final group mfh spr 3 21 13.pptx [read-only] · 2018-07-09 · 5 liquidated damages enforceable...
Post on 12-Aug-2020
1 Views
Preview:
TRANSCRIPT
1
WELCOMEMultifamily Housing Seminar: Trends & Topics for Developers
and Owners
March 21, 2013
© Husch Blackwell LLP
Multi-Family ConstructionPlanning and Implementation
By: Richard Walters
2
Planning / Due Diligence
Get Engaged in Planning / Proactive Role
– City / County ARC Meetings
• Planning Department
• Building Services Department
No Surprises
Due Diligence
Zoning / Utilities / Property Tax Levies
Contractor Selection Qualifications / Multi-Family Construction Experience Delay Claims Payment and Performance bond - Mitigation strategy
– Lender Requirement– Bond underwriter will also closely examine the financial strength of the contractor
before underwriting the project Financial Strength
– Contractor Financial Statements Key Risks of This Stage: Selecting a contractor that is unqualified or does not have the financial
stability to deliver the project and support its warranty obligations A financially weak contractor may result in suppliers and subcontractors not
getting paid. The impact to the owner is significant:– Liens against the building may prevent occupancy– Construction delays until subcontractors and suppliers are paid– Reluctance or refusal by professionals to work on the project– Lost discounts and credits
3
Competitive Bid / Negotiated Contract
Competitive Bidding– More risk to owner– More risk for contractor– Sets up adversarial relationship among contractor, architect/engineer and owner– High charges for change orders– No contractor involvement during planning stage– Assumes that the quality workmanship will be the same with all contractors– Price is the deciding factor
Negotiated Contract– Less risk to owner– Less risk for contractor– Sets up "TEAM" relationship among contractor, architect/engineer and owner– Emphasizes quality– Reasonable charges for change orders– Heavy involvement of contractor during planning– Requires good conceptual estimator– Emphasizes service– Considers experience, quality, reliability, on-time completion and creativity
Contract Documentation
Contract Documents
– AIA
– Assumptions / Qualifications
Schedule of Values
Contingency
– Owner Approval
– Limit use to errors in contract documents (plans) and unforeseen conditions
4
Guaranteed Maximum Price (GMP) Contracts
Benefits:– Establishes a not-to-exceed price
• Costs that exceed the GMP are the responsibility of the Contractor– Budgetary Certainty and the benefit of cost savings
• Benefit from value added engineering, price reductions, and well managed procurement
– Enables the owner to select and contract with the contractor while still designing the facility
Burdens:– Requires proper administration and oversight
Commonly executed in 2 parts– Initial Contract – Retain the services of a contractor acting as a design phase GC
• Provides cost estimating, alternative construction methods and materials• Fee is generally lump-sum (preconstruction services)
– Second Contract (Addendum) – Establishes the GMP• Cost Breakdown
Shared Savings
AIA Contract Forms do not provide language for Shared Savings or Savings Split
– Owner must provide language
Cost of the Finished Project and GMP
– Shared on a percentage basis
Accountability / Documentation
– Audit Rights
5
Liquidated Damages
Enforceable liquidated damages generally have 5 elements (may vary from state to state)– 5 elements:
• Actual damages must be difficult to quantify.
• The amount must be liquidated (i.e., agreed on and set in advance)
• The amount must be reasonable
• They must be compensation, not a penalty
• They must be exclusive (i.e., the only remedy available)
Substantial Completion and Final Completion• Impact on Occupancy
Construction Implementation / Completion
Disbursement
– Title Company
– Mechanic’s Lien Endorsement
Change Orders
– Impact on construction and loan budgets
Work In Process / Schedule of Values
Warranty / Punchlist / Close-Out Documentation
6
Affordable Multi-Family Construction
Significance of construction budget Affordable Multi-Family Construction Contract Requirements (MHDC) Prevailing Wage
– MHDC’s 2013 Qualified Allocation Plan requires that all MHDC financed projects pay at least the Federal prevailing wage
– Prevailing wage will apply to any person performing construction labor on the construction site
– Certified Payrolls MBE / WBE Requirements
– Initiative to encourage MHDC funded projects to utilize businesses certified as a Minority Business Enterprise (MBE) and as a Woman Business Enterprise (WBE)
– Minimum participation goals of 10% for MBE companies 5% for WBE companies for both hard and soft project costs
– Preference in funding – Evidence of MBE/WBE participation and certification for soft cost firms are required at
application. Evidence of MBE and WBE proposals and certifications for hard cost firms will be required as a part of the firm submission
Bank Financing for Multifamily Projects
How does a deal get done?
By: Kent Lammers
7
Stage 1‐‐Plan Vs Dream
• Financials
– Personal
– Business
– Debt Schedules
• Budgets
• Plans
Stage 2—Bank Goals and Analysis
• Construction‐‐Bank “insures” completion and/or credits issued– Does it make sense?
• Cost/unit
• Market Vacancy
– Cast of Characters (usual suspects)• CPA
• Attorney
• GC—Bonding/GMP
• Management Company
• Investors
8
Stage 2 Cont—Developer Analysis
• Experience
• Current construction/lease up on other projects
• Completed projects performance
– Underperforming
– Strong Performers—wrap to new project initially?
• Global Analysis
– Personal debt, business debt schedule
Stage 2 Cont Project Analysis
• Market Study
– AMI Mixes—30%, 60% AMI
– Enhanced Units
– Vacancy—market and tax credit
– Location
• Competition
– Age
– Projected Rents—can you get it?
9
Stage 2 Perm Debt Analysis
• Debt/Door
• Sensitivity Analysis
– Rate Shocking
– Break Evens
• Interest Rates
• Vacancy
• Rental Rates
Stage 2 Cont Equity
• Investor
– Cash
– Letters of Credit‐‐Issuer
– Timing vs Construction Needs vs Debt
• Developer
– Cash
– Cash flowing projects
10
Stage 3—Construction
• On Time
• On Budget
• Change Orders
• Inspections
• Draws
Misc
• Phasing
• Amenities Packages
• Guarantor Release
11
Conclusion
• Communication
– “Much unhappiness has come into the world because of bewilderment and things left unsaid.”
– ― Dostoevsky
Gershman
Permanent Financing: Navigating the Waters
By: Ron Weis
12
Gershman
Understand what has happened
Gershman
Prior to 2007 ‐ 2008• Multiple sources for permanent financing• Rates 6.0% ‐ 7.0%• Aggressive underwriting, quick turnarounds• Financing chasing deals• New construction at a high pace putting pressure on
occupancies
After • Wall Street CMBS go away. Investors are burnt by
defaults and delinquencies. • Strong regulatory response: Fannie & Freddie troubles• Underwriting so tight that lending dramatically slows• New construction almost ceases• Deals chasing scarce financing: supply & demand
13
Gershman
Results of slow economic recovery• FHA and GSEs Fannie Mae & Freddie Mac
become the dominant sources• Rates drop as the Fed drops rates, 10 year T‐
note rate drops as the market seeks security. CMBS make slow progress with much tighter underwriting as investors seek higher yield
• Tight, conservative underwriting, likely to last • Cap rates drop in response to low rates and
demand for existing product: rent increases and high occupancies
• New construction returns as occupancies rise. Occupancies and low rates attract equity.
• Risk mitigation becomes key to successful underwriting
Gershman
Getting Permanent FinancingIdentify possible perceived risks
• Rents & expenses vs. the market area• Physical condition/property age• Handicap accessibility • Leverage• Borrower
14
Gershman
Getting Permanent Financing“Risk Mitigation”
• Rents & expenses vs. the market area› Underwrite to market rents or lower› Expenses based upon market, not historical› LTV and debt service coverage above the minimum› Change in management agent
• Physical condition/age› Required repairs & escrows for repairs› Reserves› Shorter term› Renovations & updates
• Handicap accessibility › Required repairs & escrows for repairs› Reserves
Gershman
Borrower• Experience
› Partner with experience› Management agent with experience
• Financial strength› REO/Debt schedule & demonstrating that
maturing debt or interest rate resets will be accommodated
› Partner with strength• Financial & operational history
› Tell the story with supporting documentation
› Independent & strong management agent› Demonstrate that things have changed› Have a plan that is being implemented› Partner with strength
15
Gershman
Trump Cards
• Equity
• Cash
Gershman Getting ready to finance
“Think like a lender”
• Analyze strengths & weaknesses• Document the strengths• Document and be prepared to mitigate
weaknesses• Ask questions, ask for help• Be ready to prepare a detailed package.• Be over prepared – anticipate all the
questions, even if you think the answers are self‐evident
16
© Husch Blackwell LLP
By: S. Shawn Whitney
• Low Income Housing Tax Credit • Section 42 of the Internal Revenue Code
• Chapter 135 of the Missouri Revised Statutes
• Credit is a dollar for dollar tax reduction on Federal and State Income Tax
• Credit Amount is based upon cost of constructing or rehabilitating housing developments
• Objective: To provide investor equity to lower/eliminate debt service to allow for lower rents
• Projects Subject to MHDC Compliance Requirements
17
• Syndication is the process by which the owner of an affordable housing building brings an equity investor into the ownership structure to allow the investor to claim the credits in exchange for providing equity to the project.
• Investors become owners in the property as members/limited partners of the ownership entity
• Investors receive other economic and tax benefits from ownership
• Investors require a certain amount of control, disclosure/reporting, and removal rights.
• Project Team (important to have experienced architect, general contractor, accountant, property manager, and lawyer)
• Investor will require a loan commitment
• Investor will perform significant due diligence on the developer and underlying real estate (personal financials, environmental, title, zoning, etc.)
18
• Economic Benefits – to be evidenced by CPA prepared projections. Investors consider:– Amount of credits
– Depreciation (losses passed through to the investor)
– Cash flow
– Location of Project
• Community Reinvestment Act (banks receive credit for participation CRA developments)
• Higher equity pricing for CRA developments (20% to 30%)
• Difficult to Developer Areas (DDAs) and Qualified Census Tracts (QCTs) areas where the need is greatest for affordable housing, but which can be the most difficult to develop.
• distressed areas, the LIHTC can be claimed for 130% (instead of the normal 100%) of the project’s total cost excluding land costs.
• Project Feasibility– Experienced developer (built and managed other LIHTC
projects)
– Strong guarantors
– Strong project (low loan to value/no debt)
– Strong market (need evidenced by market study)
• Searching for Investors– Relationships are key components
• Investors with working knowledge of development/key team members allows for better deal terms and less fact finding.
– Hire professionals with strong relationships within equity markets
– Consider investor reputation before selection (past deals/ due diligence/ integrity)
19
• Key terms to negotiate within Investor Letter of Intent
– Pricing (but not always most important)
– Pay in schedule - Time value of money (discount future payment by interest rate paid on construction loan)
– Annual asset management fee/ Preferred Return
– Costs (whose paying investors costs for due diligence and professional fees)
– Kick out clause in LOI
– Reserves (how much and when reserves can be used)
– Income allocation provisions (whose taking recharacterization of income risk)
– Tax opinion
– Adjusters
– Cash flow waterfall
– Guarantees (limit duration and amount)
– Exit strategies (Put & Call provisions)
• Abatements – Great for Market Rate and LIHTC– Two main considerations when applying for an abatement:
• Type of Abatement to pursue
• Location of project
• Two most common types of abatement:– Chapter 99
– Chapter 353
• The purpose of both abatements is to facilitate eradication of blight in a community by encouraging redevelopment by private enterprise.
20
• Offers tax abatement for 10 years – Receive a full tax abatement on the increased value of the real
property and improvements
• Any person may apply for Chapter 99 abatement
• Must demonstrate that the property is blighted under the standards for a Chapter 99 tax abatement and submit a redevelopment plan for the property
• Offers tax abatement for 25 years– First 10 years: Receive a full tax abatement on the value of the improvements
– Last 15 years: The land and improvements are assessed at 50% of their true value
• Must prove property is blighted under the standards for a Chapter 353 tax abatement and submit a redevelopment plan for the property
• Must demonstrate the project is not financially viable without the abatement (referred to as the “but for” test)
– This typically requires submitting a pro forma and internal rate of return analysis with the application.
• Also must submit a tax impact analysis with the application showing how the taxing districts will be impacted with and without the abatement
• Typically longer and more expensive process than Chapter 99 abatement since the application is more comprehensive and the components take more time and to prepare
21
• Several parts of Springfield are already blighted under Chapter 99. Some of these areas have redevelopment plans in place and some do not.
• If you redevelop in a blighted area and your project conforms to the redevelopment plan in place, you will only need to submit a Chapter 99 tax abatement application to the LCRA for approval to receive tax abatement on your project.
• If you redevelop in a blighted area that does not have a redevelopment plan, you will need to submit a redevelopment plan for approval that is specific to your proposed redevelopment and, once the plan is approved, apply for chapter 99 tax abatement under the plan.
• Both of these options will allow for considerable cost savings since it eliminates the need to demonstrate that the area is blighted.
– City Grants/Soft loans
– HOME Funds
22
S. Shawn Whitney901 St. Louis St., Suite 1800
Springfield, MO 65806Direct: (417) 268-4030Fax: (417) 268-4040
Email: shawn.whitney@huschblackwell.com
An Overview of Value Trends and Appraisal Issues in Multi-Housing
Presented by
Stephen Cosby, MAI, MRICSManaging DirectorCBRE Valuation & Advisory Services
23
CBRE | Page 45
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
United States Valuation & Advisory Services
9 Regions in USA 60 offices Over 400 Appraisal Professionals Nationwide
Pacific Northwest
NorthernCalifornia
SouthernCalifornia
Intermountain
SouthCentral Southeast
North Central
Northeast
New England
CBRE | Page 46
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Line of Services
Appraisal ServicesAppraisal Services
Assessment & Consulting ServicesAssessment & Consulting Services
Financial & Tax Reporting ServicesFinancial & Tax Reporting Services
24
CBRE | Page 47
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Clients and Reporting
Our Clients• Investment and commercial banks• Corporations• Pension funds• Investors• REITs• Government agencies
All CBRE reporting conforms to• The Appraisal Institute• USPAP• FIRREA• FNMA/FHLMC• International Standards as applicable
Our ClientsOur Clients
All CBRE reporting conforms toAll CBRE reporting conforms to
CBRE | Page 48
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
CBRE VAS Multi-Housing Assignments
25
CBRE | Page 49
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
CBRE VAS Multi-Housing Contacts
CBRE | Page 50
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
The Health of the Apartment Market
26
CBRE | Page 51
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
The Health of the Apartment Market
Source: Reis
CBRE | Page 52
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Effect of Class on Rent
Source: Reis
27
CBRE | Page 53
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Effect of Class on Vacancy
Source: Reis
CBRE | Page 54
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
National Trends – 2001-Present - Apartments
Source: Real Capital Analytics
28
CBRE | Page 55
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
What is a “Cap Rate”
Basic Formulas for Direct Capitalization
Where:• I = Income (NOI)• V = Value• R= Rate• F = Factor
I = R x V R = I / V V = I / R
CBRE | Page 56
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Band of Investment
BAND OF INVESTMENTMortgage Interest Rate 4.25%Mortgage Term (Amortization Period) 30 YearsMortgage Ratio (Loan-to-Value) 75%Mortgage Constant 0.05903Equity Dividend Rate (EDR) 10%
Mortgage Requirement 75% x 0.05903 = 0.04427Equity Requirement 25% x 0.10000 = 0.02500
100% 0.06927
Indicated OAR: 6.90%Compiled by: CBRE
29
CBRE | Page 57
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Agency 10-Year Mortgage Rates
CBRE | Page 58
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Avg. Cap Rate – Garden Apartments
Source: Real Capital Analytics/St. Louis Federal Reserve Bank
30
CBRE | Page 59
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Valuation - LIHTC
VALUATION Total Per Unit
Land Value $85,000 $1,771
Cost Approach - Conventional $1,900,000 $39,583
Sales Comparison Approach - Conventional $2,200,000 $45,833
Income Capitalization Approach - Conventional $1,900,000 $39,583
Cost Approach - LIHTC $1,150,000 $23,958
Income Capitalization Approach - LIHTC $1,150,000 $23,958
Insurable Value $2,750,000 $57,292
CONCLUDED MARKET VALUE
Appraisal Premise Interest Appraised Value
As Is - Conventional Fee Simple Estate $1,900,000
As Is - LIHTC Fee Simple Estate $1,150,000
Compiled by CBRE
Date of Value
January 4, 2013
January 4, 2013
CBRE | Page 60
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Federal LIHTC Sales
31
CBRE | Page 61
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Valuation – HAP Contract
VALUATION - Market Total Per Unit
Land Value $550,000 $3,986
Market Value As Is On February 19, 2013Cost Approach $1,800,000 $13,043
Sales Comparison Approach $1,850,000 $13,406
Income Capitalization Approach $1,800,000 $13,043
Market Value As Stabilized On November 19, 2013Cost Approach $3,950,000 $28,623
Sales Comparison Approach $4,000,000 $28,986
Income Capitalization Approach $3,950,000 $28,623
Insurable Value (Replacement Cost) $6,200,000 $44,928
CONCLUDED MARKET VALUE
Appraisal Premise Interest Appraised Value
As Is - Market Fee Simple Estate $1,800,000
As Stabilized - Market Fee Simple Estate $3,950,000
As Is - HAP Contract/ Restricted Rents Fee Simple Estate $3,250,000
As Stabilized - HAP Contract/ Restricted Rents Fee Simple Estate $5,400,000
Compiled by CBRE
November 19, 2013
Date of Value
February 19, 2013
November 19, 2013
February 19, 2013
CBRE | Page 62
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Student Housing
Because of rapid enrollment growth at many universities and colleges along with tight capital budgets, on-campus housing has been outgrown.
Student housing has filled this gap with a variety of lease-by-the-bed products.
Student housing is characterized by a “true” cyclical market – due to 9 or 10 month university calendars.
Student housing complexes are typically priced with capitalization rates 50-100 basis points higher than otherwise equivalent traditional apartment complexes
71 properties are known to be in development across the US at present totaling nearly 40,000 beds• Two complexes, totaling 1,626 beds, are under
development at Columbia, MO
32
CBRE | Page 63
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Student Housing
According to ARA, 2012 was a record year for sales of student housing complexes. • Based on transactions with a sale price of $5MM
and above, total sales volume was $3.7 Billion for 83 properties.
• This is higher than the previous peak in 2008 of approximately $2.8 Billion for 64 properties.
The average cap rate for stabilized student housing complex sales in 2012 was 6.76%.• In late 2012, MSU purchased The Monroe, a 122
bed student housing complex built in 2011 for $8,000,000 – which equates to a 6.75% OAR based on proforma income.
CBRE | Page 64
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Student Housing in Springfield, MO
SUMMARY OF COMPARABLE APARTMENT RENTALS
Comp. No. Property Name Location
Year Built Occ.
No. Units
No. Bedrooms
Avg. Rent Per Unit
Avg. Rent Per Bed
1 2012 100% 48 96 $1,106 $553
2 2012 85% 50 200 $2,300 $575
3 2012 98% 32 86 $1,519 $565
4 2012 81% 38 115 $1,713 $566
5 2010 100% 12 48 $2,040 $510
6 2010 95% 114 208 $878 $481
7 2010 100% 8 32 $1,800 $450
Compiled by CBRE
Beacon Park 415 East Monroe,Springfield, MO
The Jefferson
Beacon Commons 525 East Madison,Springfield, MO
835 South Jefferson,Springfield, MO
815 South Kimbrough,Springfield, MO
701 East Elm,Springfield, MO
Deep Elm
Bear Village
Walnut Quads 450 East Walnut,Springfield, MO
1744 West Catalpa,Springfield, MO
Eko Park
33
CBRE | Page 65
CB
RE
Val
uat
ion
& A
dvi
sory
Ser
vice
s
Ov
erv
iew
of
Val
ue
Tre
nd
s an
d A
pp
rais
al I
ssu
es in
Mu
lti-
Ho
usi
ng
Student Housing at University of Arkansas
Thank you
Stephen Cosby, MAI, MRICS | Managing DirectorCBRE | Valuation & Advisory Services438 E Millsap Ste 204 | Fayetteville, AR 72703425 W Capitol 15th Floor | Little Rock, AR 72201T +1 479 4427401 x. 3 | F +1 479 4427806
steve.cosby@cbre.com
top related