 Expansion & Contraction Joints, Joint Sealers, Bearing Devices 57 Sealing of Concrete Surfaces with Epoxy or Non-Epoxy Sealers
10
Roadway & Pavement Work Type
• 304 Aggregate Base: 91,000 CY
• 302 Asphalt: 132,000 CY
• 442 Inter. Asphalt: 24,000 CY
• 442 & 806 Surface Asphalt: 20,000 CY
• 452 Concrete Pavement: 31,000 CY
Roadway & Pavement WorkEstimated Cost $39.6 M
FRA-71-9.62/9.71 Project Matchmaker
11
Structures Work Type
• Deck replacement and widening: 3 pairs of mainline bridges
• Replace 3 Structures
• WB I-270 to SB I-71 – Ramp B – New Structure
Structures WorkEstimated Cost $31 M
FRA-71-9.62/9.71 Project Matchmaker
12
Maintenance of Traffic Work Type
• 614 Work Zone and Crossover Lighting
• 615 Temporary Pavement: 130,000 SY
• 622 Port. Concrete Barrier: 273,000 LF
Maintenance of Traffic WorkEstimated Cost $12.6 M
FRA-71-9.62/9.71 Project Matchmaker
13
Drainage Work Type
• 605 Underdrains: 310,000 LF
• Misc. 8 in. to 42 in. drainage conduit: 23,000 FT
Drainage WorkEstimated Cost $9.5 M
FRA-71-9.62/9.71 Project Matchmaker
14
Retaining Walls, Noise Barriers and Floodwall Work Types
• Retaining walls
• Noise Barriers west side of I-71 near White Road and Dyer Road
• US Army Corps of Engineers 408 Floodwall
Retaining Walls, Noise Barriers and Floodwall WorkEstimated Cost $5.6 M
FRA-71-9.62/9.71 Project Matchmaker
15
Traffic Control, Lighting & Traffic Surveillance Work Types
• Misc. overhead and ground mounted signs
• LED high mast and low mast lighting
• 804 Fiber Optic cable
Traffic Control, Lighting & Traffic Surveillance Work
Estimated Cost $4.8 M
FRA-71-9.62/9.71 Project Matchmaker
16
Disadvantage Business
Enterprise (DBE)
DBE Goal 11%
• Contains the Proposal Note 013 - Disadvantaged Business Enterprise (DBE) Utilization Plan and Good Faith Efforts, updated 01/20/2017
• All bidders shall submit a DBE Utilization Plan at the time of bid, setting forth specific information demonstrating how the bidder will achieve the DBE goal.
• DBE Certified Firms: